IOP Purposes Flashcards

1
Q

IO 1 Refueling to Cold Shutdown

A

This procedure provides a sequence for placing the plant in a configuration required for
Cold Shutdown (OPERATIONAL CONDITION 4) from Refueling (OPERATIONAL
CONDITION 5). This sequence ensures conformance with T/S requirements, integration
of plant personnel Refuel Floor activities, personnel and equipment safety and compliance
with the station ALARA program. This procedure also addresses system operability
requirements when lowering the Reactor Cavity level, or installing the cavity gates while in
CONDITION 5.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

IO 2 Preparations for Plant Startup

A

This procedure provides guidelines for placing all systems necessary for the startup
(hot OR cold) of the plant in their required mode of operation. This procedure ensures that
the surveillances required for the reactor startup have been performed and provide plant
alignment and direction for pressure testing of components with the Reactor not “Critical”,
using Decay and/or Non-Nuclear heat.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

IO 3 Startup from Cold Shutdown to Rated Power

A

This procedure provides guidelines for the startup of the plant from a cold shutdown
condition to rated power. It is also applicable to startups from conditions other than
cold shutdown with the Shift Manager/Control Room Supervisor/Work Control
Center Supervisor (SM/CRS) determining the steps, which are not applicable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

IO 4 Shutdown from Rated Power to Cold Shutdown

A

This procedure provides guidelines for the shutdown of the plant from rated power to
a Cold Shutdown condition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

IO 5 Cold Shutdown to Refueling

A

This procedure provides a sequence for placing the plant in a Refueling configuration
(OPERATIONAL CONDITION 5) from Cold Shutdown (OPERATIONAL CONDITION 4).
This sequence ensures conformance with T/S requirements, integration of plant
personnel refuel floor activities, personnel and equipment safety and compliance with
the station ALARA Program. [CD-443X]
This procedure partially satisfies an NRC commitment for the License Renewal ASME
Section XI IWE Aging Management Program (AMP) activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

IO 6 Power Changes during operation

A

The purpose to this procedure is to provide guidance when making routine power changes during operation above 45% POWER, until HC.OP-IO.ZZ-0004(Q), Shutdown From Rated Power to Cold Shutdown is implemented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

IO 7 Operations in Hot Standby

A

This procedure provides guidelines for the following operations:
 Maintaining Hot Standby (with the MSIVs closed)
 Maintaining Hot Standby (with the MSIVs open)
 Plant Shutdown from Hot Standby to Cold Shutdown
 Plant Startup from Hot Standby.
 Plant Shutdown from Hot Standby to Cold Shutdown (MSIVs Open)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

IO 8 Shutdown from Outside the Control Room

A

This procedure provides guidelines for the shutdown of the plant from outside the Control
Room, AND for re-establishing control in the Control Room.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IO 9 Refueling Operations

A

This procedure provides a mechanism for ensuring that the TECH SPEC / UFSAR
requirements are satisfied prior to conducting CORE ALTERATIONS. In addition this
procedure provides a means of identifying and coordinating in-vessel activities with other
plant activities while the plant is in OPERATIONAL CONDITION 5 - Refueling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

IO 10 Scram Recovery

A

This procedure provides the guidance for aligning systems required for plant startup,
following a Reactor Scram, to facilitate re-starting the plant. This procedure also ensures
that the surveillances required for the Reactor Startup have been performed or are being
performed. This procedure is intended to be used when the cause of the Reactor Scram is
KNOWN, and that cause has been or is being corrected, and will not inhibit or affect the
safe operation of the Reactor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly