12.3 Control Procurements (Procurement MGMT) Flashcards
what is 12.3 control procurements? (4)
- managing procurement relationships
- monitoring contract performance
- making changes and corrections as appropriate
- closing out contracts
what is the key benefit to 12.3 control procurements?
ensure that both the seller’s and buyer’s performance meet the project’s requirements according to the terms of the legal agreement
when is 12.3 control procurements performed during a project?
throughout as needed
12.3 control procurements - inputs (8)
- project management plan (5)
- project documents (8)
- agreements
- procurement documentation
- APPROVED change requests
- work performance data
- EEFs
- OPAs
what project management plan inputs are relevant to 12.3 control procurements? (5)
a. requirements management plan
b. risk management plan
c. procurement management plan
d. change management plan
e. schedule baseline
what project document inputs are relevant to 12.3 control procurements? (8)
a. assumption log
b. lessons learned register
c. milestone list
d. quality reports
e. requirements documentation
f. requirements traceability matrix
g. risk register
h. stakeholder register
what EEF inputs are relevant to 12.3 control procurements? (4)
- contract change cotnrol systems
- marketplace conditions
- financial management and accounts payable systems
- buying organization’s code of ethics
what OPA inputs are relevant to 12.3 control procurements? (1)
procurement policies
what approved change requests are relevant to 12.3 control procurements? (3)
modifications to terms and conditions of contract including:
- procurement statement of work
- pricing
- descriptions of the products/services/results to be provided
12.3 control procurements - tools and techniques (5)
- expert judgement
- claims administration
- data analysis (3)
- inspection
- audits
what data analysis tools and techniques are relevant to 12.3 control procurements? (3)
a. performance reviews
b. earned value analysis
c. trend analysis
12.3 control procurements - outputs (7)
- closed procurements
- work performance information
- procurement documentation updates
- change requests
- project management plan updates (4)
- project documents updates (5)
- OPA updates
what project management plan update outputs are relevant to 12.3 control procurements? (4)
a. risk management plan
b. procurement management plan
c. schedule baseline
d. cost baseline
what project document updates are relevant for 12.3 control procurements? (5)
a. lessons learned register
b. resource requirements
c. requirements traceability matrix
d. risk register
e. stakeholder register