Refueling Machine and Operations Flashcards

1
Q

Who must be present for refueling operations to occur?

A

A licensed Reactor Operator: located in the Control Room

Reactor Engineering Technician

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is required to use the INTERLOCK OVERRIDE on the refueling machine?

A

CRS/SM concurrence (unless an emergency), unless directed by procedure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the limit to get a Fuel Transfer Overload on the Fuel Transfer Machine?

A

800 lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the required response if startup channel counts increase during fuel insertion?

A

IF during insertion of a fuel assembly, the sustained count rate from either or both startup channel increases by a factor of five (5) from the last stable counts, excluding anticipated changes due to spatial effects, THEN perform the following:
1. Withdraw the fuel assembly immediately.
2. Discontinue CORE ALTERATIONS.
3. REFER TO Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Do “Core Alteration” requirements apply to the last Fuel Assembly removed or the first Fuel Assembly inserted?

A

No
Per 40OP-9ZZ23

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who approves Altering Fuel Movement?

A

Approved by Reactor Engineering and Refueling SRO. Verbally approved by SM/CRS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Refueling Boron Concentration minimum? (LCO 3.9.1)

A

3,000 ppm. If not met immediately stop core alts. Emergency borate at least 26 gpm from 4,000 ppm source.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the minimum keff during refueling (LCO 3.9.1)?

A

less than or equal to 0.95 keff during fuel handling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the communication requirements per TLCO 3.9.100 during Core Alterations?

A

Control Room and refueling station (CTMT and FB) during core alt. Verified within 1 hour prior to core alts then every 12. If lost immediately suspend core alts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the minimum decay time required per TLCO 3.9.100 before moving irradiated fuel assemblies in the vessel?

A

Subcritical for greater than or equal to 100 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the weight limit of TLCO 3.9.103 Crane Travel - SFP Storage Building?

A

Loads greater than 2,000 pounds prohibited from travel over fuel assemblies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Overload Hoist Interlock on the Refueling Machine?

A

Fuel only region. Hoist will stop motion if weight indication is > 150 pounds more than the weight of the grapple, hoist box, and fuel (maximum setting for fuel only is 1600 lbs).