In which process are the activities necessary to make sure the project is viable and worthwhile undertaken?
Starting up a project
Starting up a project
Directing a project
Initiating a project
Managing a stage boundary
Who decides whether to initiate the project and states the level of authority to be delegated to the Project Manager for the initiation stage?
The Project Board
Which process is used exclusively by the Project Board?
Directing a project
What is the idea or need that triggers a PRINCE2 project called?
Project mandate
Project brief
Project initiation documentation
Project mandate
Project plan
What is the output of starting up a project?
Project brief
Project brief
Project initiation documentation
Project mandate
Project plan
Which regular report does the Project Manager send to the Project Board to keep them informed of progress during a stage?
Highlight report
Checkpoint report
Highlight report
End stage report
Exception report
In which process are the activities necessary to close a project planned?
Managing a stage boundary
Managing a stage boundary
Closing a project
Managing product delivery
Directing a project