4.6 Perform Integrated Change Control (Integration MGMT) Flashcards

1
Q

What is 4.6 Perform Integrated Change Control

A
  1. The process of reviewing all change requests
  2. Approving changes
  3. Managing changes to ✔deliverables, ✔project documents, and the ✔project management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the key benefit to 4.6 Perform Integrated Change Control?

A

Allows for documented changes to ✔considered in an ✔integrated manner while addressing overall project ✔risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When does project risk arise?

A

From changes made without consideration of the ✔overall project objectives or ✔plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is 4.6 Perform Integrated Change Control performed during the project?

A

Throughout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

4.6 Perform Integrated Change Control - Inputs

A
  1. Project Management Plan (5)
  2. Project documents (3)
  3. Work performance reports
  4. Change requests
  5. Enterprise environmental factors
  6. Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

4.6 Perform Integrated Change Control - Tools and Techniques

A
  1. Expert judgement
  2. Change control tools
  3. Data analysis (2)
  4. Decision making (3)
  5. Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

4.6 Perform Integrated Change Control - Outputs

A
  1. APPROVED change requests
  2. Project management plan updates
  3. Project document updates
    a) change log
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What elements of the Project Management Plan are relevant for 4.6 Perform Integrated Change Control - Inputs?

A

a) change management plan
b) configuration management plan
c) scope baseline
d) schedule baseline
e) cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the configuration management plan?

A

It describes the configurable items of the project and identifies the items that will be recorded and updated so that the product of the project remains consistent and operable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What Project Documents are relevant for 4.6 Perform Integrated Change Control - Inputs?

A

a) basis of estimates
b) requirements traceability matrix
c) risk reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the basis of estimates?

A

The indicate how the duration, cost and resources estimate were derived and cab be used to calculate the impact of the change in time, budget and resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What Data Analysis Tools and Techniques are relevant for 4.6 Perform Integrated Change Control?

A

a) alternative analysis

b) cost benefit analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What Decision Making Tools and Techniques are relevant for 4.6 Perform Integrated Change Control?

A

a) voting
b) autocratic decision making
c) multicriteria decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly