LADDERS 6 - TOWER LADDER OPERATIONS Flashcards

1
Q

Lieutenant Jones is working a day tour in TL100 and has just arrived at a fire on the 3rd floor of a 6 story MD. The street is not level and the Officer’s side of the rig is lower than the LCCs side of the rig. In this situation, the Lieutenant would be most correct to give his LCC the following order?

A) Lower the jacks and outrigger on the low side 1st, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed.

B) Lower the jacks and outrigger on the high side 1st, followed by the jacks and outrigger on the low side until the green lights indicate that all stabilizers are properly deployed.

C) Lower the jacks and outriggers at the same time until the green lights indicate that all the stabilizers are properly deployed.

D) Lower all the jacks first and then lower both outriggers at the same time until the green lights indicate that all the stabilizers are properly deployed.

A

ANSWER: A) Lower the jacks and outrigger on the low side 1st, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed.

(FFP - TL 6 - 1.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Jacks and outriggers on the TL are controlled either through individual levers or an “all jacks” lever which operates all the jacks and outriggers simultaneously. When the TL is on level ground the preferred method to lower the jacks and outriggers can be found in which choice?

A) Use the individual levers to lower the jacks first and then lower the outriggers.

B) Use the “all jacks” lever to lower all the jacks and outriggers simultaneously.

C) Use the individual levers to lower the outriggers first and then lower the jacks.

D) Use all the individual levers at the same time to lower all the jacks and outriggers simultaneously.

A

ANSWER: B) Use the “all jacks” lever to lower all the jacks and outriggers simultaneously.

(FFP - TL 6 - 1.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Members of TL99 were conducting MUD with E99 when they started to teach the members of E99 about TL placement, set up and basic operations. Which is the only correct point regarding the information given in this drill?

A) A guide firefighter, typically the Roof FF, should assist the LCC in positioning the apparatus so that the outriggers will clear parked cars and other obstructions such as curbs or manholes.

B) The guide FF is to remain in position until the outriggers are completely lowered on both sides of the TL. The guide FF should remain with the LCC until released for other FF duties.

C) If a member commences to set up a TL for an operation and then decides to abort the operation, the member must return all outriggers and jacks to the pre- set up position.

D) When operating with a 75’ or 95’ TL, a 6’ hook may be used as a gauge to determine if the outriggers will clear all obstructions. If the apparatus is set on an angle ensure that the measurement is taken from the part of the outrigger that is nearest the obstruction.

A

ANSWER: C) If a member commences to set up a TL for an operation and then decides to abort the operation, the member must return all outriggers and jacks to the pre- set up position.

A - Guide FF is typically the OUTSIDE VENT FF

B - Guide FF remains in position until the outrigger are fully lowered on the OPERATOR’S BLIND SIDE.

D - 75’ TL you can use 6’ hook as guide / For 95’ TL you need 6’8” of clearance so you cannot use the 6’ hook.

(FFP - TL - 1.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

FF Bongino is a new TL LCC and is driving on the 9x6 tour. After arriving at a small fire in a vacant Rowframe, he and the proby, who has the OV for the first time, are in the process of setting up the TL. FF Bongino would be correct to tell the proby which of the following? (More than 1 correct)

A) The preferred placement of the manual pins for outriggers shall be at the lowest hole available once extended. The preferred placement of manual pins for jacks shall be the highest slot available once extended.

B) The preferred placement of the manual pins for outriggers shall be at the highest hole available once extended. The preferred placement of manual pins for jacks shall be the lowest slot available once extended.

C) The controls at the pedestal will allow for smoother positioning than the joystick controls in the bucket. For this reason the pedestal FF should, in most cases, perform delicate movements.

D) The joystick controls will allow for smoother positioning than the controls at the pedestal. For this reason the basket FF should, in most cases, perform delicate movements.

A

ANSWER: A and C are CORRECT

A) The preferred placement of the manual pins for outriggers shall be at the lowest hole available once extended. The preferred placement of manual pins for jacks shall be the highest slot available once extended.

C) The controls at the pedestal will allow for smoother positioning than the joystick controls in the bucket. For this reason the pedestal FF should, in most cases, perform delicate movements.

(FFP - TL 6 - 1.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lt. O’Reilly is working a 6x9 tour in TL99 and just arrived at a fire on the 6th floor of a 6 story “H” type where it appears the fire has entered the cockloft and the TL is going to be used. As the LCC steps off the rig he steps into a large pothole and breaks his ankle. EMS removes him to the hospital. In this situation who should Lt. O’Reilly designate to operate the turntable for this operation?

A) FF Gray who has 20 years on the job and is assigned to E99.

B) FF Ingram who has 20 years on the job and is assigned to L100 an Aerial ladder.

C) FF Levine who has 2 years on the job and is assigned to L98, an Aerial ladder, and is a LCC.

D) FF Sexton from E99 who has 10 years on the job and is on a long term detail to TL99.

A

ANSWER: C) FF Levine who has 2 years on the job and is assigned to L98, an Aerial ladder, and is a LCC.

  • Detailed members should not operate on the turntable unless they are presently assigned to a Tower Ladder unit or are a qualified Chauffeur-Tiller (QCT, School Trained).

(FFP - TL 6 - 1.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The bucket is the primary work area for the TL apparatus. Mounted inside the bucket is a single handed joystick used to control movement from an elevated position. Which point about the bucket and bucket operations is not entirely correct?

A) Each member operating a TL bucket must personally verify the placement of both door latches in the locked position prior to movement.

B) Bucket railings are not a substantial part of the bucket and shall not be used as a substantial object when tying off.

C) Under normal conditions the member operating from an elevated position should control movement of the bucket. The member on the pedestal should take over when delicate maneuvers are required.

D) Due to the lack of space in the bucket, the number of FFs operating in the bucket should be limited to three.

A

ANSWER: D) Due to the lack of space in the bucket, the number of FFs operating in the bucket should be limited to three. (INCORRECT)

  • Limited to TWO (2) FFs in the bucket.

(FFP - TL 6 - 1.3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The TL is provided with an intercom system that allows for bucket to pedestal communications. This should be the primary means of communication between the bucket and the pedestal as it is the most effective and will limit radio traffic on the Handie Talkie. Which point below is correct regarding the communications system in the TL?

A) A test of the intercom system shall be made each tour and at the initial stages of placing the TL into operation. If the results are negative members shall rely on the HT tactical channel during operations. When communicating the reference point is always the pedestal, not the bucket position.

B) A test of the intercom system shall be made each weekly and at the initial stages of placing the TL into operation. If the results are negative members shall not use the TL. When communicating the reference point is always the bucket, not the pedestal position.

A

ANSWER: A) A test of the intercom system shall be made each tour and at the initial stages of placing the TL into operation. If the results are negative members shall rely on the HT tactical channel during operations. When communicating the reference point is always the pedestal, not the bucket position.

(FFP - TL6 - 1.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Arriving 1st usually allows the choice of position best suited for initial TL operations. Officers and LCCs are to maintain situational awareness and not impede the accessibility of hydrants for Engine company use. Which point below regarding TL positioning is incorrect?

A) Careful consideration should be given to the operations of TLs during severe lightning storms. The apparatus is grounded and usually wet during stream operations.

B) The TL apparatus should not be placed on any sidewalk either fully or partially. Some buildings have underground vaults which can collapse under the weight of the TL or an outrigger.

C) Generally, the apparatus should be placed parallel to the building. Occasionally, the scrub area of the bucket will be reduced by the cab of the apparatus. This can be corrected by parking the apparatus with the front end angled away from the building line.

D) Positioning the TL at a corner building afford coverage on two fronts. Generally the boom has enough clearance to reach most 3rd floor windows and above when operating over the crew cab.

A

ANSWER: B) The TL apparatus should not be placed on any sidewalk either fully or partially. Some buildings have underground vaults which can collapse under the weight of the TL or an outrigger. (INCORRECT)

  • The Tower Ladder apparatus MAY BE PLACED on the sidewalk either fully or partially to reach upper levels or to gain better vantage points. In this situation, verify the
    condition under the sidewalk and make certain that the jacks and outriggers are on a firm foundation.
  • Some buildings (e.g. Older Cast Iron Lofts) may have underground vaults. Improper apparatus positioning and outrigger placement may collapse vaulted sidewalks.
    Tower Ladders shall NOT be placed on sidewalks containing underground vaults.

(FFP - TL6 - 2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Observing the relationship of the objective (e.g window) to the lines in the sidewalk may assist LCC with initial positioning of the TL. The ideal horizontal distance from the center line of the turntable to an objective is _____ feet. When the center line of the turntable is _____ feet from the building, there will be sufficient room for the TL bucket to be dropped below the horizontal with the boom perpendicular to the side of the apparatus.

A) 25’ / 32’

B) 35’ / 30’

C) 30’ / 25’

D) 32’ / 25’

A

ANSWER: D) 32’ / 25’

  • Cross reference with Ladders 2 Aerial Ladders
  • Aerial = 25’ to 35’ from building

(FFP - TL6 - 2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When operating with a TL at a fire in a Brownstone, the TL provides an excellent platform for top floor VEIS and cornice operations. Which point below about using the TL at a fire in a Brownstone is incorrect?

A) Particular attention should be given to the small bedroom having their only entrance from the hall.

B) A “backing in” maneuver may permit booming under the 1st arriving Aerial ladder.

C) Where large trees prohibit positioning, stopping before the objective and booming over the cab may present a viable option.

D) The LSR and saw shall be taken to the roof when the bucket is used for roof access. Prompt repositioning of the bucket for top floor VEIS is essential.

A

ANSWER: C) Where large trees prohibit positioning, stopping before the objective and booming over the cab may present a viable option. (INCORRECT)

  • Stopping PAST the objective and boom over the REAR of the cab may present a viable option.

(FFP - TL6 - 2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Members of TL99 are discussing a recent operation where members rescued numerous civilians from a fire on the 4th floor of a 5 story OLT. FF Jones is a brand new LCC and was asking FF Stein, a regular LCC in TL99, what is the preferred method to rescue victims with the TL bucket. FF Stein would be most correct to tell FF Jones?

A) The preferred method of rescue is a straight on approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends for the rescue.

B) The preferred method of rescue is an angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends for the rescue.

C) The preferred method of rescue is a straight on approach where the member operating the bucket first raises the bucket up to the victim’s level, and within the victim’s reach, and then extends for the rescue.

D) The preferred method of rescue is an angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out within the victim’s reach, and then extends for the rescue.

A

ANSWER: B) The preferred method of rescue is an angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends for the rescue.

  • ANGULAR / OUT OF VICTIMS REACH

(FFP - TL6 - 2.1.3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When operating at fires in “H” types the TL can be a tremendous asset to our operations. Which point below is incorrect when operating the TL at an “H” type building?

A) At fires in “H” type buildings, it is often beneficial to position the TL to cover the “throat” of the building.

B) The positioning of the TL in the courtyard or rear lot of an “H” type building can be used to prevent the spread of fire across the throat.

C) Potential long stretches in “H” type buildings require constant communications between ECC and LCCs. The TL LCC should not delay positioning of the TL and the Engine company should not interfere with the placement of the TL.

D) Consider the possibility of operating from an adjacent street over the top of lower buildings into the throat, rear, or side of the fire building should not be overlooked.

A

ANSWER: C) Potential long stretches in “H” type buildings require constant communications between ECC and LCCs. The TL LCC should not delay positioning of the TL and the Engine company should not interfere with the placement of the TL. (INCORRECT)

  • The Ladder Company chauffeur should be PATIENT AND ANTICIPATE A DELAY in positioning in the throat, allowing the Engine to complete a backstretch.

(FFP - TL6 - 2.1.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Captain Hannity is working a day tour in TL100 and has just arrived 1st due to a fire in an old Gothic style church. Exposure 1 is a street, exposure 2 is a large parking lot, exposure 3 is a small rear yard and exposure 4 is a street. Captain Hannity would be most correct to order the TL placed in which location?

A) Directly in front of the church to provide ventilation of the Rose window and the roof.

B) At the exposure 1/4 corner to cover two side of the building and provide ventilation of the rose window and the roof.

C) In the exposure 2 parking lot in order to provide roof and window ventilation.

D) Take a preliminary position in front of the church and await the arrival of the IC so he can direct TL placement.

A

ANSWER: B) At the exposure 1/4 corner to cover two side of the building and provide ventilation of the rose window and the roof.

  • At fires in Places of Worship, the Tower Ladder should be positioned to cover two sides of the building and provide ventilation of the roof and rose window

(FFP - TL6 - 2.1.8)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When positioning the TL on a hill, there are certain guidelines that must be followed in order to ensure a safe operation. From the choices below, please choose the incorrect point when positioning the TL on a hill.

A) Position the apparatus parallel to the direction of the slope so that boom operations will be in the uphill direction.

B) All boom operations should be performed delicately and at low speed while on steep inclines. All sudden movements should be avoided.

C) Retracting and/or raising of the boom may be required for uphill operation as this will allow the load to rotate on a shorter radius thereby reducing torque requirements for uphill rotation.

D) The apparatus must always face in the downhill direction. When facing downhill the turntable should be past the objective.

A

ANSWER: D) The apparatus must always face in the downhill direction. When facing downhill the turntable should be past the objective. (INCORRECT)

  • IF POSSIBLE the apparatus should be facing in the downhill direction , past the objective with boom operations in the uphill direction.

(FFP - TL6 - 2.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

At a recent fire in a junkyard the IC ordered Lt. Smith and his mmebers of TL 98 to place the apparatus in the vacant lot next to the junkyard in order to extinguish the fire. When positioning the TL in a vacant lot, all but which of the following precautions should be taken?

A) When positioned in lots, the boom should be operated at right angles to the chassis at low elevations; it should not be operated at narrow angles over the front and rear of the apparatus.

B) The Officer and LCC must conduct a survey for potential collapse zones and voids such as a cellar under a foundation, drywells and cesspools.

C) Where the ground is of doubtful stability, such as a junkyard, it may be more advantageous to position the apparatus perpendicular or nearly perpendicular to the fire building as this will tend to equalize pressure on the outriggers resulting from lateral movement of the apparatus.

D) Shoring placed under outriggers and jacks will provide greater stability. SOC may be able to facilitate operations where extensive shoring is required.

A

ANSWER: A) When positioned in lots, the boom should be operated at right angles to the chassis at low elevations; it should not be operated at narrow angles over the front and rear of the apparatus. (INCORRECT)

  • SHOULD NOT BE operated at right angles
  • SHOULD BE operated at narrow angles over front/rear

(FFP - TL6 - 2.5)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Live overhead wires can present a problem if they fall onto the TL apparatus. It is possible for the apparatus to become energized, particularly if the jacks and outriggers are down in place. If this should occur members should take all but which of the following actions?

A) Notify the IC of the condition by transmitting a MAYDAY message. The IC should then notify all members that the TL is OOS.

B) No member shall touch the apparatus; also consider supply line and the supply pumper. Safeguard civilians and other unsuspecting members.

C) Any members already in position on an energized apparatus should attempt to remain in place and are not touched until power has been removed.

D) Immediately request a priority response of the Utility company.

A

ANSWER: A) Notify the IC of the condition by transmitting a MAYDAY message. The IC should then notify all members that the TL is OOS. (INCORRECT)

  • Transmit an URGENT

(FFP- TL6 - 2.7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Members of TL 100 are operating at a 10-75 with the TL bucket raised to the roof. The two members operating in the bucket suddenly hear scraping noises and notice the boom movement appears stalled. They now believe that the bucket is wedged and stuck. In this situation they would be correct to think which of the following?

A) The IC must be notified with a MAYDAY message indicating the “bucket is wedged”

B) Both members in the bucket should immediately crouch, sit, or otherwise remain low.

C) Both members in the bucket must verify they are secured to a bucket post or railing using the installed safety belt, life belt or personal harness.

D) The apparatus must be shut down and the PTO disengaged.

A

ANSWER: B) Both members in the bucket should immediately crouch, sit, or otherwise remain low.

A - Two NEW URGENTS - Bucket wedged and live wires dropping onto the T.L

C - Bucket Railing IS NOT SUBSTANTIAL / Use bucket post or waterway.

D - Apparatus must be shut / PTO REMAINS ENGAGED

(TL 6 - Ch.3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The TL bucket has many benefits when utilized properly and safely. Of the following choices, which one is incorrect?

A) PPE shall be worn at all times while operating in the bucket.

B) Whenever a TL operation is in progress, the pedestal position should be staffed. This provides an extra pair of eyes to warn of impending danger and override bucket controls in an emergency.

C) Each member operating in the TL bucket must personally verify the placement of both door latches and ensure proper use of the installed safety belt or life belt/personal harness secured to a substantial part of the bucket (one of the bucket posts or railings) prior to raising the boom from the bedded position.

D) Consideration should be given to using the TL bucket to return personnel and equipment from upper levels of a building to ground level. This is particularly appropriate at vacant buildings and extensively damaged buildings where visibility is limited, and the stability of the stairs are in doubt.

A

ANSWER: C) Each member operating in the TL bucket must personally verify the placement of both door latches and ensure proper use of the installed safety belt or life belt/personal harness secured to a substantial part of the bucket (one of the bucket posts or railings) prior to raising the boom from the bedded position. (INCORRECT)

  • One of the bucket posts or WATERWAY
  • Railing on TL Bucket is NOT SUBSTANTIAL.

(FFP - TL 6 - ch 3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Operating from a TL bucket offers many benefits to well trained members. Which choice below is not in accordance with Department policy?

A) Prior to gaining entry by way of the bucket, members should clear the entire window. Setting the end of a 6’ hook firmly into the corner of a windowsill, and/or placing the bucket cord light into the window to be entered, may offer a reference point in the event of a hasty retreat is required.

B) When there is a need to search an adjoining area or room in an area accessed via the bucket, it is sound practice to exit the IDLH and reposition the bucket to the appropriate window.

C) When size-up indicates a need to employ a tactical two member approach from the bucket, one member remaining in the bucket is a distinct safety and overall tactical advantage. When a decision is made to operate in this manner, the IC shall immediately be notified.

D) When permission is granted for VEIS, the priority action will be to isolate the area by closing a door. It is essential for the Bucket Firefighter to remain in visual contact with the member conducting a search. Both members must maintain heightened situational awareness.

A

ANSWER: D) When permission is granted for VEIS, the priority action will be to isolate the area by closing a door. It is essential for the Bucket Firefighter to remain in visual contact with the member conducting a search. Both members must maintain heightened situational awareness. (INCORRECT)

  • Must remain in VOICE contact with the member conducting the search.

(TL 6 - ch 3 3.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

A TL Bucket provides a steady platform to reach windows and other accessible areas normally out of reach. Which choice below contains incorrect information regarding this procedure?

A) When the bucket is properly positioned at a window, immediate HT notification to the company officer will alert members of the additional means of egress (“Ladder 100 LCC to Ladder 100, the bucket is at the window if you need it”)

B) When a member enters a window from a TL bucket for VEIS, the bucket shall not be moved unless required for rescue purposes. When required to reposition the bucket for rescue, immediate notification to the member(s) who entered the window from the bucket shall be made and the bucket returned to the window (or replaced with another aerial/portable ladder) as soon as possible.

C) Rescue via the bucket may be achieved by positioning the top of the bucket at a level where a person can easily step into it without straddling the windowsill or fire escape railing.

D) When multiple trips of the bucket are required to remove a large number of occupants, removal directly to street level may not be necessary or practical. When time is critical, occupants may be removed to lower levels of the fire building, across the throat to an opposite wing, to an adjoining roof, fire escape or other safe refuge area.

A

ANSWER: C) Rescue via the bucket may be achieved by positioning the top of the bucket at a level where a person can easily step into it without straddling the windowsill or fire escape railing. (INCORRECT)

  • Position the MIDDLE OF THE BUCKET at a level where a person can easily step into it without straddling the window sill or fire escape railing.

(TL 6 - ch 3 3.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Proper positioning and use of the TL bucket is necessary for a successful operation. Of the following choices, which is not entirely correct?

A) To expedite placing the bucket to a window, position the apparatus parallel to the objective while lining the turntable up with the window.

B) When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite it preceding movement (e.g. after extending the boom to reach a window, the subsequent move should generally be to retract)

C) To remove victims from bridges, elevated tracks and highways, and buildings under construction, place the TL in a strategic location directly below the area involved. Use the bucket as an exterior elevator but do not extend the bucket over a roadway or elevated track.

D) When placed to the roof for access, the preferred positioning is with the bucket over the roof, parapet or cornice and the gate parallel to the roofline.

A

ANSWER: A) To expedite placing the bucket to a window, position the apparatus parallel to the objective while lining the turntable up with the window. (INCORRECT)

  • Line the BUCKET up with the window

(TL 6 - ch 3 3.3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The TL bucket may be utilized to assist in the removal of an incapacitated patient in a variety of situations such as construction accidents, collapse, obese patients, etc. Of the following choices, which contains correct information regarding this procedure?

A) Securing the patient into a SKED may facilitate a safe and professional operation and is the preferred removal method for incapacitated victims.

B) The stokes basket may be lashed to a substantial part of the bucket in an upright, horizontal or diagonal position. Horizontal positioning is preferred as it is the easiest and safest of the three options.

C) The apparatus should be positioned so that the center line of the turntable is at least 25’ to 30’ from the building; this will allow the bucket to reach street level and ensure a sufficient transfer to EMS.

D) To ensure a smooth operation, the Bucket FF should perform the lowering operation if conditions permit.

A

ANSWER: C) The apparatus should be positioned so that the center line of the turntable is at least 25’ to 30’ from the building; this will allow the bucket to reach street level and ensure a sufficient transfer to EMS.

A - Securing patient to a STOKES BASKET may facilitate a safe and professional operation.

B - DIAGONAL positioning is preferred as it is the easiest and safest of the 3 options.

D - The PEDESTAL FF should perform lowering operations if conditions permit.

(TL 6 - ch 3 3.3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The TL bucket may be beneficial for roof operations. However, strict adherence to Department policy should be followed. Of the following choices, which is incorrect?

A) The TL bucket may get caught on surfaces or objects due to the self leveling feature and the design of the “L” bracket attached to the underside of the bucket.

B) When utilized for roof access, once safe egress is confirmed (e.g. adjoining building or aerial ladder) prompt repositioning of the bucket to a fire apartment/floor above window provides a secondary means of egress for members operating on the interior. Notification shall be made to the Roof FF prior to the bucket being repositioned.

C) When no other option is available, members may escape from the bucket by means of escape ladder in the hinged position. Prior to exiting the bucket, members shall ensure that the apparatus remains in PTO, the engine is shut down and the escape ladder side rails are raised.

D) When preparing to move a properly positioned bucket from a roof, the first movement is generally to “RETRACT” the bucket.

A

ANSWER: D) When preparing to move a properly positioned bucket from a roof, the first movement is generally to “RETRACT” the bucket. (INCORRECT)

  • First movement is generally to RAISE the bucket.

(TL 6 - ch 3 3.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The power saw can be used effectively from the TL bucket to open peaked roofs. Which of the following tactics are correct when implementing this procedure?

  1. Position the bucket on the roof as close to the ridge pole as possible and check the stability of the roof with a tool. The saw operator shall wear the installed safety belt which allows enough play to reach the edge of the platform and still have one foot on the roof.
  2. If the safety belt is not used for any reason, the LSR shall be tied to a substantial part of the bucket with a bowline. The loop of the bowline should be large enough to reach the edge of the bucket platform and the saw operator hooks his or her personal harness to the loop in the LSR, and places one foot on the roof and the other in the bucket.
  3. The Guide FF, properly secured in the bucket, takes a firm hold on the operator’s personal harness or life belt. The saw is started outside the bucket and held outside for the duration of the operation until it is shut off.
  4. The area beneath the bucket shall be kept clear and a utility cord shall be attached to the Guide FF in the bucket.
  5. Make the 1st cut perpendicular to the ridge pole; the size of the cut will depend on the reach of the operator. Never overextend; reposition the bucket if a larger opening is necessary.
  6. Remove cut roofing with 6’ hooks and push down any ceiling below.

A) 1,2,4,6 B) 2,3,4,6 C) 1,3,5,6 D) 3,4,5,6

A

ANSWER: A) 1,2,4,6 (3 and 5 are INCORRECT)

3 - Saw started INSIDE the bucket and held OUTSIDE until shut off.

5 - Make the 1st cut PARALLEL to the ridge pole

(TL 6 - ch 3 3.5)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

If the TL bucket makes contact with a building, structure or other obstruction, there is a likelihood of the bucket becoming wedged or stuck. In the event that this occurs, members in the bucket should take all of the following actions except for which one?

A) Verify all members are secured to a substantial part of the bucket using the installed safety belt, life belt or personal harness.

B) Notify the IC (transmitting an “URGENT” message after depressing the EAB) of the condition.

C) Remain low in the bucket; all members should immediately crouch, sit or otherwise remain low in the bucket to lower their center of gravity in anticipation of possible sudden, violent movements.

D) PTO should be immediately disengaged and the apparatus shut down.

A

ANSWER: D) PTO should be immediately disengaged and the apparatus shut down. (INCORRECT)

  • Ensure Apparatus REMAINS IN PTO

(TL 6 - ch 3 3.6)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

The TL provides an excellent platform for overhaul operations including cornice securing/removal and exterior wood sheathing, siding and cockloft overhaul. Of the following choices, which is not in accordance with Department Policy?

A) A properly positioned bucket adhering to all safety guidelines provides a stable and secure area from which to work.

B) The area below the bucket shall be kept clear and an announcement shall be made over the HT when overhaul will commence.

C) The top of the bucket railing should be positioned slightly above the work area.

D) The boom shall not be used to force timbers or cornices back into a building or onto a roof, to pull or push objects, or as a derrick.

A

ANSWER: C) The top of the bucket railing should be positioned slightly above the work area. (INCORRECT)

  • Slightly BELOW the work area

(TL 6 - ch. 3 3.7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Only the IC may order the use of Large Caliber Streams (LCS); this may be the first arriving Officer. Because of this, which statements below are most correct regarding the appropriate supply method?

  1. Generally only one supply source at the base of the TL should be used. A Satellite Water Unit is the best source of supply if available; the largest diameter hose should be used.
  2. 100-150 psi is the recommended pressure at the gated inlet for an effective operation.
  3. The TL may be supplied at either side of the apparatus. The location of the fire building and the ability of the Pedestal FF to monitor the connection in the event corrective action is required are factors to consider.
  4. When stretching a 3 1/2” supply line to a TL, ensure the female end is stretched to the gated inlet.
  5. Water flow to the TL should be controlled at the supply source (e.g. Engine apparatus or Satellite Manifold). Water should always be shut down at the supply pumper.
  6. When repositioning the TL is required, this may be accomplished by disconnecting the 3 1/2” supply line at the base of the the TL apparatus. However, if the distance is short and sufficient slack remains in the supply line, the TL may be repositioned without disconnecting the supply line.

A) 1,3,5,6 B) 2,4,5,6 C) 1,2,3,5 D) 1,4,5,6

A

ANSWER: A) 1,3,5,6 ( 2 and 4 are INCORRECT)

2 - TWO HUNDERED TO TWO HUNDRED AND FIFTY (200-250 PSI) is the recommended pressure at the gated inlet.

4 - Ensure the MALE end of the 3 1/2” supply line is stretched to the hated inlet.

(TL 6 - ch. 4 4.1)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Prior to calling for water, members in the TL bucket are reminded to comply with each of the following procedures except?

A) Verify the use of the installed safety belt, life belt or personal harness secured to a substantial part of the bucket.

B) Enure the presence of the stream shaper and correct stacked tips necessary for the task. The stream shaper should normally be left in place to ensure a good quality stream with maximum reach.

C) Set and lock the monitor high into the air while awaiting water delivery. Pull the safety pin on the waterway if water will be applied below horizontal (e.g) junkyard fires, brush fires, etc.)

D) The platform monitor should be stationary when applying water. When necessary, the stream may be directed forward and upward with an aggressive side to side or counterclockwise rotation.

A

ANSWER: D) The platform monitor should be stationary when applying water. When necessary, the stream may be directed forward and upward with an aggressive side to side or counterclockwise rotation. (INCORRECT)

  • Monitor should be IN MOTION when applying water
  • Aggressive side to side or CLOCKWISE rotation.

(TL 6 - ch. 4 4.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Proper utilization of the TL LCS is necessary to successfully control and extinguish fire. Of the following choices, which is correct?

A) When the fire building is heavily involved or there are multiple floors of fire, LCS delivery should generally start at the highest level and work downward.

B) For an advances fire in a Rowframe, begin stream application at the first floor and work your way upward, operating into the cockloft last.

C) When common cockloft exposure protection is required, commence LCS attack at the middle and traverse towards the leading edge of the structure to facilitate extinguishment.

D) In extreme situations, the LCS directed through an attic window of a peaked frame dwelling can be used to ventilate by literally blowing off the roof.

A

ANSWER: D) In extreme situations, the LCS directed through an attic window of a peaked frame dwelling can be used to ventilate by literally blowing off the roof.

A - Heavily involved or multiple floors of fire LCS delivery should generally start at the LOWEST level and work UPWARD.

B - Advanced fire in Rowframe begin stream applicationj at the TOP FLOOR AND INTO THE COCKLOFT.

C - Common cockloft exposure protection is required, LCS attack at LEADING EDGE and traverse towards MIDDLE OF BUILDING. This will allow water to cascade down.

(TL 6 - ch. 4 4.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Two newly assigned TL members were discussing LCS applications when one member identified an incorrect statement. Which comment is incorrect?

A) Openings made in exterior walls or cornices will often permit stream penetration to the seat of the fire. Power tools should be utilized as necessary; be aware that time lost breaching walls to reach the cockloft may lead to extension in exposures.

B) The application of a LCS downward into roof openings from an elevated position can be counter productive. Operating the TL stream into the roof vent holes is generally ineffective and may result in a prolonged operation.

C) The Turbomaster nozzle is preferable when deep penetration of the stream is necessary to hydraulically overhaul stock. Increasing nozzle pressure within allowable limits will often facilitate access into partitions and sidewalls.

D) When conditions such as heavy clutter or doubtful floor stability exist, the IC may order all personnel removed from the bucket, lock the monitor in place, and extend the bucket into the building via a large window or other opening to achieve extinguishment and hydraulic overhaul.

A

ANSWER: C) The Turbomaster nozzle is preferable when deep penetration of the stream is necessary to hydraulically overhaul stock. Increasing nozzle pressure within allowable limits will often facilitate access into partitions and sidewalls. (INCORRECT)

  • The 1 1/2” TIP is preferable in this situation.

(TL 6 - ch. 4 4.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Breaching exterior walls may be necessary to gain access for life saving or stream penetration. Members of a Queens TL reviewing this procedure would know which choice below to be correct?

A) Exterior walls can be breached with a maul and/or power tool; however this is an arduous operation requiring frequent relief. When using the maul to breach cinder blocks, start at the bottom.

B) When the power saw is being used to cut through brick and concrete, the carbide tipped saw blade shall be used. Electric or pneumatic hammers may also be used for breaching operations from the bucket, when necessary.

C) Cuts in brick should be triangular with the vertex angle upward to prevent further collapse. The 1st and 2nd cuts should be at the mortar joint since the easiest cut is at the brickwork and the blade at this point will be worn.

D) Make the opening large enough so that the saw can be inserted to cut an inner wall, if necessary. Usually, on two-course brick walls, the second course can be removed by hand tools or a heavy stream.

A

ANSWER: D) Make the opening large enough so that the saw can be inserted to cut an inner wall, if necessary. Usually, on two-course brick walls, the second course can be removed by hand tools or a heavy stream.

A - Breaching cinder blocks start at the TOP.

B - Use COMBINATION METAL/CONCRETE (DIAMOND BLADE)

C - 1st and 2nd cuts should be made at the BRICKWORK since the easiest cut is at the MORTAR JOINT and the blade by this point will usually be worn.

(TL 6 - ch 5 5.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

At certain incidents, the TL may be used as a high point anchor. Which of the following choices contains incorrect information regarding this procedure?

A) The preferred location for the high point anchor is under the bucket. Pending the arrival of units from SOC, the bucket shall be positioned in a manner that will allow for rigging to be properly secured.

B) Under no circumstances shall the landing pads of the bucket be used as a high point anchor.

C) Remove all members from the apparatus, turn the siren to the “off” position and place the apparatus to the “off” position.

D) Under no circumstances should a TL be used as a crane to “lift” a patient.

A

ANSWER: C) Remove all members from the apparatus, turn the siren to the “off” position and place the apparatus to the “off” position. (INCORRECT)

  • Turn siren to the ON position

(TL 6 - ch. 5 5.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

During extreme cold weather, each of the following should be adhered to in regards to TLs except which?

A) The TL Officer should facilitate periodic relief of members in the bucket to prevent overexposure to the elements.

B) Units engaged in outside operations shall keep the apparatus engines running to prevent congealing of diesel oil.

C) During extended operations, consider placing all pressurized water extinguishers in the crew cab.

D) During operations in freezing weather, frequent boom repositioning will prevent ice buildup. However, if operations are to remain stationary, the boom should be periodically rotated left and right.

A

ANSWER: D) During operations in freezing weather, frequent boom repositioning will prevent ice buildup. However, if operations are to remain stationary, the boom should be periodically rotated left and right. (INCORRECT)

  • Periodically EXTENDED AND RETRACTED

(TL 6 - ch. 5 5.5)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Snow and ice present formidable challenges to TL units. Of the following choices, which action is not in accordance with Department policy?

A) During winter operations, use rock salt or speedy dry on icy surfaces under and around jack and outrigger pads to prevent slipping.

B) During periods of heavy snow accumulation, when conditions warrant, Department issued snow chains shall be mounted on all four inner drive wheel tires.

C) During periods of heavy snow accumulation, prior to setting jacks/outriggers on surfaces, clear snow to verify stabilizers are not being lowered onto manhole vaults.

D) During winter storms, the Vehicle Recovery Strap attached to a TL may assist in vehicle/apparatus/ambulance recovery.

A

ANSWER: B) During periods of heavy snow accumulation, when conditions warrant, Department issued snow chains shall be mounted on all four inner drive wheel tires. (INCORRECT)

  • On all OUTER drive wheel tires.

(TL 6 - ch. 5 5.5)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Efficient operation of the TL requires proper maintenance. Which choice below is incorrect?

A) At the start of every tour, verify the platform control switch on the pedestal is not engaged, as this will deactivate the bucket controls.

B) The condition of safety belts installed int he bucket shall be inspected weekly.

C) During MUD, at operations or in quarters, a visual check of the compression and tension bolts at the turntable “5th wheel” shall be made for missing or sheared bolts. A hand check for tightness of those bolts that are accessible shall be made.

D) During bleeding of the air brake tanks, a visual check of the hydraulic lines to the main reservoir shall be made, noting any developing cuts or other signs of possible failure of these lines. In addition, a visual check for broken spring sections shall be made.

A

ANSWER: B) The condition of safety belts installed int he bucket shall be inspected weekly. (INCORRECT)

  • DAILY

(TL 6 - ch. 7 7)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The tower ladder apparatus is equipped with four corner jacks and two hydraulically-extended outriggers (stabilizers). Which of the following statements concerning the tower ladders stabilizer supports is incorrect?

A) All stabilizing components are equipped with locks (pins) that must be inserted manually in case of hydraulic failure.

B) Jacks and outriggers are controlled either through individual levers or an “All Jacks” lever. The individual levers are the preferred method for lowering when on level ground.

C) Jacks and outriggers must be lowered until every green light is illuminated on the outrigger control panel prior to raising the boom.

D) If the apparatus is not level, lower the jacks and outrigger on the low side first, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed.

A

ANSWER: B) Jacks and outriggers are controlled either through individual levers or an “All Jacks” lever. The individual levers are the preferred method for lowering when on level ground.

(Tower Ladders Ch 1: 1.1)

B - The “ALL JACKS” is the preferred method for lowering when on level ground.

NEW REWRITTEN BULLETIN RELEASED 10/1/19

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

When positioning a tower ladder, the ideal horizontal distance from the centerline of the turntable to an objective is _______ feet. With the centerline of the turntable _______ feet from a building there will be sufficient room for the bucket to be dropped from the horizontal with the boom perpendicular to the side of the apparatus.

A) 25 – 35 / 25

B) 32 / 15

C) 25 – 35 / 32

D) 32 / 25

A

ANSWER: D) 32 / 25

Lad 6 Chapter 2 Page 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

When supplying a tower ladder for use of the water delivery system, generally one supply source at the base of the TL should be used. ________________ psi is the recommended pressure at the gated inlet for an effective operation.

A) 250 - 300

B) 150 - 200

C) 200 - 250

D) 100 - 150

A

ANSWER: C) 200 - 250

Lad 6 Chapter 4 4.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Choose an incorrect statement regarding tower ladder large caliber stream operations.

A) When stretching a 3 ½” supply line to a TL, ensure the female end is stretched to the gated outlet.

B) A Satellite Water Unit is the best source of supply if available.

C) Water flow to the TL should be controlled at the supply source (e.g. engine apparatus or Satellite manifold).

D) The TL may be supplied at either side of the apparatus.

A

ANSWER: A) When stretching a 3 ½” supply line to a TL, ensure the female end is stretched to the gated outlet.

(Lad 6 Chapter 4 4.1)

  • Ensure the MALE end is stretched to the gated outlet
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

When operating with a 75’ TL, a ________________ may be utilized as a gauge to determine if the outriggers will clear obstructions.

A) Halligan tool

B) 6’ hook

C) Maul

D) 10’ hook

A

ANSWER: B) 6’ hook

(Lad 6 Chapter 1 Page 4)

  • For a 95’ TL, the clearance needed is 6’8” therefore a 6’ hook would not be sufficient.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

The preferred placement of manual pins for TL outriggers shall be at the _____________ hole available once extended. The preferred placement of manual pins for jacks shall be at the ________________ slot available once extended.

A) Highest/ highest

B) Lowest/ highest

C) Highest/ lowest

D) Lowest/ lowest

A

ANSWER: B) Lowest/ highest

Lad 6 Chapter 1 Page 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Which one of the following should be the primary means of communication between the TL bucket and the pedestal?

A) Hand signals

B) Handie-talkie

C) The intercom system

A

ANSWER: C) The intercom system

Lad 6 Chapter 1 1.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

During TL bucket operations the terms “Extend, Retract, Raise, Lower, Boom Left and Boom Right” shall be used when transmitting orders between the bucket and pedestal. The reference point used should always be the?

A) Bucket position

B) Pedestal

A

ANSWER: B) Pedestal

Lad 6 Chapter 1 Page 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

When removing a victim in a Stokes basket via the TL bucket, which action below would be incorrect?

A) The apparatus should be positioned at least 25’-30’ from the building to allow the bucket to reach street level.

B) Diagonal positioning is preferred as it is the easiest and safest of the three options.

C) To ensure smooth operation, the Bucket Firefighter should perform the lowering operations if conditions permit.

D) The Stokes basket may be lashed to a substantial part of the bucket in an upright, horizontal or diagonal position.

A

ANSWER: C) To ensure smooth operation, the Bucket Firefighter should perform the lowering operations if conditions permit.

(Lad 6 Chapter 3 3.3)

  • The PEDESTAL FF should perform the lowering operation if conditions permit
45
Q

If the TL bucket makes contact with a building, structure or other obstruction, a potentially dangerous condition may present itself. The TL bucket may become wedged or stuck. Should this occur members in the bucket should take all but which one of the following actions?

A) Remain low in the bucket. All members should immediately crouch, sit or otherwise remain low in the bucket.

B) Notify the IC by transmitting an “URGENT” message after activating the EAB.

C) Verify all members are secured to a substantial part of the bucket using the installed safety belt, life belt or personal harness.

D) The P.T.O. should be disengaged and the apparatus engine should be shut down

A

D) The P.T.O. should be disengaged and the apparatus engine should be shut down. (INCORRECT)

(Lad 6 Chapter 3 3.6)

  • PTO should REMAIN ENGAGED and the apparatus shut down
46
Q

Which Tower Ladder (TL) operation is incorrect?

A) When operating with a 75’ or 95’ TL, a 6’ hook may be utilized as a gauge to determine if the outriggers will clear all obstructions.

B) If the apparatus is not level, lower the jacks and outrigger on the low side first, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed

C) To assess clearance between parked cars, LCCs can use the “knuckle” at the bottom of the outrigger an initial marker

D) The preferred placement of manual pins for outriggers shall be at the lowest hole available once extended. The preferred placement of manual pins for jacks shall be at the highest slot available once extended

A

ANSWER:A) When operating with a 75’ or 95’ TL, a 6’ hook may be utilized as a gauge to determine if the outriggers will clear all obstructions. (INCORRECT)

(Ladders 6 ch 1.)

  • When operating with a 75’ TL, a 6’ hook may be utilized as a gauge to determine if the outriggers will clear all obstructions.
  • This method MAY NOT BE USED WITH A 95’ TL as the clearance needed for the outrigger to an obstruction is 6’ 8”
47
Q

Setting up the tower ladder apparatus is key to safe operation. Which choice is CORRECT about setting up the tower ladder?

A) While not preferred, tower ladders are designed to operate with outriggers and jacks down on one side while on level ground.

B) Jacks and outriggers are controlled by individual levers or an all jacks lever. The All Jacks lever is the preferred method for lowering on other than level ground.

C) If the apparatus is not level, lower the jacks/tormentors on the high side followed by the jacks/tormentors on the low side until the green lights indicate proper deployment.

D) Raising the high side fully before raising the low side can be a safety hazard and may cause damage to the suspension system.

A

ANSWER: D) Raising the high side fully before raising the low side can be a safety hazard and may cause damage to the suspension system.

(Tower Ladders - Chapter 1 1.1)

A – They are NOT designed to operate with outriggers and jacks down on one side only.

B – The All Jacks is the preferred method for lowering ON LEVEL GROUND.

C – LOW SIDE FIRST

48
Q

The members of Tower Ladder 99 are finishing up roll call and begin their inspection of the rig. Which of the following inspections is conducted each tour?

A) The level of the platform of the bucket.

B) Condition of the safety belts installed in the bucket.

C) Verify the platform control switch on the pedestal is not engaged.

D) Evidence of hydraulic leaks at all connections.

A

ANSWER: C) Verify the platform control switch on the pedestal is not engaged.

(TOWER LADDERS CHAPTER 7)

  • At the start of EACH TOUR, verify the platform switch on the pedestal is not engaged as this will deactivate the bucket controls. Pg 1
  • A, B, D are all DAILY inspections.
49
Q

Positioning on narrow streets always presents the possibility of encountering a parked car during set up. Which choice below is CORRECT regarding positioning under these circumstances?

A) A guide firefighter, typically the roof firefighter, should assist the chauffeur in positioning the apparatus.

B) When positioning a 95’ tower ladder, a six-foot hook can be used as a guide to determine if the outriggers will clear all obstructions.

C) Presetting apparatus spotlights may provide an estimate of the final outrigger location at night.

D) Using the knuckle at the bottom of the outrigger may help the chauffeur assess the clearance between the apparatus and parked cars.

A

ANSWER: C) Presetting apparatus spotlights may provide an estimate of the final outrigger location at night.

(TOWER LADDERS – CHAPTER 1)

A – Guide FF is typically the OVM firefighter. 1.1 PG 3

B – When positioning a 75’ TL the 6’ hook is sufficient. The Clearance for a 95’ tower ladder is 6’8”

D – Clearance between PARKED CARS (not the apparatus and parked cars).

50
Q

The placement of the pins once the jacks and outriggers are extended are critical to the stability of the apparatus. Which choice is CORRECT regarding the preferred pin placement?

A) The preferred placement of manual pins for outriggers shall be at the lowest hole available.

B) The preferred placement of manual pins for jacks shall be at the lowest hole available.

C) The preferred placement of manual pins for outriggers and jacks shall be at the highest slot available once extended.

D) The preferred placement of manual pins for outriggers and jacks shall be at the lowest slot available once extended.

A

ANSWER: A) The preferred placement of manual pins for outriggers shall be at the lowest hole available.

(TOWER LADDERS – CHAPTER 1)

  • Outriggers (Lowest)
  • Jacks (Highest)
51
Q

Tower Ladder placement will depend upon conditions encountered on arrival. Which of the following choices is not listed as a factor in tower ladder placement?

A) Fire Conditions – location and extent of fire.

B) Type of Structure – Height and Area.

C) Time of Day.

D) Smoke Conditions – light, medium, heavy.

A

ANSWER: D) Smoke Conditions – light, medium, heavy. (INCORRECT)

(TOWER LADDERS – CHAPTER 2)

  • A, B, C are all correct

D – Not listed – Smoke Conditions are NOT listed as factors influencing TL positioning.

52
Q

The Tower Ladder bucket has a limited amount of space for firefighters. Which choice is the CORRECT maximum number of firefighters that should operate in the bucket?

A) 1

B) 2

C) 3

D) 4

A

ANSWER: B) 2

(TOWER LADDERS CHAPTER 1 - 1.3)

  • Maximum of 2 FFs in TL bucket
53
Q

Tower Ladder 1 is responding first due to a reported fire in a row of occupied Brownstone type Row Frame buildings. The Officer and members have a number of position related considerations to make. Which point below is INCORRECT?

A) The recommended apparatus positioning upon arrival should be for top floor VEIS.

B) A properly positioned Tower Ladder could potentially cover six row frame buildings.

C) Particular attention should be given to the larger room that shares two windows.

D) The LSR and Saw shall be taken to the roof when the bucket is used for roof access.

A

ANSWER: C) Particular attention should be given to the larger room that shares two windows. (INCORRECT)

(TOWER LADDERS CHAPTER 2)

  • Particular attention should be given to the SMALL BEDROOMS having their only entrance from the hall.
54
Q

When positioning the bucket for Rescue and Removal of people from windows, it is important to properly position the bucket for operation. Which choice below is CORRECT about bucket and apparatus positioning?

A) To expedite placing the bucket to a window, position the apparatus with the cab angled away from the objective lining up the bucket with the window.

B) To expedite placing the bucket to a window, position the apparatus parallel to the objective, lining up the bucket with the window.

C) To expedite placing the bucket to a window, position the apparatus parallel to the objective, lining up the turntable with the window.

D) To expedite placing the bucket to a window, position the apparatus with the cab angled away from the objective, lining up the turntable with the window.

A

ANSWER: B) To expedite placing the bucket to a window, position the apparatus parallel to the objective, lining up the bucket with the window.

(TOWER LADDERS – CHAPTER 3)

  • RIG PARALLEL / BUCKET LINED UP WITH WINDOW
55
Q

Ladder 99 is responding to an advanced fire on the 1st and 2nd floors of a 2 ½ story peaked roof private dwelling. Which of the following is INCORRECT about their positioning upon arrival?

A) At an advanced fire, the main objective is to position a tower ladder in front of the fire building.

B) When possible, the preferred position is with the apparatus cab angled away from the building so the bucket can be placed over the corner of the building near the peak of the roof.

C) The turntable should be positioned to enable the bucket to cover two sides of the private dwelling

D) If the apparatus cannot be placed in the preferred position, place the bucket to the valley area where a hook ladder can be used to reach the peak.

A

ANSWER: B) When possible, the preferred position is with the apparatus cab angled away from the building so the bucket can be placed over the corner of the building near the peak of the roof.

(TOWER LADDERS – CHAPTER 2 - PG 11)

  • PARALLEL to the front of the building.
56
Q

When positioning the tower ladder at a fire in a place of worship with access from all sides, which choice below most reflects the CORRECT sides(s) the apparatus should cover?

A) Exposure 1 or 3 side

B) Exposures 2 or 4 side

C) Exposures 2 and 3 sides

D) Exposures 1 and 4 sides

A

ANSWER: D) Exposures 1 and 4 sides

(TOWER LADDERS – CHAPTER 2)

  • At fires in places of Worship, the Tower Ladder should be positioned to cover two sides of the building and provide ventilation of the roof and rose window. The Rose window is exposure 1.
57
Q

Which of the following is CORRECT regarding apparatus positioning and the scrub area of the tower ladder?

A) Generally, the boom has enough clearance to reach most 2nd floor windows and above when operating over the crew cab.

B) The ideal horizontal distance from the center line of the turntable to an objective is 32 feet.

C) When the center line of the turntable is 20 feet from a building, there is sufficient room for the bucket to be dropped below the horizontal with the boom perpendicular to the side of the apparatus.

D) Observing the relationship of the objective to the building line may assist chauffeurs with initial positioning.

A

ANSWER: B) The ideal horizontal distance from the center line of the turntable to an objective is 32 feet.

(TOWER LADDERS – CHAPTER 2)

A – Clearance to reach most THIRD (3rd) floor windows.

C – TWENTY FIVE (25) FEET from the building line

D – Relationship of objective to lines in SIDEWALK.

58
Q

Which truck company member is responsible for personally verifying that all outriggers, jacks, and pins are properly placed prior to raising the boom?

A) Officer

B) Chauffeur

C) OVM Firefighter

D) Roof Firefighter

A

ANSWER: B) Chauffeur

TOWER LADDERS CHAPTER 1

59
Q

Tower Ladders have their own communications system installed. Which choice below is CORRECT regarding communicating during tower ladder operations?

A) A test of the intercom shall be made each tour, and at the initial stages of placing the Tower Ladder into operation.

B) When transmitting orders between the bucket and pedestal, the reference point is always the bucket position.

C) The HT tactical channel is the preferred means of communicating between the pedestal and bucket.

D) Boom Right is terminology that refers to rotating the boom to the bucket firefighter’s right.

A

ANSWER: A) A test of the intercom shall be made each tour, and at the initial stages of placing the Tower Ladder into operation.

(TOWER LADDERS – CHAPTER 1 - 1.5)

B – PEDESTAL is reference point

C – INTERCOM SYSTEM is preferred communication

D – Pedestal FF’s RIGHT

60
Q

When it comes to deployment of the tower ladder stream, there are several precautions the members in the bucket must take. Which of the following choices below is CORRECT?

A) Prior to water delivery, set and lock the monitor in the direction of the start point of water delivery.

B) Unlike the Engine Company Multiversal, the stream shaper is not required to ensure a good quality stream and maximum reach.

C) Members must verify use of the installed safety belt, life belt, or personal harness secured to a substantial part of the bucket prior to calling for water.

D) If water will be applied to the horizontal or below, pull the safety pin on the waterway prior to calling for water.

A

ANSWER: C) Members must verify use of the installed safety belt, life belt, or personal harness secured to a substantial part of the bucket prior to calling for water.

(TOWER LADDERS CHAPTER 4 - 4.2)

A – Set and lock the monitor HIGH IN THE AIR

B – The stream shaper should normally be left in place

D – BELOW the horizontal, pull the pin on the waterway.

61
Q

You are the officer working in Tower Ladder 99 and you are charged with having the bucket supplied with water for TL operations.Which choice below is CORRECT regarding supply operations?

A) Water flow to the tower ladder should be controlled at the supply source (Engine or Satellite manifold). Water should always be shut down at the supply pumper.

B) When stretching supply line to the Tower Ladder, ensure the female end is stretched to the gated inlet; storing spanners and fittings in proximity to the gated inlet at the base of the Tower Ladder will increase unit efficiency when transitioning to an LCS operation.

C) To maximize the efficiency of the Tower Ladder, if possible, two sources should generally be employed to supply the bucket.

D) The recommended pressure at the Tower Ladder nozzle for an effective operation should be 200-250 psi.

A

ANSWER: A) Water flow to the tower ladder should be controlled at the supply source (Engine or Satellite manifold). Water should always be shut down at the supply pumper.

(TOWER LADDERS – CHAPTER 4 - 4.1)

B - Ensure the MALE end is stretched to the TL

C - Generally, ONE SUPPLY SOURCE at the base of the tower ladder should be used.

D - Recommended pressure at the GATED INLET should be 200-250 psi.

62
Q

Certain components of the tower ladder require inspection by the members to ensure serviceability. Which of the following regarding inspection times is CORRECT?

A) Condition of the safety belts installed in the bucket is conducted each tour.

B) A visual check of the condition or presence of the clip/nut at the end of each boom section is done daily.

C) A visual check of the compression and tension bolts at the turntable 5th wheel shall be made monthly.

D) A test of the electrical outlets at the bucket and lights is conducted each tour.

A

ANSWER: B) A visual check of the condition or presence of the clip/nut at the end of each boom section is done daily.

(TOWER LADDERS CHAPTER 7 – INSPECTION)

A – Safety belt inspection is DAILY

B – Clip/nut at end of the boom is inspected DAILY

C – Turntable 5th Wheel inspected during MUD at operations or in quarters.

D – Electrical outlets at the bucket and lights is conducted DAILY.

63
Q

Pictures are a part of the testing process as well and are fair game when writing exams. According the picture associated with ventilating a peaked roof private dwelling, there are a series of cuts made in a sequential order. Which cut is the first cut made perpendicular to the ridge pole in the illustration?

A) 1st cut

B) 2nd cut

C) 3rd cut

D) 4th cut

A

ANSWER: C) 3rd cut

(TOWER LADDERS – CHAPTER 3 - 3.3.5)

  • The 3rd cut is perpendicular to the ridge pole.
64
Q

Tower Ladder 99 is assigned to a box where they are tasked with removing an injured construction worker via stokes basket from the upper floors of a building. TL positioning is as important as the manner in which the stokes is secured to the bucket. Which of the choices below CORRECTLY indicates the preferred positioning of the stokes basket along with the proper placement of the apparatus in relation to the building?

A) The preferred positioning of the stokes is in a horizontal position and the apparatus should be positioned so that the center line of the turntable is at least 25-30’ from the building.

B) The preferred positioning of the stokes is in an upright position and the apparatus should be positioned so that the center of the turntable is at least 25-35’ from the building.

C) The preferred positioning of the stokes is in a downward position and the apparatus should be positioned so that the center of the turntable is at least 25-35’ from the building.

D) The preferred positioning of the stokes is in a diagonal position and the apparatus should be positioned so that the center of the turntable is at least 25-30’ from the building.

A

ANSWER: D) The preferred positioning of the stokes is in a diagonal position and the apparatus should be positioned so that the center of the turntable is at least 25-30’ from the building.

(TOWER LADDER 3 - 3.3)

  • Diagonal positioning is the preferred as it is the easiest and safest of the three options. The apparatus should be positioned so that the center line of the turntable is at least 25-30 feet from the building.
65
Q

Tower Ladders discusses a two member tactical approach at fire operations. Which of the following is INCORRECT about this approach from the tower ladder bucket?

A) When the ladder company members make the decision to operate in this manner, the incident commander should immediately be notified.

B) One member remaining in the bucket to act as a beacon to monitor, ventilate, assist in rescue and establish a valuable communications link to the Incident Commander is an overall tactical advantage.

C) It is essential for the bucket firefighter to maintain radio contact with the member conducting a search of the fire area.

D) If a known life hazard is discovered and immediate action could prevent the loss of life, appropriate action may be taken consistent with the provisions stated in FFP Safety Team.

A

ANSWER: C) It is essential for the bucket firefighter to maintain radio contact with the member conducting a search of the fire area. (INCORRECT)

(TOWER LADDER 3 - 3.1)

  • It is essential for the bucket firefighter to maintain VOICE CONTACT with the member conducting a search.
66
Q

Members of Tower Ladder 99 were having a round table discussion about positioning the bucket for removals during fire operations.Which statement below is the only CORRECT one made regarding bucket positioning operations?

A) When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite its preceding movement.

B) Positioning the apparatus parallel to the objective and lining up the turntable with the window will shorten the horizontal travel distance, reduce the time required to reach the target, and ensure an angular approach.

C) The preferred position for the removal of Unconscious, incapacitated, or obese victims is to position the middle bucket rail level with the window sill or top rail of the fire escape.

D) Position the top of the bucket at a level where a person can easily step into it without straddling the window sill or fire escape railing.

A

ANSWER: A) When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite its preceding movement.

(TOWER LADDERS – CHAPTER 3)

B – Line up the BUCKET with the objective.

C – The preferred position for unconscious, obese, incapacitated victims is the TOP BUCKET RAIL LEVEL WITH THE WINDOW SILL OR TOP RAIL OF THE FIRE ESCAPE.

D – Position the MIDDLE of the bucket at a level where a person can easily step into it without straddling the window sill or fire escape railing 3.3

67
Q

Bucket safety has become a high priority for members operating in tower ladder companies. Ladder 99 held a drill following roll call to address issues related to the bucket in compromised positions. Which statement made by members was CORRECT regarding these operations?

A) If no other option is available and members must use the escape ladder to exit the bucket, the apparatus shall be taken out of PTO, shut down, and the escape ladder side rails raised.

B) If the bucket becomes stuck or wedged, the members in the bucket should depress the EAB button and transmit an urgent message to the Incident Commander.

C) If the bucket becomes stuck or wedged, the members shall remain low in the bucket and the LCC should take over all bucket movement until the condition is corrected.

D) If the bucket becomes stuck or wedged, the apparatus should be taken out of PTO and shut down.

A

ANSWER: B) If the bucket becomes stuck or wedged, the members in the bucket should depress the EAB button and transmit an urgent message to the Incident Commander.

(TOWER LADDERS – CHAPTER 3 - 3.6)

A – The apparatus shall REMAIN IN PTO and shut down.

C – Members shall remain low, the apparatus shall be SHUT DOWN.

D – The PTO shall REMAIN ENGAGED

68
Q

Tower Ladder 99 is responding first due to a working fire on the fourth floor of a six story H type Multiple Dwelling. The building is 200x200, has two large wings with wing stairs separated by a throat and there are two fire escapes present on the front of both wings. The first arriving engine reports fire out two windows off the far end fire escape near the exposure 2 wall in the A wing. Based on this information, which choice is CORRECT regarding the recommended initial positioning Ladder 99 should take on arrival?

A) Position at the front of the building with the bucket positioned to cover the throat.

B) Position to cover the fire apartment/floor above for VEIS and secondary egress.

C) Position to allow the aerial access to the roof of the fire building.

D) Position to provide roof access for the 1st & 2nd arriving roof firefighters.

A

ANSWER: B) Position to cover the fire apartment/floor above for VEIS and secondary egress.

(TOWER LADDERS – CHAPTER 2 - 2.1.4)

  • Additional TLs shall be positioned to cover the throat.

A – Initial Throat positioning for TOP FLOOR FIRES

C and D - Not stated / TL NOT primary means to access the roof in H-type MD’s

69
Q

Which of the following choices is CORRECT regarding the use of the Tower Ladder Bucket?

A) The controls at the pedestal allow for smoother positioning than the joystick controls. The pedestal firefighter should always perform delicate movements.

B) All jacks and outriggers must be fully lowered whenever the Tower Ladder Bucket is to be used.

C) Detailed members should not operate on the turntable unless they are assigned to a truck company, are a qualified Chauffeur, or Company trained FF assigned to a TL.

D) The pedestal firefighter should relay operational and safety concerns received from the bucket to the company officer.

A

ANSWER: B) All jacks and outriggers must be fully lowered whenever the Tower Ladder Bucket is to be used.

(TOWER LADDERS – CHAPTER 1 – PG 6)

A – EXCEPTION is when pedestal firefighter’s view is obstructed.

C – TL Company firefighter and NOT Company trained.

D – INCIDENT COMMANDER should be notified

70
Q

Water delivery via Tower Ladder at a fire is a major factor in the success of an operation. Which water delivery strategy is INCORRECT according to Large Caliber Stream delivery from a Tower Ladder?

A) At an advanced Row Frame fire where multiple floors are involved, LCS delivery should begin at the lowest level and work its way up to the top floor and cockloft area.

B) For common cockloft protection, commence LCS attack at the leading edge of the building and traverse towards the middle to facilitate extinguishment.

C) At H-types with fire showing out windows in the front, courtyard, and throat, the TL stream should be directed at the windows in the throat first, then advanced toward the front of the building, and finally into the front windows.

D) A street level attack at a taxpayer fire using the LCS to penetrate the ceiling and collapse it, thereby exposing fire in the cockloft, enables extinguishment of fire therein.

A

ANSWER: A) At an advanced Row Frame fire where multiple floors are involved, LCS delivery should begin at the lowest level and work its way up to the top floor and cockloft area. (INCORRECT)

TOWER LADDERS – CHAPTER 4

  • The exception is - At an advanced fire in a Row Frame, begin application at the TOP FLOOR and into the cockloft.
71
Q

Positioning a tower ladder on a hill has always been a tricky proposition. Which choice below is MOST CORRECT regarding positioning of the apparatus when operating on a hill?

A) Position the apparatus parallel to the slope facing downhill, turntable before the objective.

B) Position the apparatus parallel to the slope facing uphill, turntable past the objective.

C) Position the apparatus parallel to the slope facing downhill, turntable past the objective.

D) Position the apparatus parallel to the slope facing uphill, turntable before the objective.

A

ANSWER: C) Position the apparatus parallel to the slope facing downhill, turntable past the objective.

(TOWER LADDERS CHAPTER 2 - pg 19)

  • Position the apparatus parallel to the direction of the slope so that boom operations will be in the uphill direction.
  • If possible, the apparatus should be facing downhill (e.g. if facing downhill, place the turntable past the objective)
72
Q

Scrub Area is an important feature of tower ladder positioning. A properly positioned tower ladder can cover how many Brownstone type Row-Frame buildings?

A) 7

B) 6

C) 5

D) 4

A

ANSWER: B) 6

TOWER LADDERS – CHAPTER 2 - 2.1.2

73
Q

Lt. Tenon is working in Tower Ladder 199 and her unit is assigned to a breaching operation at a stubborn fire in a commercial building. Which action taken by the truck company is CORRECT according to the TL bulletin?

A) Members were assigned to breach cinder block windows and started at the middle where the wall was weakest and hollow to provide quick access.

B) Cuts in brick walls shall be triangular with the vertex angle downward to prevent further collapse.

C) The first cuts shall be at the mortar since this is the easiest part of the cuts and the blade will not be worn at this point.

D) On two course brick walls, the second course can be removed by hand tools, or if a heavy stream will be used by the stream itself.

A

ANSWER: D) On two course brick walls, the second course can be removed by hand tools, or if a heavy stream will be used by the stream itself.

(TOWER LADDERS – CHAPTER 6 - 5.2)

A – Start at the TOP as this area is usually hollow 5.2

B – Vertex angle UPWARD to prevent further collapse.

C – The first and second cuts shall be at the BRICK AND CONCRETE since the easiest cut is at the mortar joint and the blade at this point will be worn.

74
Q

Initial positioning of the apparatus is a mark of a company’s professionalism & often is a determining factor in the success at an operation. Which choice below is INCORRECT according to the recommended initial tower ladder positioning guidelines?

A) At a fire on the 3rd floor of a 4-story brownstone, the initial apparatus positioning of the tower ladder would be for top floor VEIS.

B) At a fire on the 4th floor of a 5-story tenement, the initial positioning of the tower ladder would be to the fire apartment/floor above or off window of the fire escape.

C) At a taxpayer with fire extending to exposures, the initial positioning of the tower ladder would be to operate at roof level and protect exposures.

D) At a top floor fire in an H-type multiple dwelling, positioning a tower ladder in the throat can dramatically influence an operation.

A

ANSWER: C) At a taxpayer with fire extending to exposures, the initial positioning of the tower ladder would be to operate at roof level and protect exposures. (INCORRECT)

(TOWER LADDERS – CHAPTER 2 - 2.1.4)

  • Position to operate at STREET LEVEL and protect exposures
75
Q

Arriving as the extra truck at a fire involving a large 2 ½ story private dwelling, Tower Ladder 90 is tasked with ventilating the peaked roof. Which choice below is CORRECT regarding this operation?

A) The tower ladder bucket should be positioned on the roof as close to the ridge pole as possible.

B) The saw operator shall wear the installed safety belt or the LSR tied with a bowline to the bucket railing to allow maneuverability.

C) The saw shall be started outside the bucket and held outside the bucket until it is shut off.

D) The saw operator shall make the first cut perpendicular to the ridge pole. The size of the cut will depend on the reach of the operator.

A

ANSWER: A) The tower ladder bucket should be positioned on the roof as close to the ridge pole as possible.

(TOWER LADDERS CHAPTER 3 - 3.5)

B – LSR tied to a substantial part of the bucket. Bucket railings are NOT a substantial pare of the bucket and shall not be used as a substantial object when tying off.

C – Saw shall be started INSIDE the bucket and held outside until shut off.

D – Make the first cut PARALLEL to the ridge pole 3.5 -3

76
Q

Anytime a Tower Ladder is set up, supplied, and placed into operation, Safety remains on the front burner. Which choice below regarding operations is INCORRECT?

A) The pedestal firefighter must don PPE and be continuously aware of changing fire conditions. This member should have a working knowledge of the location of other operating units.

B) The pedestal firefighter shall activate the platform control switch and/or Safety Interlock Foot Pedal during overhaul and whenever members or civilians enter or leave an elevated bucket to prevent accidental movement.

C) The member operating the joystick should preplan bucket movement in the event of an imminent or actual collapse. When operating at upper floors, this will generally be upwards.

D) When collapse is feared, the height of the wall vertically above the bucket is the minimum distance horizontally that the bucket should be away from the wall.

A

ANSWER: B) The pedestal firefighter shall activate the platform control switch and/or Safety Interlock Foot Pedal during overhaul and whenever members or civilians enter or leave an elevated bucket to prevent accidental movement. (INCORRECT)

(TOWER LADDERS – CHAPTER 4 – LARGE CALIBER STREAM OPERATIONS)

  • CONSIDER activating the platform control switch.
77
Q

On a cold winter night, the members of Ladder 199 were discussing Tower Ladder operations as the snow piled up deep on the city streets. Which statement below made by the members is CORRECT regarding these operations?

A) If operations are to remain stationary in freezing weather, the boom should periodically be rotated to the left and right to prevent ice build-up.

B) When conditions warrant, Department issued snow chains shall be mounted on both front and four rear outer drive-wheel tires.

C) During extreme cold weather, the incident commander should facilitate periodic relief of members operating in buckets to prevent overexposure to the elements.

D) Clear snow prior to setting jacks/outriggers to verify stabilizers aren’t being lowered on vaults/manholes. Use rock salt or speedy dry under and around jack and outrigger pads to prevent slipping.

A

ANSWER: D) Clear snow prior to setting jacks/outriggers to verify stabilizers aren’t being lowered on vaults/manholes. Use rock salt or speedy dry under and around jack and outrigger pads to prevent slipping.

(TOWER LADDERS CHAPTER 6 – 5.5)

A – EXTEND and RETRACT boom to prevent ice build-up

B – NOT front tires. Just four rear outer drive-wheel tires.

C – TL OFFICER should facilitate periodic relief

78
Q

Tower Ladder 199 arrives first due at a trench collapse and is in prime position to be used as a high point anchor to assist with SOC operations. Which of the following regarding the set up and use of the TL is CORRECT?

A) The Tower Ladder can support at least 1000 lbs. The preferred location for the high point anchor is under the bucket.

B) The landing pads under the bucket are suitable for securing anchor straps for the high point.

C) Remove all members from the apparatus and disengage the PTO once the apparatus is in position.

D) Once secured to the metal stokes, the TL can be used in extreme circumstances to lift the patient.

A

ANSWER: A) The Tower Ladder can support at least 1000 lbs. The preferred location for the high point anchor is under the bucket.

(TL 6 - 5.4) (Confined Space 4.4)

  • Recent change / books used to say something else.

B – Incorrect – UNDER NO CIRCUMSTANCES shall the landing pads be used as a high point anchor.

C – Incorrect – Remove all members, turn the siren to on and turn the apparatus to the off position.

D – Incorrect – UNDER NO CIRCUMSTANCES should a tower ladder be used as a crane to lift a patient.

79
Q

Capt. Smith was discussing the application of snow chains with his members. He was correct in all but which point below?

A) When snow chains are applied to an apparatus, that vehicle should not exceed 30 MPH.

B) When the weather conditions and weather improve, the chains must be removed.

C) When returning from an alarm; if the snow chains break, the officer shall cause the vehicle to stop immediately and have the conditions corrected.

D) When required, members shall install the snow chains on the apparatus. The turtle ramp shall be used only if the “drive over” method is not possible.

A

ANSWER: D) When required, members shall install the snow chains on the apparatus. The turtle ramp shall be used only if the “drive over” method is not possible. (INCORRECT)

(Training Bulletins Apparatus C2)

Turtle ramp CAN BE used as an alternative.

80
Q

As a Captain of a 95’ Tower Ladder, it is your duty to have a certain amount of company trained chauffeurs (not school trained) on your roster. The incorrect Tower Ladder chauffeur training you provided can be found in which choice?

A) TLs are not designed to operate with outriggers and jacks down on one side only. If the apparatus is not level, lower the jacks and outrigger on the low side first, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed

B) Using the “knuckle” at the bottom of the outrigger as an initial marker may help chauffeurs assess clearance between parked vehicles

C) The number of FFs operating in the bucket should be limited to 2

D) A 6’ hook may be utilized as a gauge to determine if the outriggers will clear all obstructions

A

ANSWER: D) A 6’ hook may be utilized as a gauge to determine if the outriggers will clear all obstructions (INCORRECT)

(Ladders 6 1.1)

  • 75’ TL may use a 6’ hook.
  • 95’ TL outriggers need 6’8” of clearance
81
Q

The Tower Ladder apparatus is equipped with four corner jacks and two hydraulically-extended outriggers (stabilizers). The outriggers, when fully extended, produce a solid foundation for the apparatus during operations involving the Tower Ladder bucket. Which statement below is incorrect regarding the stabilizer supports?

A) All stabilizing components are equipped with locks (pins) that must be inserted manually in case of hydraulic failure.

B) The “All Jacks” method is the preferred method for lowering when on uneven ground.

C) Jacks and outriggers must be lowered until every green light is illuminated on the Outrigger Control Panel prior to raising the boom.

D) If the apparatus is not level, lower the jacks and outrigger on the low side first, followed by the jacks and outrigger on the high side until the green lights indicate that all stabilizers are properly deployed.

A

ANSWER: B) The “All Jacks” method is the preferred method for lowering when on uneven ground. (INCORRECT)

(Tower Ladders Ch 1: 1.1 Pg 2)

  • The “All Jacks” method is the preferred method for lowering when on LEVEL ground.
82
Q

Ladder 99 responded to reports of an incapacitated person on the 5th floor of a 6 story MD and was tasked with using the tower ladder to remove the patient via tower ladder bucket. Which action taken below is CORRECT according to TL operations?

A) The LCC positioned the turntable 25’ from the building to allow the bucket to reach the street level and ensure an efficient transfer to EMS.

B) Members operating in the bucket lashed the stokes basket to the top railing of the Tower Ladder bucket.

C) The stokes was secured in the horizontal position which is the preferred position as it is the easiest and safest of the three positioning options.

D) To ensure a smooth operation, the basket firefighter performed the lowering operation.

A

ANSWER: A) The LCC positioned the turntable 25’ from the building to allow the bucket to reach the street level and ensure an efficient transfer to EMS.

(TOWER LADDERS – CHAPTER 3 - 3.3)

B – Must be lashed to a SUBSTANTIAL PART of the bucket. Not the doors or railings.

C – The preferred position is DIAGONAL.

D – The PEDESTAL FIREFIGHTER should perform the lowering operation if conditions permit.

83
Q

Positioning the Tower Ladder may be challenging on streets that are narrow and lined with parked cars. When positioning and setting up the Tower Ladder for operations which comment below is incorrect?

A) A guide firefighter, typically the outside vent firefighter, should assist the chauffer in positioning the apparatus so that the outriggers will clear parked cars and other obstructions.

B) The guide firefighter is to remain in position until the outrigger is fully lowered on the operator’s blind side.

C) When operating any Tower Ladder, a 6’ hook may be utilized as a gauge to determine of the outriggers will clear all obstructions.

D) The preferred placement of the manual pins for the jacks shall be the highest slot available once extended.

A

ANSWER: C) When operating any Tower Ladder, a 6’ hook may be utilized as a gauge to determine of the outriggers will clear all obstructions. (INCORRECT)

(Tower Ladder Ch 1 Pgs 3-4)

  • When operating WITH A 75’ Tower Ladder , a 6’ hook may be utilized as a gauge to determine of the outriggers will clear all obstructions.
  • THIS METHOD MAY NOT BE USED WITH A 95’ TOWER LADDER AS THE CLEARENCE NEEDED FOR THE OUTRIGGER TO AN OBSTRUCTION IS 6’8”.
84
Q

If the Tower Ladder bucket makes contact with a building, structure or other obstruction, a potentially dangerous condition may present itself. The likelihood of the bucket becoming wedged or stuck will dramatically increase and extreme caution must be exercised. When this occurs member shall take certain safety precautions. Which one is correct?

A) Verify all members are secured to a substantial part of the bucket using the life belt or personal harness. The installed safety belt shall not be used.

B) Notify the IC (transmitting a “MAYDAY” message after depressing the EAB) of the condition.

C) Remain low in bucket but do not crouch. All members must immediately sit to lower their center of gravity in anticipation of possible sudden, violent movements.

D) PTO should remain engaged and the apparatus shut down.

A

ANSWER: D) P.T.O should remain engaged and the apparatus shut down.

(Tower Ladders 3.6)

A - Verify all members are secured to a substantial part of the bucket using the INSTALLED SAFETY BELT, life belt or personal harness.

B - Notify the IC (transmitting a “URGENT” message after depressing the EAB) of the condition.

C - Remain low in the bucket. All members SHOULD immediately CROUCH, SIT, OR OTHERWISE REMAIN LOW in the bucket to lower their center of gravity in anticipation of possible sudden, violent movements.

85
Q

Having a basic understanding of how the pedestal controls and boom assembly operate on a tower ladder is essential to operating safely and effectively from the bucket. Which description below is incorrect?

A) The tower ladder chauffer must personally verify all outriggers, jack, and manual pins are properly placed prior to raising the boom from the bedded position.

B) All jacks and outriggers must be fully lowered whenever the tower ladder bucket is to be used, and remain lowered until the boom is bedded.

C) The joystick controls in the bucket will allow for smoother positioning than the controls at the pedestal.

D) Detailed members should not operate on the turntable unless they are presently assigned to a tower ladder unit or are a qualified chauffer-tiller (QCT, school trained).

A

ANSWER: C) The joystick controls in the bucket will allow for smoother positioning than the controls at the pedestal. (INCORRECT)

(Ladders 6 - Tower Ladders 1.2)

  • The CONTROLS AT THE PEDESTAL will allow for smoother positioning than the JOYSTICK CONTROLS IN THE BUCKET.
86
Q

The bucket is the primary work area of the tower ladder apparatus. Which statement below concerning the operation of the bucket is incorrect?

A) All three boom functions (raise/lower, rotate left/right, extend/retract) can be performed simultaneously.

B) If two members are operating in the tower ladder bucket, one member must personally verify the placement of both door latches in the locked position prior to movement.

C) Due to the lack of space, the number of firefighters operating in the bucket should be limited to two.

D) Under normal conditions the member operating from an elevated position should control the movement of the bucket. However, the member on the pedestal should take over when delicate maneuvers are required, as long as this member’s line of sight is not obstructed.

A

ANSWER: B) If two members are operating in the tower ladder bucket, one member must personally verify the placement of both door latches in the locked position prior to movement. (INCORRECT)

(Tower Ladders 6 - 1.3)

B - EACH member operating in a tower ladder bucket must personally verify the placement of both door latches in the locked position prior to movement.

87
Q

You’re the ladder company officer working the day tour in a busy tower ladder. The newly assigned proby asks you to describe some of the key aspects of tower ladder positioning. You make the following statements, but you were incorrect in which one?

A) The ideal horizontal distance from the center line of the turntable to the objective is 25 feet.

B) Generally, the apparatus should be parallel to the building.

C) Occasionally, the scrub area of the bucket will be reduced by the cab of the apparatus. This condition can be corrected by parking the apparatus with the front end angled away from the building line.

D) Generally, the boom has enough clearance to reach most 3rd floor windows and above when operating over the crew cab.

A

ANSWER: A) The ideal horizontal distance from the center line of the turntable to the objective is 25 feet. (INCORRECT)

(Tower Ladders Chapter 2 Page 2 & 3)

  • The ideal horizontal distance from the center line of the turntable to the objective is THIRTY TWO (32) feet.
88
Q

Members of your unit are discussing Tower Ladder positioning at taxpayers during roll call. They make the following comments. Which one is incorrect?

A) When the fire is located at the end of a row of stores, high compartments in the rear of the apparatus can impeded the scrub area and may necessitate remaining parallel to the building line and/or angling in.

B) Direct the monitor at the cockloft area from the roof level.

C) The Tower ladder can be used to overhaul a façade to gain access into the cockloft.

D) The Tower Ladder can be used as an observation point at a roof level when lightweight construction, gypsum, and bowstring truss roofs are encountered.

A

ANSWER: B) Direct the monitor at the cockloft area from the roof level. (INCORRECT)

(Tower Ladder Ch 2 2.1.5)

  • Direct the monitor at the cockloft area from the STREET LEVEL.
89
Q

Exterior walls can be breached with a maul and/or power tools. Breaching may be necessary to gain access for life saving or stream penetration. This is an arduous operation requiring frequent relief. Which procedure below is correct when using the saw to breach a wall?

A) The carbide tip blade shall be used to cut through brick and concrete.

B) Cuts in brick walls should be triangular with the vertex angle downward to prevent further collapse.

C) The first and second cuts should be at the brickwork.

D) The mortar joint must always be cut to remove the bricks.

A

ANSWER: C) The first and second cuts should be at the brickwork.

(Tower Ladder - Ch 5 5.2)

A - The DIAMOND BLADE shall be used to cut through brick and concrete.

B - Cuts in brick walls should be triangular with the vertex angle UPWARD to prevent further collapse.

D - THE CUT AT THE MOTAR JOINT MAY NOT BE NECESSARY SINCE BRICKS ALONG THIS PLANE MAY BE LOOSENED AND REMOVED EASILY WITH HAND TOOLS.

90
Q

According to Tower Ladder Operations, what is the best source of supply for a Tower Ladder?

A) High Pressure Pumper

B) Drafting

C) Fireboat

D) Satellite Water Unit

A

ANSWER: D) Satellite Water Unit

Tower Ladder Ch 4: 4.1

91
Q

Live overhead wires can present a problem if they fall onto the tower ladder apparatus. It is possible for the apparatus to be energized, particularly if the jacks and outriggers are down in place. If this should occur, which tactic below is correct for members to take?

A) Depress the EAB and transmit an “urgent” message to the IC informing him/her of the condition.

B) A member shall immediately raise the jacks and outriggers off the ground.

C) Any members in position on an energized apparatus must be immediately removed.

D) In this situation, the supply lines and supply pumper being energized are not a consideration.

A

ANSWER: A) Depress the EAB and transmit an “urgent” message to the IC informing him/her of the condition.

(Tower Ladder 2.7)

B - NO MEMBER SHALL TOUCH THE APPARATUS.

C - Any members in position on an energized apparatus SHOULD ATTEMPT TO REMAIN IN PLACE AND ARE NOT TO BE TOUCHED UNTIL POWER HAS BEEN REMOVED.

D - In this situation, the supply lines and supply pumper being energized ARE A consideration.

92
Q

The full capacity of the tower ladder will be realized when there are many persons to be removed, and/or victims are unconscious, incapacitated or obese. Rescue via the bucket may be achieved in several ways. Which of the following ways is incorrect?

A) The preferred position for unconscious, incapacitated, or obese victims is to position the top bucket rail level with the window sill or top rail of the fire escape.

B) To expedite placing the bucket to a window, position the apparatus parallel to the objective while lining the bucket up with the window.

C) When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite its preceding movement (e.g. after extending the boom to reach a window, the subsequent move should generally be to RAISE.)

D) When multiple trips of the bucket are required to remove a large number of occupants, removal directly to street level may not be necessary or practical.

A

ANSWER: C) When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite its preceding movement (e.g. after extending the boom to reach a window, the subsequent move should generally be to RAISE.) (INCORRECT)

(Tower Ladder 3.5)

  • When preparing to move a properly positioned bucket from a window, the first joystick movement should generally be opposite its preceding movement (e.g. after extending the boom to reach a window, the subsequent move should generally be to RETRACT.)
93
Q

When using the Tower Ladder as a highpoint anchor which procedure below is incorrect?

A) Remove all members from the apparatus, turn the siren to the “on” position and place the apparatus to the “off” position.

B) The metal stokes basket should be utilized at all high point anchor operations.

C) Under no circumstances should a Tower Ladder be used as a crane to “lift” a patient.

D) The preferred location for the high point anchor is the landing pads of the bucket.

A

ANSWER: D) The preferred location for the high point anchor is the landing pads of the bucket. (INCORRECT)

(Tower Ladder Ch 5: 5.4)

  • The preferred location for the high point anchor is UNDER THE BUCKET. UNDER NO CIRCUMSTANCES SHALL THE LANDING PADS OF THE BUCKET BE USED AS A HIGH POINT ANCHOR.
94
Q

A test of the intercom system shall be made __ and at the initial stages of placing the Tower Ladder into operation.

A) Each tour

B) Daily

C) Weekly

D) Monthly

A

ANSWER: A) Each tour

(Tower Ladder Ch 1 - 1.5)

UPDATED IN NEW BULLETIN RELEASED 10/1/2019

IT IS NOW EACH TOUR NOT DAILY

95
Q

Ladder companies in Battalion 99 are 1084 at a fire on the 3rd floor of a 6-story multiple dwelling. Several laddering decisions were made during the early stages of this fire. Which one was CORRECT?

A) The 1st arriving LCC placed the aerial to the roof at an extreme angle so that it barely touched the building. It was extended 4 feet above the roof.

B) The 2nd arriving OV placed the first portable ladder to the first fire escape balcony alongside the drop ladder to assist with the number of people coming down the fire escape.

C) The 2nd arriving LCC positioned the Tower Ladder top basket railing level with the fire escape so members could load an unconscious 1045 victim in the bucket.

D) The 1st arriving LCC placed the aerial on the 3rd floor fire escape balcony, less than 6” above the railing.

A

ANSWER: C) The 2nd arriving LCC positioned the Tower Ladder top basket railing level with the fire escape so members could load an unconscious 1045 victim in the bucket.

(LADDERS– PORTABLES – AERIALS – TLS)

C IS CORRECT – Tower Ladders 3.3

A - When placing the ladder to the roof, extend the ladder so that the tip is at least 5 feet above the point where the ladder comes in contact with the building. (Ladders 2 - 7.13)

B - A portable ladder should be raised to the first balcony at a point OPPOSITE the drop ladder. (Portable Ladders 10.1)

D – Aerial Ladders are NOT placed on Fire escapes. Place the ladder alongside the fire escape with the tip TWO INCHES (2”) away from face of building and about ONE TO THREE FEET above the balcony railing.

96
Q

If the bucket of the tower ladder makes contact with a building, structure or other obstruction, a potentially dangerous condition may present itself. The likelihood of the bucket becoming wedged or stuck will dramatically increase and extreme caution must be exercised. When this occurs which statement below is correct?

A) A possible indicator that the bucket is wedged is an inoperable joystick or a throttle decrease (noise level).

B) The P.T.O. should remain engaged and the apparatus shut down.

C) Members in the bucket shall notify their company officer via an “urgent” transmission.

D) Members in the bucket should remain standing while secured to a substantial part of the bucket using the installed safety belt, life belt or personal harness.

A

ANSWER: B) The P.T.O. should remain engaged and the apparatus shut down.

(Tower Ladder Ch 3 3.6)

A - A possible indicator that the bucket is wedged is an inoperable joystick or a throttle INCREASE (noise level).

C - Members in the bucket shall notify THE INCIDENT COMMANDER via an “urgent” transmission.

D - Members in the bucket should remain LOW (IMMEDIATELY CROUCH, SIT OR OTHERWISE REMAIN LOW) while secured to a substantial part of the bucket using the installed safety belt, life belt or personal harness.

97
Q

When positioning the Tower Ladder the ideal horizontal distance from the center line of the turntable to the objective is ___ feet. A test of the intercom system shall be made ___ and at the initial stages of placing the Tower Ladder into operation.

A) 25; daily

B) 25; each tour

C) 32; daily

D) 32; each tour

A

ANSWER: D) 32; each tour

Tower Ladder Ch 1: 1.5; Ch 2: Pg 2

98
Q

The proper position of the Tower Ladder varies depending on the type of building involved. Which apparatus position described below is incorrect?

A) The Tower Ladder can potentially cover six Rowframes.

B) When performing a rescue at a tenement, the preferred method of rescue is the angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends in for the rescue.

C) The positioning of the Tower Ladder in the courtyard or rear lot of an H-type building can be used to prevent the spread of fire across the throat.

D) At a taxpayer, the Tower Ladder should be positioned to operate at the roof level and protect exposures.

A

ANSWER: D) At a taxpayer, the Tower Ladder should be positioned to operate at the roof level and protect exposures. (INCORRECT)

(Tower Ladder Ch 2: 2.1.2, 2.1.3, 2.1.4, 2.1.5)

D - At a taxpayer, the Tower Ladder should be positioned to operate at the STREET level and protect exposures.

99
Q

Company Commanders are tasked with providing some chauffeur training before sending the firefighter to chauffeur school. This is especially important when it comes to Tower Ladders. From the list below, you incorrectly train your firefighter in Tower Ladder operations in which choice?

A) When positioning the Tower Ladder in a vacant lot, the chauffeur and OV FF must conduct a survey for potential collapse zones and voids.

B) When positioning the apparatus on a hill, position the apparatus parallel to the direction of the slope so that the boom operations will be in the “up-hill” direction. If possible, the apparatus should be facing “down-hill” (turntable past the objective)

C) Generally, the boom has enough clearance to reach most 3rd floor windows and above when operating over the crew cab

D) Properly positioned, the Tower Ladder can potentially cover 6 Row Frames

A

ANSWER: A) When positioning the Tower Ladder in a vacant lot, the chauffeur and OV FF must conduct a survey for potential collapse zones and voids. (INCORRECT)

(Ladders 6 - 2.5)

A - OFFICER and Chauffeur.

B - sec 2.4

C - Top of p-3

D - sec 2.1.2

100
Q

Being a Company Commander of a Tower Ladder, you are responsible for drilling your members on the proper positioning of the apparatus when operating at structural fires. Choose the incorrect statement you made during drill in regards to positioning a Tower Ladder.

A) For Rowframe fires, the TL can potentially cover six Rowframes

B) The TL may be placed on the sidewalk either fully or partially to reach upper levels or to gain better vantage points

C) The preferred method of rescue is the angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends in for the rescue

D) For top floor fires in a H-Type multiple dwelling, positioning a TL to the fire apartment for VEIS and secondary egress can dramatically influence an operation

A

ANSWER: D) For top floor fires in a H-Type multiple dwelling, positioning a TL to the fire apartment for VEIS and secondary egress can dramatically influence an operation (INCORRECT)

(Ladders 6 ch 2)

  • For top floor fires in a H-Type multiple dwelling, positioning a TL in the THROAT can dramatically influence an operation
  • The LSR and saw shall be taken to the roof when the bucket is used for roof access
101
Q

As a Company Commander of a Tower Ladder, you should be well versed in its use. Choose the incorrect tactic/positioning when using a Tower Ladder.

A) Regardless of initial placement, changing conditions may require repositioning the Tower Ladder apparatus.

B) Generally, the boom has enough clearance to reach most 2nd floor windows and above when operating over the crew cab

C) The preferred method of rescue is the angular approach where the member operating the bucket first raises the bucket up to the victim’s level, and out of the victim’s reach, and then extends in for rescue

D) When positioning a Tower Ladder in a vacant lot, the officer and chauffeur must conduct a survey for potential collapse zones and voids

A

ANSWER: B) Generally, the boom has enough clearance to reach most 2nd floor windows and above when operating over the crew cab. (INCORRECT)

(Ladders 6 - Chapter 2 - pg 3)

  • (3rd) THIRD FLOOR and above
102
Q

Due to a lack of space in a Tower Ladder bucket, the number of firefighters operating in the bucket should be limited to how many?

A) 1

B) 2

C) 3

D) 4

A

ANSWER: B) 2

(Ladders 6 ch 1 sec 1.3)

  • At the start of every tour verify the platform control switch on the pedestal is NOT engaged, as this will deactivate the bucket controls.
103
Q

Exterior walls can be breached with a maul and/or power tools. Breaching may be necessary to gain access for life saving or stream penetration. From the following choices listed below choose the most correct tactic used to breach an exterior wall.

A) When using the maul to breach cinder blocks (ex: vacant-sealed windows), start at the bottom

B) When the power saw is being used to cut through brick and concrete, the carbide tip blade shall be used

C) Cuts in brick walls should be rectangular with the long side facing upwards to prevent collapse

D) When cutting brick exterior walls, the first and second cuts should be at the brickwork since the easiest cut is at the mortar joint and the blade will usually be worn

A

ANSWER: D) When cutting brick exterior walls, the first and second cuts should be at the brickwork since the easiest cut is at the mortar joint and the blade will usually be worn.

(Tower Ladders ch 5 sec 5.2)

A - Start at the top

B - Combination metal/concrete saw blade (diamond blade) shall be used

C - Cuts in brick walls should be TRIANGULAR with the VERTEX angle facing upwards to prevent collapse

104
Q

When using the Tower Ladder as a High Point Anchor, the only tactic that is correctly indicated can be found in which choice?

A) The preferred location for the high point anchor is the landing pads of the bucket

B) Remove all members from apparatus (except chauffeur), turn the siren to the “on” position and place the apparatus to the “off” position

C) In certain circumstances a Tower Ladder can be used to lift a patient

D) The metal stokes basket should be utilized at all high point anchor operations

A

ANSWER: D) The metal stokes basket should be utilized at all high point anchor operations.

(Ladders 6 sec 5.4)

A - The preferred location is under the bucket…NOT LANDING PADS….. Under no circumstances shall the landing pads of the bucket be used as a high point anchor

B - ALL MEMBERS…INCLUDING CHAUFFEUR
C- Under NO circumstances should a TL be used as a crane to “lift” a patient

105
Q

The most correct procedure when cutting a peaked roof from a TL basket can be found in which choice?

A) There is a total of 5 cuts

B) The size of the cut will depend on the reach of the operator. Never overextend

C) The first cut is made perpendicular to the ridge pole

D) The saw must be started outside the bucket and kept outside the bucket until it is shut off

A

ANSWER: B) The size of the cut will depend on the reach of the operator. Never overextend.

(Tower Ladders ch 3 sec 3.5)

A - 4 cuts (4th cut is KO - coffin cut is 2nd cut)

C - PARALLEL to the ridge pole

D - The saw shall be started INSIDE the bucket and then hold it outside the bucket until it is shut off

  • Look at picture on pg 6 to see the 4 cuts in order. This makes for an easy test question.
106
Q

The most correct statement made when it comes to Tower Ladder operations can be found in which choice?

A) The joystick controls in the bucket will allow for smoother positioning than the controls at the pedestal. For this reason the Bucket FF should, in most cases, perform delicate movements

B) Due to lack of space, the number of firefighters operating in the bucket should be limited to two. Each member operating in a Tower Ladder bucket MUST personally verify the the placement of both door latches in the locked position prior to movement

C) The primary means of communication between the bucket and the pedestal is the HT on the tactical channel

D) A test of the Tower Ladder intercom system will be made once each day

A

ANSWER: B) Due to lack of space, the number of firefighters operating in the bucket should be limited to two. Each member operating in a Tower Ladder bucket MUST personally verify the the placement of both door latches in the locked position prior to movement.

(Ladders 6 ch 1)

A - The controls at the PEDESTAL WILL ALLOW FOR SMOOTHER POSITIONING than the joystick controls in the bucket For this reason the Pedestal FF should, in most cases, perform delicate movements.

C - The primary means of communication between the bucket and the pedestal is the Tower Ladder INTERCOM system.

D - A test of the intercom system shall be made EACH TOUR (twice each day) and at the initial stages of placing the TL into operation.

107
Q

The only correct procedure when using a power saw to cut through a brick wall can be found in which choice?

A) When using a power saw, the carbide tip blade shall be used

B) Cut in brick walls shall be rectangular in shape

C) The second cut should be made at the mortar joint

D) Openings made in brick walls should be large enough so the saw can be inserted to cut an inner wall, if necessary

A

ANSWER: D) Openings made in brick walls should be large enough so the saw can be inserted to cut an inner wall, if necessary.

(Tower ladders ch 5 sec 5)

A - Combination metal/concrete saw blade (diamond blade) shall be used

Note: TB Tools 9 app 1 sec 2.2.2 - Silicon Carbide disc will cut through concrete and other masonry materials.

B - TRIANGLE in shape with the vertex angle upwards to prevent collapse

C - 1st and 2nd cuts should be made at the brickwork since the easiest cut THIRD (3rd cut) is at the mortar joint and the blade at this point will usually be worn.

108
Q

A properly positioned Tower Ladder at a Rowframe fire can cover up to how many buildings?

A) 3

B) 4

C) 5

D) 6

A

ANSWER: D) 6

(TL ch 2 sec 2.1.2)

  • Also: when positioned on a side street the Tower Ladder may cover up to 3 buildings
  • The LSR and saw shall be taken to the roof when the bucket is used for roof access
109
Q

As a newly promoted officer bouncing through a TL company, its important to know and understand proper TL placement involving the bucket in order for you to carry out a proper drill. After studying the Ladders 6 bulletin, you wrote down four drill points for an upcoming drill. You were incorrect in which point?

A) For the removal of a unconscious, incapacitated, or an obese person, the preferred position of the bucket at a window/fire escape would be to align the top bucket rail with the window sill or top rail of the fire escape

B) For the removal of a conscious person at a window or fire escape, the proper position of the bucket would be to position the middle of the bucket at a level where the person can easily step into it without straddling the window sill or fire escape railing

C) When preparing to move a properly positioned bucket from a roof the first movement is generally to “retract” the bucket

D) Bucket railings are not a substantial part of the bucket and shall not be used as a substantial object when tying off

A

ANSWER: C) When preparing to move a properly positioned bucket from a roof the first movement is generally to “retract” the bucket. (INCORRECT)

(Ladders 6 - 3.3)

  • When preparing to move a properly positioned bucket from a roof the first movement is generally to “RAISE” the bucket.