Lesson 79. Directing a project, purpose Flashcards
Who directs the project, and which level of the project are they in?
The project board directs the project, and they are in the direction layer.
What does the project board do while directing the project?
They make decisions and spend very little time on the project but still want full control.
What is the purpose of ‘directing a project process?
The purpose of the ‘directing a project’ process is to enable the project board to be accountable for the project’s success by making key decisions and exercising overall control while delegating day-to-day management of the project to the project manager.
What is the first decision taken by the project board?
The first decision taken is to initiate the project. The project board allows the project to proceed to the initiation stage.
What is the second decision taken by the project board?
The second decision is to allow the project to continue after initiation.
Which level of the project is the interface between the project and the business?
The directing layer (project board) interfaces the project and the business layer.
What is the last decision taken by the project board?
The last decision taken is to close the project.