6.0 Project Schedule Management Flashcards

1
Q

What is 6.0 project schedule management?

A

it includes the processes required to manage the timely completion of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 6.0 project schedule management processes?

A
  1. 1 plan schedule management
  2. 2 define activities
  3. 3 sequence activities
  4. 4 estimate activity durations
  5. 5 develop schedule
  6. 6 control schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is 6.1 plan schedule management?

A

establishing the ✔policies, ✔procedures and ✔documentation for ✔planning, ✔developing, ✔managing, ✔executing and ✔controlling the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is 6.2 define activities?

A

identifying and documenting the specific ✔actions to be performed to ✔product the project ✔deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what is 6.3 sequence activities?

A

identifying and documenting the ✔relationship among the project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is 6.4 estimate activity durations?

A

estimating the number of work periods needed to complete individual activities with the estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what is 6.5 develop schedule?

A

analyzing:

  • activity sequences
  • durations
  • resource requirements and
  • schedule constraints

to create the project schedule model for

  • execution
  • monitoring and
  • controlling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what is 6.6 control schedule?

A

monitoring the status of the project to update the project schedule and manage changes to the schedule baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what are trends and emerging practices for 6.0 project schedule management?

A
  1. iterative scheduling with a backlog

2. on demand scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is iterative scheduling with a backlog?

A

a. a form of rolling wave planning based on adaptive life cycles
b. delivers incremental value to the customer
c. applicable when multiple teams can concurrently develop a large number of features that have few interconnected dependencies
d. benefit is welcomes change throughout the development life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is on-demand scheduling?

A

a. used in a Kanban system
b. pulls work from a backlog to be done immediately as resources become available
c. used for projects that evolve product incrementally in operational or sustainment environments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are tailoring considerations for 6.0 project schedule management?

A
  1. life cycle approach
  2. resource availability
  3. project dimensions
  4. technology support
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are the considerations for agile/adaptive environments for 6.0 project schedule management?

A
  1. utilizes short cycles to undertake work
  2. reviews results and adapts as necessary
  3. iterative scheduling and on-demand, pull-based scheduling