What does the project manager do in the project initiation process?

A

The project manager does the following:
* Decide how to tailor the project
* Create the nine management approach documents
* Decide on project control
* Facilitate workshops for product descriptions and project plan
* Update the business case after project plan completion
* Assemble documentation into the PID
* Request project board to continue with the project

The project manager plays a crucial role in setting the foundation for the project by ensuring all necessary documentation and plans are in place.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the inputs to the ‘initiating a project’ process?

A

The inputs are:
* Project brief
* Stage plan
* Lessons log
* Daily log

These inputs provide essential information and context for successfully initiating the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the main output of the ‘initiating a project’ process, and what does it contain?

A

The main output is the PID. It contains:
* Tailoring information and management approach documents
* Project control and approach information
* Project management team and role descriptions
* Project plan and business case

The PID serves as a comprehensive document outlining the project’s scope and direction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the purpose of the project initiation document (PID)?

A

The purpose of the PID is to provide direction and scope for the project.
The PID forms a contract between the project manager and the project board.

The PID acts as a foundational document for project governance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the primary uses of the PID?

A

The primary uses of the PID are:
* Ensure the project has a sound basis for decision-making by the project board
* Act as a baseline document for checking progress
* Provide a single source of reference for the project

These uses help maintain clarity and accountability throughout the project lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which document serves as a contract between the project board and the project manager?

A

The PID (Project initiation documentation)

This contract outlines the agreement and expectations between the two parties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly