Joining A Vessel Flashcards
1
Q
What is the handover procedure, is there any legislation?
A
- Go to the engine room and have an induction of the engine room
- Look over log books, tank levels, oil record book, ensuring all is signed and upto date
- Discuss with the engineering department of any known issues and information
- Sit down with the captain and 2nd engineer to discuss work list, project and time frame
- Meet with project managers to discuss contractor schedules and ship yard schedules to find out any major issues or items that need attention.
- Check all safety procedures are followed and implemented
- Inspect all engine room certificates are up to date
- Print your copy of standing orders and sign
- Start working on a job list and plan
- Create a list of questions that you need more information/ clarifying with the Captain/ Project Manager or Engineering department.
2
Q
What certificates are you interested in?
A
- International Oil Pollution Prevention Certificate (IOPP
Certificate) - International Sewage Pollution Prevention Certificate
- International Air Pollution Prevention Certificate
- Engine International Air Pollution Prevention Certificate
- International Energy Efficiency Certificate
- International Load Line Certificate
- Ship Sanitation Control Exemption Certificate