11.5 Plan Risk Responses (Proj. Risk MGMT) Flashcards
what is 11.5 plan risk response?
1) the process of developing options
2) selecting strategies and
3) agreeing on actions to
address overall project risk exposure / individual project risks
what is the key benefit to 11.5 plan risk response? (2)
- ID’s the appropriate way to address overall project risk and individual project risk
- allocates resources and inserts activities into project documents and PMP as needed
when is 11.5 plan risk response performed during a project?
throughout
11.5 plan risk response - inputs
- project management plan (3)
- project documents (7)
- EEFs
- OPAs
what project management plan inputs are relevant to 11.5 plan risk response? (3)
a. resource management plan
b. risk management plan
c. cost baseline
what project document inputs are relevant to 11.5 plan risk response? (7)
a. lessons learned register
b. project schedule
c. project team assignments
d. resource calendars
e. risk register
f. risk report
g. stakeholder register
what EEFs are relevant inputs to 11.5 plan risk response? (1)
- risk appetite / thresholds of key stakeholders
what OPAs are relevant inputs to 11.5 plan risk response?
- templates for RMP, risk register and risk report
- historical databases
- lessons learned repositories from similar projects
11.5 plan risk response - outputs (3)
- change requests
- project management plan updates (8)
- project document updates (7)
what project management plan update outputs are relevant to 11.5 plan risk response?
MANAGEMENT PLANS:
a. schedule
b. cost
c. quality
d. resource
e. procurement
BASELINES:
f. scope
g. schedule
h. cost
what project management plan update outputs are relevant to 11.5 plan risk response? (8)
MANAGEMENT PLANS:
a. schedule
b. cost
c. quality
d. resource
e. procurement
BASELINES:
f. scope
g. schedule
h. cost
what project document update outputs are relevant to 11.5 plan risk response? (7)
a. assumption log
b. cost forecasts
c. lessons learned register
d. project schedule
e. project team assignments
f. risk register
g. risk report
what project document update outputs are relevant to 11.5 plan risk response? (7)
a. assumption log
b. cost forecasts
c. lessons learned register
d. project schedule
e. project team assignments
f. risk register
g. risk report
what are strategies for threats? (5)
- escalate
- avoid
- transfer
- mitigate
- accept
what is the transfer strategy for threats?
shifting ownership to a third party to management the risk and bear the impact (ex. risk premium, insurance, bonds, warranties, guarantee etc.)