les 25 - business Case - Technique Flashcards

1
Q

What are the four steps in the PRINCE2 technique for business case management?

A

Develop, Check, Maintain and Confirm benefits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who develops the business case and when?

A

The project executive develops the outline business case in the pre-project process. More details are added by the project manager at the end of the initiation stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Who checks the business case at the end of each stage?

A

The project board checks the business case at the end of each stage. The project board wishes to see if continuing the project is still worth it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who maintains the business case?

A

The business case is maintained by the project manager. It is continually reviewed and updated with actual progress & forecasts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Can benefits be realized during the project?

A

Yes, some benefits may be realized during the project. For example, apartments are sold off during the project and before the building is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which role provides the benefits information after the project has closed?

A

The senior user role specifies the benefits and provides information on realized benefits during and after the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which document provides a complete and firm foundation to initiate the project?

A

Project brief

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the purpose of documenting the business justification for undertaking a project?

A

Business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which document defines the benefits management actions and reviews?

A

Benefits management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which document defines the actions, reviews, and controls for sustainability performance targets?

A

Sustainability management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Fill in the blank: The project _______ checks the business case at the end of each stage.

A

[project board]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

True or False: The project manager is responsible for developing the initial business case.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fill in the blank: The _______ role specifies the benefits during the project.

A

[senior user]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What document is continually reviewed and updated with actual progress & forecasts?

A

Business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly