Successful Int. Projects thru Effective Contract Docs - The Construction Contract Flashcards
The simplest form of contract is:
The single lump sum contract (Typically the contractor would do a portion of the work and subcontract out those portions that are more efficiently done by others)
Describe the single lump sum contract
Typically the contractor would do a portion of the work and subcontract out those portions that are more efficiently done by others
Describe a negotiated ccontract
In the negotiated contract there is no official bidding involved. The contractor is selected based on his/her credentials, enters into negotiations with the owner to arrive at a contract sum
What is commonly known as value engineering
It’s when the contractor is engaged very early in the project and has input into some of the design decisions by providing cost perameters in a process.
Define the segregated contract:
There are a number of seperate prime contractors, one for each major portion of the work. Each seperate contractor may have his/her own subcontractors. The task of coordinating the work of a number of contractors rests with the owner, who often relies on the design professional to act as coordinator
What is a cost plus contract?
The contractor agrees to complete the work of the project for whatever amount is costs him/her plus a fixed fee, or a percentage of the cost to cover overhead and profit
List one pro for the cost plus contract
Pro: The contractor cannot lose money, and the owner is assured of getting exaclty what they pay for
List one con for the cost plus contract?
The contractor has no real incentive to save money for the owner
What is one way to potentially avoid a delimma in the cost plus contract would be to:
Let the contractor suggest means of saving costs and sharing in the resulting savings (i.e.: the contractor proposed to furnish a fully acceptable material for a stipulated savings his/her fee would be increased by a pre-arranged percentage of that savings) An accurate method of cost accounting and verification along with complete and well prepared documents is essential.
When is a construction manager contract typically used?
On large projects, or a larger scale project. In this case the individual is simply the broker/contractor in a different role.
What are the (5) fundamental tasks that are covered in a legally binding document between the owner and the contractor?
Identify the agreeing parties - Identifying the work to be performed by the contractor - Set forth the terms of payment for the work (what the law calls consideration) - State the time for performance - be sealed with the signatures of the parties
List the documents that make up a contract
Conditions of the Contract - Agreement - the drawings, specifications, any addenda incorporated before the agreement - any change orders incorporated after the agreement
AIA Form A101, Standard Form of Agreement Between Owner & Contractor, Article I simply defines what?
The contract documents
AIA Form A101, Standard Form of Agreement Between Owner & Contractor, Article II defines what?
The scope of work
AIA Form A101, Standard Form of Agreement Between Owner & Contractor, Article III establishes what?
The time for performance, which is the date of commencement, often the same as the Notice to Proceed. Also establishes the date of substantial completion and provides for liquidated damages if applicable