40AO-9ZZ16 RRS Malfunctions Flashcards
1
Q
For RRS Malfunctions (40AO-9ZZ16) what is the first mitigating step?
A
Ensure CEDMCS is NOT in AS
2
Q
For an uncontrolled CEA withdrawal when is prompt and prudent action allowed?
A
Motion:
In - In the book, use AOP
Out - out of the book, Prompt and Prudent
3
Q
For RRS Malfunctions (40AO-9ZZ16), what condition could affect COLSS?
A
-If a failed instrument is failed, but still reading in normal range
4
Q
During a Turbine Load Index (TLI) Failure what action should be taken if SBCS responds?
Why?
A
- Remove SBCS from Remote-Auto
- changes to SBCS Master Controller signal when in 1E could cause perturbations in DFWCS, may result in a Rx trip.
5
Q
What are the Upper and Lower limits for TLI(Tref)
A
- 564°F
- 587°F