7.3 Determine Budget (Cost MGMT) Flashcards

1
Q

what is 7.3 determine budget?

A

aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit to 7.3 determine budget?

A

determines the cost baseline against which project performance can be monitored and controlled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 7.3 determine budget performed during the project?

A

once or at predefined points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7.3 determine budget - inputs

A
  1. project management plan (3)
  2. project documents (4)
  3. business documents (2)
  4. agreements
  5. EEF
  6. OPAs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan inputs are relevant to 7.3 determine budget

A

a. cost management plan
b. resource management plan
c. scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what project documents are relevant to 7.3 determine budget?

A

a. basis of estimates
b. cost estimates
c. project schedule
d. risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what business documents are relevant to 7.3 determine budget?

A

a. business case

b. benefits management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

7.3 determine budget - tools and techniques

A
  1. expert judgement
  2. cost aggregation
  3. data analysis (1)
  4. historical information review
  5. funding limit reconciliation
  6. financing
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what data analysis tools and techniques are relevant for 7.3 determine budget?

A

a. reserve analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what is funding limit reconciliation

A

exposing variances between the funding limits and the planned expenditures - potentially necessitating the rescheduling of work to level out the rate of expenditures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

7.3 determine budget - outputs

A
  1. cost baseline
  2. project funding requirements
  3. project document updates (3)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what project document update outputs are relevant for 7.3 determine budget?

A

a. cost estimates
b. project schedule
c. risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

what is the cost baseline?

A
  • approved version of the time-phased project budget, excluding management reserves
  • can only be changed through formal change control procedure
  • summation of the approved budgets for the different schedule activities
  • typically displayed in the form of an S-curve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what are project funding requirements?

A
  • derived from the cost baseline

- includes projected expenditures plus anticipated liabilities