les 15 planning Flashcards

1
Q

Do Agile projects do planning?

A

No, agile projects have a different type of planning, but they still have to be planned.

Agile planning differs from traditional planning but is still essential for project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What type of project plan is best to start with?

A

A high-level project plan that overviews the project’s scope.

This plan serves as a foundation for more detailed planning later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does a project manager’s ability to predict project outcomes affect planning?

A

The project manager can create a more detailed project plan if they wish to, as they can predict from experience how the project will work.

Experience allows for better forecasting and planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is another name for ‘Adaptive’ projects?

A

Agile.

Agile is a common term used for projects that adapt to changes and focus on iterative progress.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which is better: Predictive or Adaptive (Agile)?

A

This is a trick question: For more projects, it is better to use the predictive approach, and for some projects, it is better to use the adaptive approach.

The choice depends on project specifics and requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does ‘planning horizon’ refer to?

A

How far the project can be planned in detail.

This can range from just one week to three months, depending on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why is it a good idea to plan in stages?

A

It makes the project much more manageable and easier to plan, making it less overwhelming.

Staged planning allows for adjustments and improvements as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who facilitates the project planning?

A

Project manager.

The project manager organizes workshops and invites users to provide an overview of requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly