les 14 issues and changes Flashcards
What is a request to change an approved ‘management product’?
A ‘request for change’ or ‘change request’
This refers to a formal proposal to modify an existing product or management plan.
Can a change request also be for a new product?
Yes
At the end of the initiation stage, users can request new products, leading to unique product descriptions.
What is the second step for a project manager when they discover a new issue?
Assess
CARDI
The steps are capture, assess, recommend, decide, and implement.
Can the project board allow the project manager to make small decisions regarding issues?
Yes, if the cost is less than € 10,000
If the impact of the issues is higher, the project manager must escalate to the project board.
Who should facilitate the issue management steps?
Project manager
The project manager is responsible for overseeing the management of issues.
What typically happens to open issues at the end of the project?
They are reviewed with those who will take ownership of the project output
This ensures that all issues are addressed before project closure.
In which document are issues that need to be assessed and added?
Issues register
The issues register is a key document for tracking and managing project issues.