LAW P3 CONTRACT CASES (DISCHARGE) Flashcards
What is the case for discharge by performance exception (severable contracts)
Ritchie v Atkinson, the claimant is entitled to payment for the amount supplied
What is the case for discharge by performance exception (substantial performance)
Hoeing v Isaacs, the claimant had substantially performed the contract and was therefore entitled to the contractually agreed price minus the cost of the defects
What is the case for discharge by performance exception (acceptance of partial performance)
Sumpter v Hedges, the defendant had no choice but to accept partial performance as he was left with a half completed house on his land
What is the case for discharge by performance exception (tender of performance)
Startup v Macdonald, the claimant had tendered performance within the agreed contractual period and was thus entitled to damages for non acceptance
What is the case for discharge by performance exception (performance prevented by the promisee)
Planche v Colburn, the claimant was entitled to recover £50 because the defendant had prevented the performance
What is the case for discharge by agreement (satisfaction)
Williams v Roffey, consideration must be provided to end a contract
What is the case for discharge by breach (anticipatory breach)
Hochester v de la tour, the court held that D was liable for breach which removed Cs obligation to perform the contract
What is the case for discharge by frustration (impossibility)
Taylor v Caldwell, a contract may become impossible to perform wher the subject matter is destroyed
What is the case for discharge by frustration (illegality)
Spolka v Fairbairn, the contract was no longer possible to perform because of the supervening illegality
What is the case for discharge by frustration (radical change)
Krell v Henry, cancellation of the procession deprived it of its commerical purpose
What is the case for limits of frustration (foreseeable)
Amalgamated investment v john walker, a building was listed as ‘historic’ after a contract was signed but this was foreseeable
What is the case for limits of frustration (self induced)
Maritime national fish v ocean trawlers, D caused the issue themselvges so could not claim frustration
What is the case for limits of frustration (more difficult or expensive)
David contractors v Fareham UDC, the contract became harder to perform but frustration was not allowed