6.2 Define Activities (Schedule MGMT) Flashcards
what is 6.2 define activities?
identifying and documenting specific actions to be performed to produce the project devlierables
what is the key benefit to 6.2 define activities?
- decomposes work packages into schedule activities that
2. provide a basis for estimating, scheduling, executing, monitoring and controlling the project work
when is 6.2 define activities performed in the project?
throughout the project
6.2 define activities - inputs
- project management plan (2)
- EEF
- OPA
what project management plan inputs are relevant for 6.2 define activities?
a. schedule management plan
b. scope baseline
6.2 define activities - tools and techniques
- expert judgment
- decomposition
- rolling wave planning
- meetings
what is the schedule management plan?
defines the schedule methodology, duration of waves for rolling wave planning and the level of detail necessary to manage the work
what is the scope baseline?
documentation of the WBS, deliverables, constraints and assumptions
what is rolling wave planning?
- iterative planning technique
- near term work planned in detail
- future work planned at a higher level
6.2 define activities - outputs
- activity list
- activity attributes
- milestone list
- change requests
- project management plan updates (2)
what project management plan update outputs are relevant for 6.2 define activities?
a. schedule baseline
b. cost baseline