Glencoe: 6 Flashcards

1
Q

CSI MasterFormat Checklist:

A

The Construction Specificiations Institute’s standard that organanizes all aspects of construction into 16 main categories.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Sources for cost information: Gathering information about the exact cost of materials and labor can be time-consuming. The estimator must check at least these 4 sources:

A

Material Suppliers

Prior Bids

Pricing Guides

Online Databases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Scheduling:

A

Organizes the construction process so the contractor can make the most efficient use of resources. It also enables the builder to determine when the project is ahead or behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Two elements must be scheduled when building a home:

A

Materials and activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Material Scheduling:

A

General must order and store materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Material Schedule First Load:

A

All items needed to complete the house up to an including the subfloor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Material Schedule second Load:

A

Wall framing and ceiling joists

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Material Schedule third Load:

A

roof framing materials and roof coverings. If roof trusses are used these will be shipped to the site on a special truck. This truck sometimes has a crane to lift trusses into position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Material Schedule fourth Load:

A

exterior doors, windows, exterior trim, and siding, as needed after the house has been enclosed with doors and windows and can be locked up, the interior wall finish is applied. If the walls are plastered, adequate drying time must be allowed before additional material shipments are made.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Material Schedule fifth Load:

A

hardwood flooring and underlayment materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Material Schedule sixth Load:

A

interior doors, trim, and built in cabinet materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Activity Scheduling:

  1. Survey:
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Activity Scheduling:

  1. Permit:
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Activity Scheduling:

  1. Excavation:
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Activity Scheduling:

  1. Temporary Power:
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Activity Scheduling:

  1. Temporary Water:
A
17
Q

Activity Scheduling:

  1. Foundation:
A
18
Q

Activity Scheduling:

  1. Plumbing:
A
19
Q

Activity Scheduling:

  1. Slabs:
A
20
Q

Activity Scheduling:

  1. Framing:
A
21
Q

Activity Scheduling:

  1. Backfilling:
A
22
Q

Activity Scheduling:

  1. Mechanicals:
A
23
Q

Backfill Timing:

A
24
Q

Activity Scheduling:

  1. Windows and Doors:
A
25
Q

Activity Scheduling:

  1. Roofing and Siding:
A