RMCS Flashcards

1
Q

Conditions which require emergency boration:

4 reasons

A
  1. Failure of more than one RCCS to fully insert following reactor trip or shutdown.
  2. Uncontrolled cooldown with the reactor shutdown.
  3. Inadequate shutdown margin
  4. Cb<2000ppm in the canal, cavity, or RCS or 1/M plot indicates approach to criticality after fuel movement ceased.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Sources of Emergency boration per BOA pri-2

A
  1. Boric acid transfer pump through 8104 and flow >30gpm.
  2. Boric acid transfer pump with RMCS in manual -or- Borate with greater than 30 gpm flow. (7000 ppm)
  3. RWST through CV112D and CV112E via CV pumps:
    • must maximize charging
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BA flow deviation alarm:

A

BA flow +- 1.0 gpm
Automatic actions:
1CV110B Closes if CS in auto
1CV111B closes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

PW flow deviation:

A

PW flow +- 8 gpm
Automatic actions:
In all modes EXCEPT BORATE and after a 30 second time delay. CV110B and CV111B close.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

0A starts on _____RCS and 0B starts on _____RCS

A

Unit 1 ; Unit 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Design basis of RMCS system:

A
  1. Regulate boron concentration in the RCS to control slow reactivity changes.
  2. Amount of boric acid stored is capable of borating the RCS to cold shutdown with the most reactive rod stuck out.
  3. Rate of boration is sufficient to shutdown the reactor to 1% delta K/K with rods out in 93 minutes from full power.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Capacity of one boric acid transfer pump basis:

A

One BA transfer pump sufficient to provide 1% Shutdown Margin (SDM) from 100% RTP, with All Rods Out (ARO) in 90 min. with 55 gpm boric acid flow. 30 gpm will RAISE SDM 1% in 74 min.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CV111A supplies ____ to the blender. CV110A supplies ____ to the blender.
CV110B sends the blender to the _____of the VCT. CV111B sends the blender to the _____ of the VCT.

A

PW
Boric acid
Bottom
Top

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Immediate operator actions deviation alarms:

A
  1. Determine cause
  2. Evaluate reactivity change
  3. If cause not determined:
    a. Verify auto actions
    b. Place makeup control switch to off
  4. Set controller FK111A to <=80gpm if in dilute mode.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In auto, the blended flow rate is _____gpm. In all other RMCS modes, the controller setpoint varies flow.

A

120

0-160 range

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Totalizers stop the _____ and _____ flow whenever the preset value is reached.

A

PW and boric acid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

With mode select switch in manual, the two valves ____ and ____ do not auto open. The logic assumes makeup is to the _____.

A

CV110B and CV111B; RWST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

There is a time limit on ________ of ______ hour(s). This minimizes _______depletion.

A

Alt. Dilute; 1; hydrogen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The oxygen content in the VCT must not exceed _____% by volume when hydrogen also present.

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

There are 2 _____ gallon boric acid tanks and 2 _____ gallon PW tanks.

A

48,000; 500,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

F0111 looks at both ______ and F0110 looks at_____.

A

boric acid and water flow, throttles water flow;

boric acid flow rate only

17
Q

CV110a, b and CV 111 a, b fail ____ on loss of instrument air.

A

CV110A Fails open

CV110B, CV111A, CV111B all fail closed

18
Q

For borated water sources to be operable when operating,

temperature must be______, boric acid concentration must be ________, and tank level must be ______.

A

> =65F
=7000 ppm
=40%

19
Q

What indications does the operator have on the pm05J concerning RMCS?

A
Emerg boration flow
BA and total flow recorder
BA storage tank level
BA storage tank temperature
VCT level
20
Q

Borated water sources shutdown requires either of RWST or BAST. RWST temperature must be ____. BAST must be _____, ______, and ______. RWST must be____, _____, and ____.

A

> =35F
=65F, >=7000ppm, >=12%
2300-2500ppm, >=9%, 35F only applies when outside air <35F

21
Q

How to determine required flowrate of boric acid if given boron of the rcs:

A

120Brcs/Bbat

22
Q

Boric acid tank pumps are powered from a _____ power supply

A

non-esf, 133x/233x

23
Q

LCO 3.3.9 BPDS LCO

A

3.3 INSTRUMENTATION
3.3.9 Boron Dilution Protection System (BDPS)
LCO 3.3.9 BDPS shall be OPERABLE with:
a. One or more reactor coolant pump(s) in operation;
b. Each Reactor Coolant System (RCS) loop isolation valve
open; and
c. The BDPS instrumentation in Table 3.3.9-1 OPERABLE.
—————————-NOTE—————————-
The Boron Dilution Alert Alarm may be bypassed in MODE 3
during reactor startup.
————————————————————
APPLICABILITY: MODES 3, 4, and 5.

24
Q

Boric acid flow controller range is up to

A

40 gpm