9.1 Plan Resource Management (Resource MGMT) Flashcards
what is 9.1 plan resource management?
defining how to estimate, acquire, manage and use team and physical resources
what is the key benefit to 9.1 plan resource management?
established the approach and level of management effort needed for managing project resources based on the type and complexity of the project
when is 9.1 plan resource management performed during a project?
once or at predefined points
9.1 plan resource management - inputs
- project charter
- project management plan (2)
- project documents (4)
- EEF’s
- OPA’s
what project management plan inputs are relevant for 9.1 plan resource managment?
a. quality management plan
b. scope baseline
what project document inputs are relevant for 9.1 plan resource management?
a. project schedule
b. requirements documentation
c. risk register
d. stakeholder register
9.1 plan resource management - tools and techniques
- expert judgement
- data representation (3)
- organizational theory
- meetings
what are examples of expert judgment tools and techniques used in 9.1 plan resource management?
- negotiating for best resources
- talent management and personnel development
- determine preliminary effort level needed
- determining reporting requirements based on organizational culture
- estimating lead times required for acquisition based on lessons learned and market conditions
- ID risk with resource acquisition, retention and release
- comply with govt. and union regulations
- manage sellers and logistics to ensure resources are available when needed
what are data representation tools and techniques used for 9.1 plan resource management?
a. hierarchical charts (3)
b. assignment matrix
c. text oriented formats
what hierarchical charts?
traditional organization chart structure showing positions and relationships in graphical top-down format
- work breakdown structure
- organization breakdown structure
- resource breakdown structure
what is an assignment matrix?
Responsibility Assignment Matrix (RAM)
- shows the connections between work packages/activities and team members
- matrix format shows all activities associated with one person and all people associated with 1 activity
what is a RACI Chart?
- responsible, accountable, consult and inform
- ensures clear assignment of roles and responsibilities when team consists of internal and external resources
what is a text oriented format?
- utilized to outline team member responsibilities, authority, competency and qualifications
what is organization theory?
- provides information regarding the way people, teams and organization units behave
- use of techniques can shorten amount of time, cost and effort needed to create Plan Resource Management process outputs
- recommendations may include flexible leadership styles
- organization’s structure/culture impacts project organizational structure
9.1 plan resource management - outputs
- resource management plan
- team charter
- project document updates (2)