Chapter 4 Practices Flashcards

1
Q

In which process are the activities necessary to make sure the project is viable and worthwhile undertaken?

A

Starting up a project

Starting up a project
Directing a project
Initiating a project
Managing a stage boundary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who decides whether to initiate the project and states the level of authority to be delegated to the Project Manager for the initiation stage?

A

The Project Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which process is used exclusively by the Project Board?

A

Directing a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the idea or need that triggers a PRINCE2 project called?

A

Project mandate

Project brief
Project initiation documentation
Project mandate
Project plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the output of starting up a project?

A

Project brief

Project brief
Project initiation documentation
Project mandate
Project plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which regular report does the Project Manager send to the Project Board to keep them informed of progress during a stage?

A

Highlight report

Checkpoint report
Highlight report
End stage report
Exception report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

In which process are the activities necessary to close a project planned?

A

Managing a stage boundary

Managing a stage boundary
Closing a project
Managing product delivery
Directing a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly