6.4 Estimate Activity Durations (Schedule MGMT) Flashcards
what is 6.4 estimate activity durations?
estimating the number of work periods needed to complete individual activities with estimated resources
what is the key benefit to 6.4 estimate activity durations?
provides the amount of time each activity will take to complete
when is 6.4 estimate activity durations performed during a project?
throughtout
6.4 estimate activity durations - inputs
- project management plan (2)
- project documents (10)
- EEF
- OPA
what project management plan inputs are relevant for 6.4 estimate activity durations?
a. schedule management plan
b. scope baseline
what project documents are relevant inputs for 6.4 estimate activity durations?
a. activity attributes
b. activity list
c. assumption log
d. lessons learned register
e. milestone list
f. project team assignments
g. resource breakdown structure
h. resource calendars
i. resource requirements
j. risk register
what are factors for consideration in 6.4 estimate activity durations?
- law of diminishing returns
- number of resources
- advances in technology
- motivation of staff
6.4 estimate activity durations - tools and techniques
- expert judgment
- analogous estimating
- parametric estimating
- three point estimating
- bottom up estimating
- data analysis (2)
- decision making
- meetings
what is analogous estimating?
- estimating duration or cost of an activity using historical data from similar activity or project
- gross value estimating approach, sometimes adjusted for known differences in project complexity
- used when there is limited amount of detailed information about the project
what is parametric estimating?
uses a statistical relationship between historical data and other variables to calculate an estimate for an activity parameters such as cost, budget and duration
what is three point estimating?
tE = time expected tO = optimistic tM = most likely tP = pessemistic
tE = (tO + tM = tP) / 3
what is bottom up estimating?
aggregating estimates of the lower level components of the WBS
what data analysis tools and techniques are relevant for 6.4 estimate activity durations?
a. alternative analysis
b. reserve analysis
what is reserve analysis?
- determine the amount of contingency and management reserve needed for the project
6.4 estimate activity durations - outputs
- duration estimates
- basis of estimates
- project document updates (3)