6.4 Estimate Activity Durations (Schedule MGMT) Flashcards

1
Q

what is 6.4 estimate activity durations?

A

estimating the number of work periods needed to complete individual activities with estimated resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit to 6.4 estimate activity durations?

A

provides the amount of time each activity will take to complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 6.4 estimate activity durations performed during a project?

A

throughtout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

6.4 estimate activity durations - inputs

A
  1. project management plan (2)
  2. project documents (10)
  3. EEF
  4. OPA
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan inputs are relevant for 6.4 estimate activity durations?

A

a. schedule management plan

b. scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what project documents are relevant inputs for 6.4 estimate activity durations?

A

a. activity attributes
b. activity list
c. assumption log
d. lessons learned register
e. milestone list
f. project team assignments
g. resource breakdown structure
h. resource calendars
i. resource requirements
j. risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are factors for consideration in 6.4 estimate activity durations?

A
  1. law of diminishing returns
  2. number of resources
  3. advances in technology
  4. motivation of staff
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

6.4 estimate activity durations - tools and techniques

A
  1. expert judgment
  2. analogous estimating
  3. parametric estimating
  4. three point estimating
  5. bottom up estimating
  6. data analysis (2)
  7. decision making
  8. meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is analogous estimating?

A
  1. estimating duration or cost of an activity using historical data from similar activity or project
  2. gross value estimating approach, sometimes adjusted for known differences in project complexity
  3. used when there is limited amount of detailed information about the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is parametric estimating?

A

uses a statistical relationship between historical data and other variables to calculate an estimate for an activity parameters such as cost, budget and duration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what is three point estimating?

A
tE = time expected
tO = optimistic
tM = most likely
tP = pessemistic

tE = (tO + tM = tP) / 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is bottom up estimating?

A

aggregating estimates of the lower level components of the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what data analysis tools and techniques are relevant for 6.4 estimate activity durations?

A

a. alternative analysis

b. reserve analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what is reserve analysis?

A
  • determine the amount of contingency and management reserve needed for the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

6.4 estimate activity durations - outputs

A
  1. duration estimates
  2. basis of estimates
  3. project document updates (3)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

what project document updates outputs are relevant for 6.4 estimate activity durations?

A

a. activity attributes
b. assumption log
c. lessons learned register