5.4 Create WBS (Scope MGMT) Flashcards
What is 5.4 Create WBS?
The process of subdividing project deliverables and project work into smaller, more manageable components
What is the key benefit of 5.4 Create WBS?
It provides a framework of what has to be delivered
When is 5.4 Create WBS performed during the project?
Once or at predefined points
5.4 Create WBS - Inputs
- Project management plan (1)
- Project documents (2)
- Enterprise environmental factors
- Organization process assets
What project management plan elements are inputs for 5.4 Create WBS?
a. scope management plan
What project document elements are inputs for 5.4 Create WBS?
a. project scope statement
b. requirements documentation
5.4 Create WBS - Tools and Techniques
- Expert judgment
2. Decomposition
What is decomposition?
A technique for dividing and subdividing the project ✔scope and project ✔deliverables into smaller, more manageable parts
5.4 Create WBS - Outputs
- Scope baseline
2. Project document updates (2)
What project document updates are relevant outputs for 5.4 Create WBS?
a. assumption log
b. requirements documentation
What is WBS?
- Hierarchical decomposition of the total scope of work to be carried out by the project team to
- Accomplish the project objectives and
- Create the required deliverables
- Each descending level of the WBS represents and increasingly detailed definition of the project work