6.1 Plan Schedule Management (Schedule MGMT) Flashcards

1
Q

what is 6.1 plan schedule management?

A

establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is the key benefit of 6.1 plan schedule management?

A

provides guidance and direction on how the project schedule will be managed throughout the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

when is 6.1 plan schedule management performed during the project?

A

once or at predefined points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

6.1 plan schedule management - inputs

A
  1. project charter
  2. project management plan (2)
  3. enterprise environmental factors
  4. organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what project management plan elements are inputs for 6.1 plan schedule management?

A

a. scope management plan

b. development approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

6.1 plan schedule management - tools and techniques

A
  1. expert judgment
  2. data analysis (1)
  3. meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

6.1 plan schedule management - outputs

A
  1. schedule management plan
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

what data analysis tool or technique is relevant for 6.1 plan schedule management?

A

a. alternative analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does the schedule management plan establish?

A
  1. project schedule model development
  2. release and iteration length
  3. level of accuracy
  4. units of measure
  5. organizational procedure links
  6. project schedule model maintenance
  7. control thresholds (% deviation allowed)
  8. rules of performance measurement
  9. reporting formats