9.6 Control Resources (Resource MGMT) Flashcards

1
Q

what is 9.6 control resources?

A
  • ensuring the physical resources assigned and allocated to the project are available as planned
  • monitoring the planned vs. actual utilization of resources and taking corrective action as necessary
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit to 9.6 control resources?

A

ensuring the assigned resources are available to the project at the right time and in the right place and are released when no longer needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 9.6 control resources performed during a project?

A

throughout

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

9.6 control resources - inputs

A
  1. project management plan (1)
  2. project documents (7)
  3. work performance data
  4. agreements
  5. OPA’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan inputs are relevant to 9.6 control resources?

A

a. resource management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what project documents are relevant to 9.6 control resources?

A

a. issue log
b. lessons learned register
c. physical resource assignments
d. project schedule
e. resource breakdown structure
f. resource requirements
g. risk register

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

9.6 control resources - tools and techniques

A
  1. data analysis (4)
  2. problem solving
  3. interpersonal and team skills (2)
  4. PMIS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what data analysis tools and techniques are relevant to 9.6 control resources?

A

a. alternative analysis
b. cost benefit analysis
c. performance reviews
d. trend analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what interpersonal and team skill tools and techniques are relevant to 9.6 control resources?

A

a. negotiating

b. influencing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

9.6 control resources - outputs

A
  1. work performance information
  2. change requests
  3. project management plan updates (3)
  4. project document updates (6)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what project management plan update outputs are relevant to 9.6 control resources?

A

a. resource management plan
b. schedule baseline
c. cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what project document update outputs are relevant to 9.6 control resources?

A

a. assumption log
b. issue log
c. lessons learned register
d. physical resource assignments
e. resource breakdown structure
f. risk register