Containment Flashcards
What is the purpose of the Containment?
The purpose of the Containment System is to limit the potential offsite radiation dose from a Design Basis Accident(DBA) to less than the values of applicable federal regulations.
What are the barriers to Radioactive Release?
- Fuel pellet - ceramic uranium dioxide fuel pellets entrap most of the fission products.
- Fuel Cladding - zircalloy sheath surrounding the fuel pellets.
- Reactor Coolant System - Rx Vessel and associated piping that contain any fission products that escape through fuel cladding defects.
- Primary Containment System or Steel Containment Vessel - Steel structure surrounding the Reactor Coolant System that is the final barrier against a significant release.
- Secondary Containment System - Concrete Containment and Annulus Ventilation System used to collect and process radioactive leakage from the Primary Containment.
What is the design of the Steel Containment Vessel?
- Vertical steel cylinder with a hemispherical dome, and a flat circular base.
- The Steel Containment Vessel encloses the Reactor Coolant System, provides biological shielding, and is a pressure boundary between the various containment volumes.
What is the design of the Concrete Reactor Building and Annulus?
- Three Foot thick reinforced concrete cylindrical structure used to provide environmental and missile protection for the Steel Containment.
- A six foot annular space exists between the Steel and Concrete Containment to allow for collection and processing of any release using the Annulus Ventilation System.
What is the design of the Containment Divider Barrier?
The Containment Divider Barrier splits the inside of Containment into upper and lower compartments to ensure that steam from a high energy release is routed to through the Ice Condenser.
What are some components of the Containment Divider Barrier?
- Submarine Hatch
- The Lower Ice Condenser Personnel Access Door
- Pressurizer Hatch
- Steam Generator Enclosures
What is the design of the Equipment Hatch Penetration and Cover?
- The Equipment Hatch Penetration and Cover are components of Steel Containment Vessel wall.
- The Equipment Hatch seal is a double o-ring design that must be type B leak rate tested.
- The Equipment hatch must be able to be replaced without AC power available.
What are the Containment Leakage Requirements?
- Allowable leakage is the maximum allowed Containment leakage rate at the peak containment pressure(14.68psig) resulting from the Design Basis LOCA.
- Allowable leakage may not exceed the license limit allowed in the UFSAR.
What are the two categories of leakage from the Containment Building?
- Leakage into the Annulus volume
- Leakage directly to the environment atmosphere know as bypass leakage.
Bypass leakage is limited to no more than 7% of the UFSAR limit under Allowable leakage conditions. The remaining leakage into the Annulus is filtered and will constitute approximately 93% of Containment leakage.
What are the normal administrative, Technical Specification, and design limits for Containment pressure?
- Administrative Limits: -0.08psig to 0.25psig
- Tech Spec limits: greater than or equal to -0.1psig and less than or equal to 0.3psig.
- Design limit: 15psig internal pressure/ -1.5psig external pressure
What are the Containment temperature Technical Specification limits?
- Greater than or equal to 75F and less than or equal to 100F for the Containment Upper Compartment.
- Greater than or equal to 100F and less than or equal to 120F for the Containment Lower Compartment.
What are the Containment design temperature limits?
- 317F in Steam Generator Compartment
- 297F average in lower containment
- 250F average in Containment overall
In what MODES can we operate with a reduced Containment temperature?
In MODES 2, 3, and 4 temperature may be reduced to 60F due to a lesser amount of energy released from the pipe break in these MODES.
How many Airlocks are there?
There are two Personnel Airlocks
Which Airlock barrier is considered the “first” and the “redundant” barrier?
- The Reactor side bulkhead is considered the “first” barrier.
- The Auxiliary Building side is considered the “redundant” barrier.
How man seals does each Airlock Door have?
2 seals per door, each providing full redundant Containment Integrity.
What system supplies air to the Airlock Door Seals?
The Instrument Air System(VI)