Decrease in Inventory TAA Flashcards
For a LCLOCA what is the assumed failure and why?
- LOOP
- has adverse impact on core re-flood
For a LBLOCA, what is the Design SI Flow Assumptions?
- 75% flow from 2 HPSI (25% out the break)
- 100% flow from 1 LPSI
- 50% flow from 1 LPSI
- 100% from 3 SITS
For a SBLOCA what is the assumed failure?
- LOOP & loss of 1 DG
What is the design criteria for ECCS?
- Max cladding temp - ≤ 2200°F
- Oxidation of cladding - ≤ 17%
- ≤ 1% of cladding reacts to produce H2
- Maintain coolable geometry
- Long-Term cooling
During a SBLOCA what is credited for the RCS Heat Removal Safety Function management?
SBLOCA
- 2 phase natural circ
- SI Flow
- SG’s
LBLOCA
- ECCS thru core and out break
- SDC HX once on recirc (RAS)
When is an RCS cooldown performed following a LOCA?
- 1 Hour
During a LOCA, what is the purpose of CS?
- CTMT integrity
- Prevents H2 gas pockets (mixes atm)
- Scrubs Iodine from atm
For Decrease in Inventory TAA, what is the assumed failure for a LD line break outside of CTMT?
CHB-515 does NOT auto close on High RHX outlet temperature
How long do you have to isolate a LD leak outside of CTMT?
- 10 minute TCA
What are the 5 phases of mass energy release during a LOCA?
Blowdown Phase - Initial leak, cladding cooled by leakage
Refill phase - Refilling core downcomer, not fuel cladding heats up
Re-flood phase - SITS refill core cladding begins cooling
Post Re-flood phase - Total core coverage with HPSI/LPSI
Long Term period - Restores CTMT press.