13.2 Plan Stakeholder Engagement (Stakeholder MGMT) Flashcards
what is 13.2 plan stakeholder engagement?
developing approaches to involve project stakeholders based on their needs, expectations, interests and potential impact on the project
what is the key benefit to 13.2 plan stakeholder engagement?
provides an actionable plan to interact effectively with stakeholders
when is 13.2 plan stakeholder engagement performed during a project?
periodically as needed
13.2 plan stakeholder engagement - inputs (6)
- project charter
- project management plan (3)
- project documents (6)
- agreements
- EEFs
- OPAs
what project management plan inputs are relevant to 13.2 plan stakeholder engagement? (3)
a. resource management plan
b. communications management plan
c. risk management plan
what project document inputs are relevant to 13.2 plan stakeholder engagement? (6)
a. assumption log
b. change log
c. issue log
d. project schedule
e. risk register
f. stakeholder register
what EEFs inputs are relevant to 13.2 plan stakeholder engagement? (6)
- organizational culture, political climate, governance framework
- personnel administration policies
- stakeholder risk appetites
- established communication channels
- global regional or local trends, practices or habits
- geographic distribution of facilities and resources
what OPA inputs are relevant to 13.2 plan stakeholder engagement? (6)
- social media, ethics and securities policies
- issue, risk, change and data management policies
- communication requirements
- development, exchange, storage and retrieval of information guidelines
- lessons learned repositories (preferences, actions, stakeholder involvement)
- software tools required
what are trigger situations that require an update to the plan in 13.2 plan stakeholder engagement? (4)
- start of new phase of project
- changes to organizational structure
- new individuals or groups become stakeholders
- outputs of other process areas cause a review
13.2 plan stakeholder engagement - tools and techniques (6)
- expert judgement
- data gathering (benchmarking)
- data analysis (2)
- decision making (prioritization/ranking)
- data representation (2)
- meetings
what data analysis tools and techniques are relevant to 13.2 plan stakeholder engagement? (2)
a. assumption and constraint analysis
b. root cause analysis
what data representation tools and techniques are relevant to 13.2 plan stakeholder engagement? (2)
a. mind mapping
b. stakeholder engagement assessment matrix
what is mind mapping
visually organize information about stakeholders and relationships
what is a stakeholder engagement assessment matrix?
shows comparison between current engagement level and desired engagement level for project success
- unaware
- resistant
- neutral
- supportive
- leading
13.2 plan stakeholder engagement - outputs (1)
- stakeholder engagement plan