Successful Int. Projects thru Effective Contract Docs - Construction Budgeting & Estimating Flashcards

1
Q

What are 2 types of estimates that are used in the early stages of a project?

A

Order of magintude estimate and square foot estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is an Order of Magnitude Estimate?

A

A ballpark estimate arrived at quickly based on scanty information and is intended to indicate only a rough range of probable cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a square foot estimate?

A

It is similar to the magnitude estimate and requires a knowledge of cost from a comparable project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Two slightly more accurate estimates to use when a project is further along are:

A

Component Estimate and Unit Price Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a component estimate?

A

It is an estimate compiled from previous projects using actual cost as they are reflected on the contractors bid breakdown or schedule of values.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is a unit price estimate used?

A

This is the type of estimate used by contractors to estimate their bids. It is exhaustive and time consuming. It cannot be used as a checkpoint because the documents have to be complete in order to do