What is the Entry Criteria for 40EP-9EO09 Functional Recovery?
- ELAP is NOT in progress
- SPTA’s complete
- M3/4 with LTOP not in svc
- Cannot identify issue
- SFSC’s not met
- Multiple events
During 40EP-9EO09 Functional Recovery, what steps are covered by Section 3.0 Entry Procedure?
- Monitor RCP trip criteria
- Open SG sample vlvs
- H2 anal in svc
- identify path
- S/U NI in svc
- BDAS in svc
- FLEX HVAC for SWGR/ DC equip if needed
- Restore power to WRF
- Monitor if SAMG’s required (CET > 1200°F)
What 3 steps are pulled forward prior to Section 3.0?
- Stopping RCP’s on LOAF
- Feeding Ruptured/ Faulted SG (1360 - 1600 gpm)
- Isolate HPSC leak
During 40EP-9EO09 Functional Recovery, what is the Success path prioritization?
- Jeopardized
- Challenged
- Not impaired
During 40EP-9EO09 Functional Recovery, which success paths require no further action once met (shaded)
- RC-1 - CEA insertion
- MVAC-1 - Off-site power
- MVAC-2 - DG power
- CI - CNTMT isolation
During 40EP-9EO09 Functional Recovery, who directs the performance of each success path?
- CRS
During 40EP-9EO09 Functional Recovery, Who can the CRS delegate non-jeopardized success paths to?
- Other available licensed operators
- BOP/OATC/STA address jeopardized funcitons
During 40EP-9EO09 Functional Recovery, what action is required if Rx Power criteria in NOT met for Reactivity Control?
- Stabilize Tc
- Borate
During 40EP-9EO09 Functional Recovery, What is the minimum RWT level to use CH pumps as a boration path?
What is the minimum SFP level?
- RWT > 44%
- SFP > 133’ 6”
During 40EP-9EO09 Functional Recovery if using the HPSI pump for boration, what is the minimum flow?
- ≥ 75 gpm
- Sq root extractor minimum
- Ensures > 40 gpm
During 40EP-9EO09 Functional Recovery, which DG’s from another unit can be cross connected?
True of False during 40EP-9EO09 Functional Recovery, MVAC and MCDC must be satisfied from the same train?
- True
During 40EP-9EO09 Functional Recovery, if Vital Battery Chargers cannot be restored in 2 hours, what actions must be performed and why?
- Vent SIT’s
- Prevents N2 injection to RCS
During 40EP-9EO09 Functional Recovery, what is the minimum HPSI Flow if SBOG’s are providing power to the HPSI pump?
- > 165 gpm
- Use RCGVS to lower pressure if needed
During 40EP-9EO09 Functional Recovery, what are the required conditions to use CSP for RCS injection?
- Ppzr < 220 psia
- LPSI not available
- CSP not needed
- CSP needed for IC
- RAS not actuated
- CS flow < 5000 gpm (pump damage)