Tech Spec 3.2 Flashcards

1
Q

What is the section heading for Tech Spec 3.2

A

Power Distribution Limits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

List the requirements, actions, and completion times for LCO:

3.2.1 Linear Heat Rate (LHR)

A

U1
3.2.1 - Linear Heat Rate (LHR)
The linear heat rate limit shall be maintained in accordance with core burnup:
13.1 kW/ft for burnup < 475 EFPD
12.3 kW/ft for burnup ≥ 475 EFPD
U2 <13.1
U3
3.2.1 - Linear Heat Rate (LHR)
The linear heat rate limit shall be maintained in accordance with core burnup:
13.1 kW/ft for burnup < 450 EFPD
12.1 kW/ft for burnup ≥ 450 EFPD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List the requirements, actions, and completion times for LCO:

3.2.2 Planar Radial Peaking Factor

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List the requirements, actions, and completion times for LCO:

A

B. (continued) B.2 Reduce Variable
Overpower trip setpoints to
55% RTP.
AND
16 hours
B.3 Restore the measured Tq to
less than the Tq allowance
used in the CPCs.
AND
Prior to increasing
THERMAL POWER
B.4 Correct the cause for
measured Tq not within
limit.
AND
Prior to increasing
THERMAL POWER
> 50% RTP.
B.5 Subsequent to power
operation > 50% RTP,
verify measured Tq is within
the limit.
Once per hour for
12 hours
OR
Until verified at
95% RTP
C. Required Actions
and associated
Completion Times
not met.
C.1 Reduce THERMAL
POWER to 20%.
6 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly