8.2 Manage Quality (Project Quality MGMT) Flashcards

1
Q

what is 8.2 manage quality?

A
  • translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project
  • uses data and results from control quality to reflect the overall quality state of the project to the stakeholders
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit to 8.2 manage quality?

A

increases the probability of meeting the quality objectives as well as identifying ineffective processes and causes of poor quality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

8.2 manage quality - inputs

A
  1. project management plan (1)
  2. project documents (4)
  3. organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what project management plan inputs are relevant for 8.2 manage quality?

A

a. quality management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project document inputs are relevant for 8.2 manage quality?

A

a. lessons learned register
b. quality control measurements
c. quality metrics
d. risk reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

8.2 manage quality - tools and techniques

A
  1. data gathering (1)
  2. data analysis (4)
  3. decision making (1)
  4. data representation 6)
  5. audits
  6. design for X
  7. problem solving
  8. quality improvement methods
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what data gathering tools and techniques are relevant for 8.2 manage quality?

A

a. checklists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what data analysis tools and techniques are relevant for 8.2 manage quality?

A

a. alternative analysis
b. document analysis
c. process analysis
d. root cause analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what decision making tools and techniques are relevant for 8.2 manage quality?

A

a. multicriteria decision analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what data representation tools and techniques are relevant for 8.2 manage quality?

A

a. affinity diagrams
b. cause and effect diagrams
c. flowcharts
d. histograms
e. matrix diagrams
f. scatter diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are affinity diagrams?

A

they organize potential causes of defects into groups showing areas that should be focused on the most

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are cause and effect diagrams?

A
  • fishbone diagrams, why-why diagrams or Ishikawa diagrams

- breaks down causes into discrete branches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what are matrix diagrams?

A

shows the strength of relationships among factors, causes and objectives that exist between rows and columns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what are scatter diagrams?

A

shows the relationship between 2 variables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what is design for X?

A
  • a set of technical guidelines that may be applied during the design of a product for the optimization of a specific aspect
  • DfX –> X can be reliability, deployment, assembly, manufacturing, cost, service, usability, safety, quality etc.
  • may result in cost reduction, quality improvement, better performance and customer satisfaction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what are the basic element of problem solving?

A
  1. define problem
  2. identify root cause
  3. generate possible solutions
  4. choose best solution
  5. implement solution
  6. verifying solution effectiveness
17
Q

8.2 manage quality - outputs

A
  1. quality reports
  2. test and evaluation documents
  3. change requests
  4. project management plan updates 4)
  5. project document updates (3)
18
Q

what project management plan update outputs are relevant for 8.2 manage quality?

A

a. quality management plan
b. scope baseline
c. schedule baseline
d. cost baseline

19
Q

what project document update outputs are relevant for 8.2 manage quality?

A

a. issue log
b. lessons learned register
c. risk register

20
Q

what are quality reports?

A
  • all quality management issues escalated by team
  • recommendations for process, project and product improvements
  • corrective action recommendations
  • summary of findings from Control Quality process
  • can be used by other processes and departments to take corrective actions in order to achieve the project quality expectations
21
Q

what are test and evaluation documents?

A
  • inputs to control quality process
  • used to evaluate the achievement of the quality objectives
  • may include checklists and detailed requirements traceability matrices