11.5 Plan Risk Responses (Proj. Risk MGMT) Flashcards

1
Q

what is 11.5 plan risk response?

A

1) the process of developing options
2) selecting strategies and
3) agreeing on actions to

address overall project risk exposure / individual project risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit to 11.5 plan risk response? (2)

A
  1. ID’s the appropriate way to address overall project risk and individual project risk
  2. allocates resources and inserts activities into project documents and PMP as needed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 11.5 plan risk response performed during a project?

A

throughout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

11.5 plan risk response - inputs

A
  1. project management plan (3)
  2. project documents (7)
  3. EEFs
  4. OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan inputs are relevant to 11.5 plan risk response? (3)

A

a. resource management plan
b. risk management plan
c. cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what project document inputs are relevant to 11.5 plan risk response? (7)

A

a. lessons learned register
b. project schedule
c. project team assignments
d. resource calendars
e. risk register
f. risk report
g. stakeholder register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what EEFs are relevant inputs to 11.5 plan risk response? (1)

A
  1. risk appetite / thresholds of key stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what OPAs are relevant inputs to 11.5 plan risk response?

A
  1. templates for RMP, risk register and risk report
  2. historical databases
  3. lessons learned repositories from similar projects
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

11.5 plan risk response - outputs (3)

A
  1. change requests
  2. project management plan updates (8)
  3. project document updates (7)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what project management plan update outputs are relevant to 11.5 plan risk response?

A

MANAGEMENT PLANS:

a. schedule
b. cost
c. quality
d. resource
e. procurement

BASELINES:

f. scope
g. schedule
h. cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what project management plan update outputs are relevant to 11.5 plan risk response? (8)

A

MANAGEMENT PLANS:

a. schedule
b. cost
c. quality
d. resource
e. procurement

BASELINES:

f. scope
g. schedule
h. cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what project document update outputs are relevant to 11.5 plan risk response? (7)

A

a. assumption log
b. cost forecasts
c. lessons learned register
d. project schedule
e. project team assignments
f. risk register
g. risk report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what project document update outputs are relevant to 11.5 plan risk response? (7)

A

a. assumption log
b. cost forecasts
c. lessons learned register
d. project schedule
e. project team assignments
f. risk register
g. risk report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what are strategies for threats? (5)

A
  1. escalate
  2. avoid
  3. transfer
  4. mitigate
  5. accept
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what is the transfer strategy for threats?

A

shifting ownership to a third party to management the risk and bear the impact (ex. risk premium, insurance, bonds, warranties, guarantee etc.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what is the accept strategy for threats?

A
  1. take no proactive action
  2. may be appropriate for low priority threats or not possible or cost-effective to address
  3. establish contingency reserve (time/money/resources) to handle if the threat occurs
17
Q

what are strategies for opportunities?

A
  1. escalate
  2. exploit
  3. share
  4. enhance
  5. accept
18
Q

what are contingent response strategies?

A

response plan that will be executed only under certain predefined conditions (ex. missing intermediate milestone or gaining higher priority)

19
Q

what are strategies for overall project risk? (5)

A
  1. avoid
  2. exploit
  3. transfer/share
  4. mitigate/enhance
  5. accept
20
Q

what risk register update may occur as an output in 11.5 plan risk response?

A
  1. agreed upon response strategies
  2. actions to implement chosen response strategy
  3. trigger conditions, symptoms, warning signs
  4. budget/schedule activities to implement responses
  5. contingency plans and associated risk triggers
  6. fallback plans
  7. residual risks
  8. secondary risks