40AO-9ZZ23 Loss of SFP Level or Cooling Flashcards

1
Q

What are the entry conditions for 40AO-9ZZ23 Loss of SFP LEVEL?

A
  • Lo-Lo level alarm (<137’)
  • Visual level lowering
  • Fuel Bldg sump
  • Continuous discharge from liner drain
  • FBEVAS or CREFAS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the entry conditions for 40AO-9ZZ23 Loss of SFP COOLING?

A
  • Hi temp alarm
  • PC low disch press alarm
  • PC pump trip
  • Loss of power to pumps (L31/L36)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the EXIT condition for 40AO-9ZZ23 Loss of SFP COOLING

A
  • < 145°F

- PC cooling restored

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the NORMAL level in the SFP

A
  • 138’ 1”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the LCO limit in the SFP? (3.7.14)

A
  • 23’ above F/A

- 137’4”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the SFP Lo-Lo level?

A
  • 137’
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

At what level in the SFP does the PC cooling pump loose suction?

A
  • 131’ 10”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the lowest level in the SFP that could occur due to a pipe break/ valve misalignment?

A

130’ 2”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the SFP temperature limits/alarms?

A
  • High - 125

- Hi-Hi - 145

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Design basis time to boil in the SFP?

A
  • 16.7 hours - M1-4

- 3.46 hours - full core offload

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the mitigating actions for Loss of SFP level or cooling?

A
  • Close roll up door
  • place F/A in safe position
  • Evacuate non-essential in Fuel Bldg
  • RP monitor Rads
  • Actuate FEBEVAS and CREFAS for Rad levels
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the BORATED m/u sources for the SFP

A
  • BAMP from RWT
  • BAMP through Batch tank eductor
  • Gravity from RWT
  • CSP/ LPSI from RWT
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the UNborated m/u sources for the SFP

A
  • DWST
  • RMT
  • RMWP from RMWT
  • CST
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When should an UNborated m/u source NOT be used for SFP m/u?

A
  • SFP < 3000 ppm boron
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How is SDC/ LPSI/ CSP impacted by being aligned to the SFP?

A
  • Results in SDC/LPSI/CSP inoperability

- Does NOT make SDC non-functional

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

During 40AO-9ZZ23 Loss of SFP Level or Cooling, what SFP temperature would require the evacuation of non-essential personnel?

A
  • 180°F