Glencoe: 6 Flashcards
CSI MasterFormat Checklist:
The Construction Specificiations Institute’s standard that organanizes all aspects of construction into 16 main categories.
Sources for cost information: Gathering information about the exact cost of materials and labor can be time-consuming. The estimator must check at least these 4 sources:
Material Suppliers
Prior Bids
Pricing Guides
Online Databases
Scheduling:
Organizes the construction process so the contractor can make the most efficient use of resources. It also enables the builder to determine when the project is ahead or behind schedule.
Two elements must be scheduled when building a home:
Materials and activities
Material Scheduling:
General must order and store materials
Material Schedule First Load:
All items needed to complete the house up to an including the subfloor
Material Schedule second Load:
Wall framing and ceiling joists
Material Schedule third Load:
roof framing materials and roof coverings. If roof trusses are used these will be shipped to the site on a special truck. This truck sometimes has a crane to lift trusses into position
Material Schedule fourth Load:
exterior doors, windows, exterior trim, and siding, as needed after the house has been enclosed with doors and windows and can be locked up, the interior wall finish is applied. If the walls are plastered, adequate drying time must be allowed before additional material shipments are made.
Material Schedule fifth Load:
hardwood flooring and underlayment materials
Material Schedule sixth Load:
interior doors, trim, and built in cabinet materials
Activity Scheduling:
- Survey:
Activity Scheduling:
- Permit:
Activity Scheduling:
- Excavation:
Activity Scheduling:
- Temporary Power: