Ch 14 Construction Drawings Flashcards

1
Q

Construction drawings are also called ________ ________.

A

Working Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

One of the most important parts of the contract documents, that describes, in detail, the extend of the work and the locations, dimensions, and relationships of the various construction elements. They must show the technically correct way of meeting the functional requirements of design. The drawings form part of the contract and are LEGAL DOCUMENTS.

A

Construction Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

________ _________ represent the interior designer’s final decisions concerning design, building methods, and construction technology.

A

Construction Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In addition to being accurate, construction drawings must coordinate with the . . .

A

Specifications and Consultant’s Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the usual sequence for a set of construction drawings produced and coordinated by the the interior designer?

A

(1) Title and Index Sheet (2)Floor Plans (3) RCP (4) Elevations (5) Details (6) Mechanical Drawings (7) Electrical Drawings (8) Fire-Protection Drawings. ** If structural drawings are needed, they are placed AFTER the interior design drawings and BEFORE the mechanical drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What dictates the general standardized sequence of construction drawings?

A

The normal sequence of construction and through many years of use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

On smaller projects, title and index sheet information is placed where on the construction drawings?

A

Usually on the first sheet of the set, which is usually the floor plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the common types of floor plans used on midsize to large projects?

A

Demolition Plans, Construction Floor Plans, Finish Plans, Telephone and Power Plans, and Furniture Plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does the number of details in a set of construction drawings depend on?

A

The size and complexity of the project and whether the job is being bid or negotiated. If it is a competitive bid, the details must be very complete and fully describe the extent of the work so the client will get a valid cost quote. On smaller, negotiated contract jobs where the majority of details are somewhat standard, there may be fewer details because some final decisions may be made during construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

On most residential projects, light fixtures and switch locations may be shown schematically by the interior designer but . . .

A

it is the electrical contractor’s responsibility to show the correct gauge of wire and to circuit the system properly and according to local building codes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When are electrical drawings prepared by an electrical engineering consultant?

A

If a project includes new or revised power and lighting circuiting and specialty wiring such as fire alarms, communications systems, security systems, and the like.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Drawings should show the general configuration, size, shape and location of the components of construction with general notes to explain materials, construction requirements, dimensions, and other graphic material. Specifications will including . . .

A

Detailed requirements for material quality, workmanship, and other items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Also called floor plans or partition plans, are the most common type of floor plan and are required for EVERY PROJECT no matter the size or complexity. They are views seen as though a building were cut HORIZONTALLY ABOUT 4’-0” ABOVE THE FLOOR with the top section removed. It shows the building configuration, including all walls, dimensions, existing construction to remain, references to elevations and details drawn elsewhere, room names/numbers, floor material indications, millwork, plumbing fixures, built-in fixtures, stairs, special equipment, and notes as required to explain items on the plan. They are usually drawn at 1/8” scale, or 1/4”. If large-scale plans are required for very complex areas, they are typically drawn at 1/2” scale. IF THERE ARE OTHER PLANS IN THE SET OF DRAWINGS, THEY SHOULD BE DRAWN AT THE SAME SCALE AS THE PRIMARY CONSTRUCTION PLAN.

A

Construction Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Show which existing construction is to be removed. If the extent of demo work is MINOR, the portions of the building to be removed can be shown with dashed lines on the construction plan. A contractor needs some type of demo plan before partitions on a remodeling project can be removed.

A

Demolition Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The interior design may draw these plans for large or complex projects. They show the locations of electrical outlets, telephone outlets, and other signal systems like the locations of computer terminals and intercommunication systems. A separate plan is usually required for large projects because there is not enough room on the construction plan to show the outlets and include dimension lines to precisely locate each one. THE INTERIOR DESIGNER’S PLAN ONLY SHOWS THE OUTLET LOCATIONS. The electrical circuiting, conduit size, and other technical information are included on the plans prepared by the electrical engineer. IF THE INTERIOR DESIGNER DOES NOT PRODUCE A POWER PLAN, THEN THE POWER PLAN DRAWN BY THE ELECTRICAL ENGINEER SHOWS THE ELECTRICAL OUTLETS, TELEPHONE OUTLETS, SECURITY SYSTEMS, AND FIRE ALARM DEVICES.

A

Power Plan or Telephone Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Developed by interior designer, and lists, in tabular format, each room and the types and specifics of finishes for the floors, walls, base and ceilings.

A

Finish Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When should a separate finish plan be used?

A

When there are several finish types on each wall and other complex finish configurations, a separate finish plan can be used. SPECIFICATION ITEMS, SUCH AS INSTALLATION INSTRUCTIONS, ARE NOT INCLUDED ON THE PLAN, BUT ARE IN THE SPECIFICATIONS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Plan that shows the location of each piece of furniture on a floor plan with corresponding code numbers that identify each piece. The plans are used to itemize the furniture for pricing and ordering as well as to show the installers where to put each piece during move-in. IT IS SOMETIMES DOUBLED UP WITH THE POWER AND TELEPHONE PLAN BECAUSE THE EXACT LOCATIONS OF OUTLETS CAN BE DIRECTLY RELATED TO THE LOCATIONS OUT OUTLETS CAN BE DIRECTLY RELATED TO THE LOCATIONS AND ORIENTATIONS OF FURNITURE. For example, telephone and electrical outlets are best placed TO THE SIDE OF A DESK.

A

Furniture Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

A view of a building as seen from directly above, showing the roof of the building as well as the surrounding yards, walks, driveways, and other features within the property line. It also usually shows streets and property immediately adjacent to the site

A

Site Plan.

THE DESIGNER DOES NOT DRAW THE SITE PLAN, but the NCIDQ may ask you to identify the characteristics of a site plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Plan that shows a view of the ceiling as though it were reflected onto a mirror on the floor.

A

Reflected Ceiling Plan

The RCP should be at the same scale as the construction plan. They show PARTITIONS THAT EXTEND TO THE CEILING and those that EXTEND THROUGH THE CEILING. They also show ceiling materials, building grid lines, notes calling out ceiling heights, locations of all lights (including exit lights), sprinkler heads, air diffusers and vents, access panels, speakers, and any other item that touches the ceiling. DIMENSIONS are included where necessary to precisely locate elemants that cannot be reasonably inferred by their relationship to something else. ALTHOUGH LIGHTS AND AIR DIFFUSERS WILL ALSO BE INDICATED ON THE ENGINEERING CONSULTANT’S DRAWINGS, EVERYTHING SHOULD BE SHOWN ON THE INTERIOR DESIGNER’S RCP. This is so the designer can have a full understanding of what the final ceiling will look like. The RCP will also have section cut reference marks and other notations referring to details drawn elsewhere in the set.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A drawing showing a vertical surface from a point of view PERPENDICULAR to the surface. All portions of the drawings are done at the same scale. They are drawn for interior design projects to indicate the configuration and finish of wall surfaces. They are also used to show the vertical dimensions and design of millwork and other freestanding construction. They are useful for showing the configuration of a surface, vertical dimensions, openings a walls, built-in items, materials and finishes on a wall, and the locations of switches, thermostats, and other wall-mounted equipment

A

Elevation

Elevations can also include horizontal dimensioning that would not fit on a floor plan. They are also used to indicate references to other sections and details with the use of section cut lines. Common scales are 1/4” for simple wall planes and 3/8” or 1/2” for more complex surfaces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Drawing showing what a part of the construction would look like if there was a cut straight through it. It shows a view that does not really exist but one that is very useful to showing the relationship between materials. It can be horizontal, as with plans, or vertical, to show partition construction

A

Section

Either way, the section cut is PERPENDICULAR to the plane of construction that will be exposed in the detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Technically, an elevation is a type of ______ ____.

A

Section Cut Generally, only the outline of the section is shown because the actual construction of the floor, walls and ceiling is not the important element of an elevation drawing.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The manner in which an assembly of several parts is organized and connected is commonly referred to as a ________. The construction drawing showing such as a part is known as a ______ __________.

A

Detail; Detail Drawing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

In addition to showing the materials cut by a section, a detail will also show . . .

A

what is beyond the section cut. In effect, the section is a small elevation of the portion of construction near the object through which the section is cut.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Details are commonly drawn at what scales?

A

1”, 1-1/2”, or 3” For very small and complex construction elements, half-size or even full-size drawings can be produced.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Show information in tabular format with rows and columns of data, and are used because they are a very efficient way to communicate a large amount of complex information in a small space.

A

Schedules

Common schedules for interior design construction include room finish, door, kitchen equipment, millwork, and hardware schedules. Schedules may also refer to other parts of the drawing.

28
Q

What are some common drafting concerns with any project?

A

Sheet size to use, make up of the title block, and how individual sheets are organized. Also, if using CAD, layering.

29
Q

Sheet size is most typically determined by . . .

A

the size needed to draw a floor plan on one sheet without dividing the plan into sections.

30
Q

What are the three systems that standardizes sheet sizes are based on?

A

Architectural, ANSI, and ISO

31
Q

ISO sheet sizes are based on . . .

A

SI System of Measurement

32
Q

Most offices in the US use _______ as their standard for sheet sizes.

A

Architectural

33
Q

The US federal government requires projects to us _____ sheet sizes.

A

ANSI

34
Q

A note placed in the title block or elsewhere on the drawing sheet with an identifying number that is used in the field of the drawing itself. This will minimize the space required on the drawing and can save time when repetitious notes are required in several places. The __________ numbers can also be coordinated with specification numbers.

A

Keynote

35
Q

What information should be on every title block?

A

(1) Designer’s name, address, phone number and fax number (logo and web address/email is optional) (2) Consultants’ names, addresses and phone numbers, and sometimes fax and email (3) Project title and address (4) Owner’s name and address, if the owner desires it (some don’t want to be identified) (5) Project number (6) Space for professional stamps , 2” x 2” for each stamp (7) Revision column that includes space for the revision number, date and a brief note - leave space for 10 revisions or more (8) Sheet Title (9) Sheet Number (10) Drawn By (11) Checked By (12) Approved By, optional (13) Copyright Notice, optional but a good idea (14) Space for a key plan, which is optional but useful for large projects (15) File Number, optional (16) Scale (17) North Arrow (18) Space for Notes, Legends or Key Notes

36
Q

Sheets can be organized to conform with the ____.

A

UDS - Uniform Drawing System of the Construction Specification Institute (CSI)

37
Q

Whatever specific method of organizing sheets, offices used standard sheet sizes and generally locate the title block along the _____ side of the drawing sheet.

A

Right

38
Q

The typical drawing module is about ___ inches square.

A

6

39
Q

Refers to the system of placing particular information on a separate layer (or level) in CAD. It allows information to be shown or hidden so that several drawings can be developed from one computer file of information.

A

Layering

40
Q

Each _________ firm develops its own drawings, so coordination among everyone on the team is critical.

A

Consulting

41
Q

The primary responsibility for overall coordination should rest with . . .

A

one design professional.

42
Q

If the interior designer is responsible for retaining the services of other consultants, then the designer is usually responsible for directing and coordinating . . .

A

the consultant’s work so the final set of construction documents (dwgs and specs) represents a complete set of coordinated information. This DOES NOT mean the interior designer is responsible for the work of any of the consultants; only responsible for managing the efforts of the team.

43
Q

Structural Drawings

A

Includes framing plans, major structural sections, and connection details. Based on info from the structural engineer, the interior designer incorporates the exact sizes of structural members in the interior design details, to coordinate construction details and make sure that sufficient space is provided for construction, clearances, tolerances, and finishes.

44
Q

What structural items are shown on the interior design drawings?

A

Only the overall outline of structural walls and framing is shown on the interior design drawings. Elevations for tops of beams, structural walls, and floors are shown on both sets of drawings.

45
Q

Mechanical and Plumbing Drawings

A

Locations of mechanical equipment, layout of ductwork, pipes, fixtures, and other major components, plumbing isometrics, details of mechanical room layouts, details, and schedules.

46
Q

What mechanical and plumbing items are shown on the interior design drawings?

A

Where they interface with other construction, like registers and grilles on the RCP, plumbing fixtures, and ducts/pipes when part of an interior design detail.

47
Q

Electrical Drawings include:

A

Power plans, lighting plans, telecommunication plans, signal and security systems, one-line diagrams, and schedules.

48
Q

A graphic indication (using an arrowhead and the numbers of the circuits) that the line on the drawing connecting lights or outlets is connected to particular circuit breakers in a particular electrical panel box. This is used so that the entire line does not have to be drawn to the panel box, avoiding clutter on the drawings.

A

Home Run

49
Q

What electrical items are shown on the interior design drawings?

A

Electrical elements are shown only for coordination and location only. Where the location of outlets are critical, the interior design drawings may include a separate power and telephone plan with exact dimensions. Luminaires are shown on the RCP . In SOME cases, the interior designer may want to show the locations of switches on the RCP.

50
Q

In most design offices, the responsibility for coordination usually falls on the . . .

A

Project Manager

51
Q

What ways can be used to accomplish coordination during the design and production of contract documents?

A

(1) Regularly scheduled meeting. (2) Progress prints should be exchanged between the interior design and consultants. (3) The PM must be responsible for notifying all consultants, in writing, of changes made as they occur. (4) The interior designer must have a thorough method for checking and coordinating the entire drawing set before issue for bidding or negotiation of a construction contract.

52
Q

Who is responsible for submitting the documents to the local building department, or the authority having jurisdiction (AHJ)?

A

Contractor

53
Q

Who is responsible for changes to the documents after being reviewed to the AHJ/building department?

A

Interior Designer

54
Q

Who is responsible for making sure that the project design complies with all applicable codes and regulations?

A

Interior Designer

55
Q

What is required of the IBC for most codes?

A

Location Plan, Means of Egress, Fire-Rated Partitions, Exit Signs and Fire Extinguisher, Fire Protection Drawings, Structural Calcs, Mechanical & Electrical Drawings, Specifications, and may also want names and addresses of all design professionals, address of the property, codes being used, area of space designed, construction type and occupancy group, occupant load calculations, sprinklered/non-sprinklered, or the valuation of new construction.

56
Q

In general, ________ ____________ must be of sufficient clarity to indicate the location, nature, and extent of the proposed work and how it will conform to the code.

A

Construction Documents

57
Q

When can construction begin?

A

After the AHJ has issued the building permit, which is displayed at the job site.

58
Q

What inspections of the job site affect the interior designer?

A

Framing inspections, GWB inspections, plumbing, mechanical, and electrical inspections, and a final inspection.

59
Q

Who is responsible for calling for inspections at the appropriate times in order not to delay work?

A

Contractor

60
Q

When is the framing inspection done?

A

Before both sides of partitions are covered and verifies that partitions are built correctly. At this time, rough electrical and plumbing inspections are also done to confirm that all work inside the partition. Mechanical inspections are also done when the equipment is roughed in.

61
Q

When is a wallboard inspection done?

A

After all the wallboard is up, but before finishing, to verify that all walls and fire-rated partitions are constructed correctly.

62
Q

What is inspected at a final inspection?

A

Finishes, final electrical, and final plumbing, and things such as glazing, handrails, door installations, and other elements. It may also include testing the fire alarm and sprinkler system, with the involvement of the fire marshal or fire department.

63
Q

When is a CO issued?

A

When the final inspection has been successfully completed. It is issued by the AHJ. It’s also sometimes called a letter of occupancy or a use and occupancy letter.

64
Q

When is A TCO issued?

A

In some cases, especially with large projects, when some problem has arisen, a Temporary Certification of Occupancy may be issued, allowing the client to occupy a portion the space while the remainder is complete. Also called a Partial Certificate of Occupancy. This is only issued if there is no danger with partial occupancy.

65
Q

What can be done if a building permit is not approved by the AHJ?

A

An appeal can be made to the Board of Appeals, which is a formal process by which a request is made in writing stating the reason why the designer feels the proposed design meets the intent of the code. The board of appeals may consult with other professionals and issue a ruling, either denying the application or issuing a variance.