Tech Spec Notes - .5 Flashcards

1
Q

If LCO is restored prior to expiration of the specified time interval, do you have to complete the action?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If there is no Action for an LCO not being met, what actions should be taken?

A

within ONE HOUR to place the unit in an opcon in which the spec does not apply, by placing it, as applicable, in: (N/A in opcon 4 or 5)
1) Startup w/in the next 6 hours.
2) Hot Shutdown w/in the following 6 hours.
3) Cold Shutdown w/in the subsequent 24 hours.
That’s 1+6+6+24 = 37 hours total

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

If LCO not met, you can still enter an OPCON if either:

A

a) The Actions you will be entering into allow operation for an unlimited amount of time.
b) A risk assessment was performed.
c) When an allowance is stated in the individual spec.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If a piece of equipment is INOP, can it be returned to service to test it?

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long do you get if a single or multiple snubbers are broken?

A

you get 72 hrs (1 train) or 12 hrs (more than one train) to fix it before the system is inop.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What happens to the equipment if it fails a surveillance?

A

it is INOP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What happens if you do not perform a surveillance on time? Can you delay the surveillance past the due date? if so, then how long?

A

It is INOP
A surveillance can be extended up to 25% longer than its periodicity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How long do you have to perform a surveillance that was accidentally skipped?

A

The greater of 24 hrs or the frequency that it is done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you enter another opcon if you have not completed all surveillances? Is there an exception?

A

No, exception is 3.0.4.
This does not apply if you need to shutdown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Describe the operability criteria for “offsite power sources”.

A

500Kv Bus Sections 1 & 2 energized by two offsite sources (Red Lion 5015, New Freedom 5023, or Salem X-Tie 5037). Two feeds (10X and 20X) into a split 13.8Kv Yard, with each feed supplying power to an energized separate Station Service Transformer (AX501 and BX501). An independent offsite feed is considered available to the safety related distribution system IF all four of the 1E infeed breakers are OPERABLE.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the basis for the Torus water level requirements?

A

ECCS Systems (3.5.3) – The limit on suppression chamber in water volume ensures that sufficient water is available to permit recirculation cooling flow to the core. (OPCON 1,2,3). In OPCON 4 and 5 the water volume is reduced because the reactor coolant is maintained at or below 200F, the min water volume is based on NPSH, recirculation volume and vortex prevention, plus a safety margin.

Containment Systems (3.6.2) – The min and max water volume ensure pressure during the design basis accident is maintained <62#. Maximum torus water level for Hope Creek - this is an indicated water level of 124 inches in the Torus.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the basis for the Recirc loop flow mismatch limit?

A

ensure an adequate core flow coastdown from either recirculation loop following a LOCA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the MSIV Isolation valve basis?

A

The maximum closure time has been selected to contain fission products and to ensure the core is not uncovered following line breaks. The minimum closure time is consistent with the assumptions in the safety analyses to prevent pressure surges.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Do you get rollover minutes when required to change opcons several times in the same LCO?

A

If your already in hot shutdown when you enter an action item, you don’t get rollover minutes. I.e. If it is a 12/24 hr action but you are already in Hot Standby, you only get 24 hours to get to cold shutdown (not 36 hrs).

However, if you are just prompt in getting to the next opcon early you do get rollover minutes. I.e. for the same 12/24 hr action, if you only take 6 hours to get to hot standby, you still get the extra 6 plus 24 hours to get to cold shutdown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe the basis for the Torus Operating Temperatures

A

Under full power operating conditions, blowdown from an initial suppression chamber water temp of 95F results in a water temp of approximately 135F immediately following blowdown, which is less than 200F. At <200F the available NPSH exceed that required by both the RHR and CS pumps, thus there is no dependency on containment overpressure during the accident injection phase. (This can be taken as the basis for the 105F limit while testing HPCI or RCIC as well. – to maintain NPSH limits for CS and RHR)
95 – max during opcon 1
105 – during testing – for NPSH post blowdown for ECCS without overpressure. Begin temperature monitoring before testing begins on HPCI/RCIC
110 – with thermal power less than 1% - MSS
120 – with MSIVs closed (depressurize to <200 w.in 12 hours)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What thermal limits do we have and how do we maintain them?

A

We maintain MFLCPR (<1)
to maintain MinimumCPR (>1) we use >1.07 for test days
MFLPD to maintan LHGR
MAPRAT to maintain APLHGR (for post LOCA cladding temp and plastic strain).

17
Q

If RHR is inoperable, what is the most limiting spec is 3.6.2.3 for suppression chamber cooling?

A

72 hrs

18
Q

If MSIV indications are broken, what tech specs are you in?(memorization of actions not required, but knowing where to go is not obvious)

A

3.3.7.5-1 #14, action 82 – close it with a manual vlv, blind flange, or deactivated aumatic vlv outside pri. Cont., and restore to operable within 30d

19
Q

What is the purpose of the 54” level TS limit?

A

ONLY to protect the MAIN TURBINE

20
Q

What is the purpose of the PRV LVL in opcon 3,4, 5

A

only applies for the removal of decay heat while shutdown to protect cladding

21
Q

If in refuel/cold shutdown and taking the mode switch for testing is a declaration required?

A

No

22
Q

Where is the acoustic monitor spec covered?

A

The TRM

23
Q

How long do you have to restore suppression pool cooling?

A

1 hr

24
Q

If C diesel goes INOP at 0500 then D goes INOP at 1000, then C comes back at 1100, what is the beginning time for the tech spec you are in?

A

0500 because the tech spec is only concerned with the number of EDG that are INOP

25
Q

If you are at 9% and are taking the unit offline, when do you enter mode 3?

A

as soon as the mode switch is out of run