6.3 Sequence Activities (Schedule MGMT) Flashcards

1
Q

what is 6.3 sequence activities?

A

identifying and documenting relationships among project activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit of 6.3 sequence activities?

A

defines the logical sequence of work to obtain the greatest efficiency given all project constraints

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 6.3 sequence activities performed in the project?

A

throughout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

6.3 sequence activities - inputs

A
  1. project management plan (2)
  2. project documents (4)
  3. EEF
  4. OPA’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan inputs are relevant for 6.3 sequence activities?

A

a. schedule management plan

b. scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what project document inputs are relevant for 6.3 sequence activities?

A

a. activity attributes
b. activity list
c. assumption log
d. milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

what are activity attributes?

A
  • defined predecessor or successor relationships

- defined lead and lag and relationships

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

6.3 sequence activities - tools and techniques

A
  1. precedence diagramming method
  2. dependency determination and integration
  3. leads and lags
  4. PMIS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is precedence diagramming method?

A
  • constructing a schedule model in which activities are represented by nodes
  • graphically linked by one or more logical relationship
  • show the sequence in which the activities are to be performed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

how can dependencies be characterized?

A
  1. mandatory or discretionary

2. internal or external

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are mandatory dependencies?

A

those that are legally or contractually required

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are discretionary dependencies?

A
  • established based on knowledge of best practices

- there may be other acceptable sequences

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

6.3 sequence activities - outputs

A
  1. project schedule network diagrams

2. project document updates (4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what project document updates are outputs to 6.2 sequence activities?

A

a. activity attributes
b. activity list
c. assumption log
d. milestone list

How well did you know this?
1
Not at all
2
3
4
5
Perfectly