6.0 Project Schedule Management Flashcards
What is 6.0 project schedule management?
it includes the processes required to manage the timely completion of the project
What are the 6.0 project schedule management processes?
- 1 plan schedule management
- 2 define activities
- 3 sequence activities
- 4 estimate activity durations
- 5 develop schedule
- 6 control schedule
What is 6.1 plan schedule management?
establishing the ✔policies, ✔procedures and ✔documentation for ✔planning, ✔developing, ✔managing, ✔executing and ✔controlling the project schedule
what is 6.2 define activities?
identifying and documenting the specific ✔actions to be performed to ✔product the project ✔deliverables
what is 6.3 sequence activities?
identifying and documenting the ✔relationship among the project activities
what is 6.4 estimate activity durations?
estimating the number of work periods needed to complete individual activities with the estimated resources
what is 6.5 develop schedule?
analyzing:
- activity sequences
- durations
- resource requirements and
- schedule constraints
to create the project schedule model for
- execution
- monitoring and
- controlling
what is 6.6 control schedule?
monitoring the status of the project to update the project schedule and manage changes to the schedule baseline
what are trends and emerging practices for 6.0 project schedule management?
- iterative scheduling with a backlog
2. on demand scheduling
what is iterative scheduling with a backlog?
a. a form of rolling wave planning based on adaptive life cycles
b. delivers incremental value to the customer
c. applicable when multiple teams can concurrently develop a large number of features that have few interconnected dependencies
d. benefit is welcomes change throughout the development life cycle
what is on-demand scheduling?
a. used in a Kanban system
b. pulls work from a backlog to be done immediately as resources become available
c. used for projects that evolve product incrementally in operational or sustainment environments
what are tailoring considerations for 6.0 project schedule management?
- life cycle approach
- resource availability
- project dimensions
- technology support
what are the considerations for agile/adaptive environments for 6.0 project schedule management?
- utilizes short cycles to undertake work
- reviews results and adapts as necessary
- iterative scheduling and on-demand, pull-based scheduling