Practice Exam #2 Flashcards
The process of updating the scope statement as it evolves over time is known as
a. tuckman’s ladder
b. parkinson’s law
c. progressive elaboration
d. enterprise environmental factors
c. progressive elaboration
The lowest level of decomposition in the WBS is called
a. a task
b. an activity
c. a deliverable
d. a work package
d. a work package
in precedence diagram method, a lag refers to
a. a fixed delay imposed on a predecessor
b. a conditional delay caused by uncertainty
c. the amount of time a successor can be initiated in advance
d. a slow moving resource
a. a fixed delay imposed on a predecessor
match the following finish to start start to start finish to finish start to finish
- predecessor may not finish until the successor starts
- successor may not finish until the predecessor is complete
- successor may not start until the predecessor is complete
- successor may not start until the predecessor starts
finish to start - 3
start to start - 4
finish to finish - 2
start to finish - 1
what is cost variance?
earned value - actual cost
CV = EV - AC
which is NOT among the tools and techniques of the estimate costs process?
a. alternative analysis
b. reserve analysis
c. cost of quality
d. funding limit reconciliation
d. funding limit reconciliation
a project has a budge of $20K. the planned value is currently $6K. the project is 25% complete and $6K has been spent. which statement is correct
a. the project is behind schedule
b. the project is ahead of schedule
c. the project is on schedule
d. the project is under budget
a. the project is behind schedule
planned value (PV) = $6k earned value (EV) = $20K x 25% = $5K schedule variance (SV) = EV - PV = $5K - $6k = -$1K SV < 0 means behind schedule
outputs of the control costs process include
a. work performance information, cost forecasts, and change requests
b. work performance data, cost estimates and project funding requirements
c. work packages, cost baseline and reserve analysis
d. work breakdown structure, cost aggregation and funding limit reconciliation
a. work performance information, cost forecasts, and change requests
Given the following factors earned value = $14K planned value = $15K actual costs = $12K what is cost variance?
a. $0
b. $1K
c. $2K
d. $3K
c. $2K
cost variance (CV) - EV - AC = $14k - $12k = $2k
match the project quality tool with it’s purpose
fishbone diagram flow chart checksheets pareto chart histogram control chart scatter diagram
- record measurements relative to upper and lower control limits
- perform root cause analysis
- data representation of statistical distribution
- identify the most common causes
- determine the correlation of 2 variables
- record variables and attributes during inspection
- illustrate how various elements interrelate
fishbone diagram - 2 flow chart - 7 checksheets - 6 pareto chart - 4 histogram - 3 control chart - 1 scatter diagram - 5