Task Item No. 5-5: Incorporate project-specific requirements into Division 01 sections. Flashcards

1
Q

You Should Understand

Task Item No. 5-5: Incorporate project-specific requirements into Division 01 sections.

  • Edit Division 01 to incorporate and not duplicate information
  • Understand dependencies and relations relative to commissioning
  • Understand Owner’s training requirements, and protocols and procedures of training
  • Understand project design requirements and parameters
  • Understand and coordinate the many divisions of the Project Manual to eliminate conflict and redundancy:
    • Division 01 and Division 00
    • Division 01 and Divisions 02-49 (technical sections)
    • Division 01 and the General Conditions/Owner Requirements
  • Identify appropriate locations within Division 01 to expand on responsibilities defined in General Conditions
  • Establish procedures assigned to parties to the Contract
A

Reading List

Task Item No. 5-5: Incorporate project-specific requirements into Division 01 sections.

CSPG 1.8.3 through 1.8.4, 1.14, 7, 11.6.1, and 13.5.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

1.8.3 Division 01—General Requirements

Division 01 contains sections that specify procedures affecting project quality. The following are several Division 01 sections that often include provisions for quality assurance or establish quality controls over the work:

  • Regulatory Requirements. Identifies AHJs along with related codes and requirements.
  • Project Management and Coordination. Describes various types of meetings to.
  • Submittal Procedures. Includes such things as shop drawings, product data, and samples and
  • . Includes subjects such as manufacturer qualifications, supplier qualifications, installer qualifications, and testing agency qualifications as well as field samples, mock-up requirements, and contractor’s quality control.
  • . Includes subjects such as testing laboratory services, source and field testing, and inspection services.
  • . Establishes procedures for proposing and evaluating substitutions during the bidding/negotiating/purchasing and construction periods without compromising quality.
  • Commissioning. Identifies process and requirements for facility, system, and component operation testing and checkout.
A

1.8.3 Division 01—General Requirements

Division 01 contains sections that specify procedures affecting project quality. The following are several Division 01 sections that often include provisions for quality assurance or establish quality controls over the work:

  • Regulatory Requirements. Identifies AHJs along with related codes and requirements.
  • Project Management and Coordination. Describes various types of meetings to ensure and monitor quality through interaction of the participants.
  • Submittal Procedures. Includes such things as shop drawings, product data, and samples and provide proactive quality assurance through mutual understanding of the design intent and the contract requirements
  • Quality Assurance. Includes subjects such as manufacturer qualifications, supplier qualifications, installer qualifications, and testing agency qualifications as well as field samples, mock-up requirements, and contractor’s quality control.
  • Quality Control. Includes subjects such as testing laboratory services, source and field testing, and inspection services.
  • Substitution Procedures. Establishes procedures for proposing and evaluating substitutions during the bidding/negotiating/purchasing and construction periods without compromising quality.
  • Commissioning. Identifies process and requirements for facility, system, and component operation testing and checkout.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
A

Refer to Item 5-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7.1 Division 01—General Requirements

The sections in Division 01, which are collectively referred to as the General Requirements, specify,, , , and .

Division 01 sections expand on certain of the administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications. Administrative and procedural requirements unique to a specific section should be covered in the affected section. Division 01 sections cover general requirements for execution of the work and should be written in language broad enough to apply to sections in Divisions 02 through 49. Without Division 01, these requirements would otherwise be repeated throughout the specifications, and the possibility of conflicts and omissions would be increased.

A

7.1 Division 01—General Requirements

The sections in Division 01, which are collectively referred to as the General Requirements, specify administrative requirements, procedural requirements, temporary facilities and controls, performance requirements, and life cycle activities.

Division 01 sections expand on certain of the administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications. Administrative and procedural requirements unique to a specific section should be covered in the affected section. Division 01 sections cover general requirements for execution of the work and should be written in language broad enough to apply to sections in Divisions 02 through 49. Without Division 01, these requirements would otherwise be repeated throughout the specifications, and the possibility of conflicts and omissions would be increased.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

7.2 Organizational Basis for Division 01

A

The administrative sections of Division 01 parallel the succession of titles in MasterFortmat® and the procedural sequence of PART 1, PART 2, and PART 3 in SectionFormat™ to lay out a consistent and logical organization of titles.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

7.2.2 Division 01 and SectionFormat™

Division 01 specifiescommon to many specification sections and to the project as a whole. Most of these requirements are related to the of the project, and others govern products and execution requirements.

Sections aligning with:

Are:

1

PART 1—GENERAL

A

Summary

2

PART 2—PRODUCTS

B

Price and Payment Procedures

3

PART 3—EXECUTION

C

Execution and Closeout Requirements

D

Product Requirements

E

Life Cycle Activities

F

Quality Requirements

G

Performance Requirements

H

Temporary Facilities and Controls

I

Administrative Requirements

A

7.2.2 Division 01 and SectionFormat™

Division 01 specifies procedural requirements common to many specification sections and to the project as a whole. Most of these requirements are related to the administrative activities of the project, and others govern products and execution requirements.

1. PART 1—GENERAL

A Summary, B Price and Payment Procedures, I Administrative Requirements, F Quality Requirements, H Temporary Facilities and Controls

2. PART 2—PRODUCTS

D Product Requirements, G Performance Requirements

3. PART 3—EXECUTION

C Execution and Closeout Requirements, E Life Cycle Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7.3.1 Procurement Requirements

By definition in American Institute of Architects (AIA) and Engineers Joint Contract Documents Committee (EJCDC) general conditions, procurement requirements are not a part of the:

  1. Construction Documents
  2. Bidding Requirements
  3. Contract Documents
  4. All of the above

The procurement requirements should not repeat Division 01 provisions but should instead refer to the appropriatesections, by number and title, to direct the bidder to relevant information.

A

7.3.1 Procurement Requirements

By definition in American Institute of Architects (AIA) and Engineers Joint Contract Documents Committee (EJCDC) general conditions, procurement requirements are not a part of the:

  1. Construction Documents
  2. Bidding Requirements
  3. Contract Documents
  4. All of the above

The procurement requirements should not repeat Division 01 provisions but should instead refer to the appropriate 3 / Division 01 sections, by number and title, to direct the bidder to relevant information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

7.3.2 Owner-Contractor Agreement

A

The owner-contractor agreement includes by reference all other contract documents. Certain provisions of the owner-contractor agreement are supplemented by the provisions of Division 01 sections that define in greater detail the responsibilities of the parties to the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

7.3.3 General Conditions

Thegovern the execution of the work and apply broadly to sections of the specifications, including those in Division 01. As these topics are covered only in very broad terms, they must be specified in further detail in Division 01 to. Although the topics are addressed in two locations, the Construction Specifications Institute (CSI) principle of “say it once” is not violated because the requirements are stated in two different levels of detail, without duplication or conflict

A

7.3.3 General Conditions

The general conditions of the contract govern the execution of the work and apply broadly to sections of the specifications, including those in Division 01. As these topics are covered only in very broad terms, they must be specified in further detail in Division 01 to tailor requirements to a specific project. Although the topics are addressed in two locations, the Construction Specifications Institute (CSI) principle of “say it once” is not violated because the requirements are stated in two different levels of detail, without duplication or conflict

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

7.3.4 Supplementary Conditions

A

Supplementary conditions should not repeat information contained in the General Conditions or encroach on topics that belong more appropriately in Division 01. Proper coordination between Division 01 and supplementary conditions will avoid conflicts, omissions, and duplications.

Other than a statement establishing the authority of Division 01, the supplementary conditions should not contain general references to Division 01.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

7.3.5 Other Specification Sections

Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01. Project requirements become more specific for each successive level of a three-tier hierarchy:

  • Thestate provisions in broad terms.
  • elaborate on the broad provisions of the conditions of the contract, but it is still written broadly enough to apply to the work of all specification sections.
  • in a specification section becomes very specific in project requirements for that section only.
A

7.3.5 Other Specification Sections

Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01. Project requirements become more specific for each successive level of a three-tier hierarchy:

  • The general conditions state provisions in broad terms.
  • Division 01—General Requirements elaborate on the broad provisions of the conditions of the contract, but it is still written broadly enough to apply to the work of all specification sections.
  • PART 1—GENERAL in a specification section becomes very specific in project requirements for that section only.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

7.3.6 Drawings

Drawings graphically define certain Division 01 subject matter, such as the extent of work, and may define related work that may or may not be part of the contract.

Sections, such as those covering,, and, usually require extensive delineation on the drawings and close coordination between the drawings and Division 01.

A

7.3.6 Drawings

Drawings graphically define certain Division 01 subject matter, such as the extent of work, and may define related work that may or may not be part of the contract.

Sections, such as those covering use of the site, phased construction, and multiple prime contracts, usually require extensive delineation on the drawings and close coordination between the drawings and Division 01.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

7.4.1 Coordination with Division 01—General Requirements

A number of articles in the general conditions are usually expanded in Division 01—General Requirements to accommodate specific administrative and procedural requirements of a project. General and supplementary conditions are written in a paragraph style, while Division 01 is written in the three-part SectionFormat™.

Proper use of Division 01 avoids mixing conditions of the contract with the administrative and procedural details of the specifications. Coordination is necessary between each section of Division 01 and the sections of Divisions 02 through 49, and among the sections of Division 01 that cover interrelated administrative and procedural requirements.

As many of the contractual relationships and responsibilities described in Division 01 sections for any project are required by the owner, the A/E should obtain instructions for preparing the affected sections. The A/E should establish the basic responsibilities of the team members for preparation of the Division 01 requirements and for overall coordination of the specifications. This involves close coordination of Division 01 provisions at an early stage in the production of the contract documents to avoid conflicts, duplication, and omissions in the project manual. The coordination effort should include:

Multiple sections within an individual division have administrative and procedural requirements unique to that division. However, the common requirements should be specified in.

A

7.4.1 Coordination with Division 01—General Requirements

A number of articles in the general conditions are usually expanded in Division 01—General Requirements to accommodate specific administrative and procedural requirements of a project. General and supplementary conditions are written in a paragraph style, while Division 01 is written in the three-part SectionFormat™.

Proper use of Division 01 avoids mixing conditions of the contract with the administrative and procedural details of the specifications. Coordination is necessary between each section of Division 01 and the sections of Divisions 02 through 49, and among the sections of Division 01 that cover interrelated administrative and procedural requirements.

As many of the contractual relationships and responsibilities described in Division 01 sections for any project are required by the owner, the A/E should obtain instructions for preparing the affected sections. The A/E should establish the basic responsibilities of the team members for preparation of the Division 01 requirements and for overall coordination of the specifications. This involves close coordination of Division 01 provisions at an early stage in the production of the contract documents to avoid conflicts, duplication, and omissions in the project manual. The coordination effort should include:

Multiple sections within an individual division have administrative and procedural requirements unique to that division. However, the common requirements should be specified in Division 01.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

7.5 Commonly Used Division 01 Sections

A

See next cards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

7.5.1 Section 01 10 00—Summary

  • Section 01 11 00—: Use this section to describe the work if all of the work required by the project manual and drawings is to be accomplished under one contract.
  • Section 01 12 00—: Use this section if the work described in the project manual and drawings is to be accomplished by more than one contract.
  • Section 01 14 00—Work Restrictions: Specify owner requirements for or occupancy of existing buildings. Carefully define restrictions on, especially if the project area will be occupied during construction. Limit this section to restrictions on the contractor’s use of the premises
A

7.5.1 Section 01 10 00—Summary

  • Section 01 11 00—Summary of Work: Use this section to describe the work if all of the work required by the project manual and drawings is to be accomplished under one contract.
  • Section 01 12 00—Multiple Contract Summary: Use this section if the work described in the project manual and drawings is to be accomplished by more than one contract.
  • Section 01 14 00—Work Restrictions: Specify owner requirements for early partial occupancy of new construction or occupancy of existing buildings. Carefully define restrictions on the contractor’s use of premises, especially if the project area will be occupied during construction. Limit this section to restrictions on the contractor’s use of the premises
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. 5.2 Section 01 20 00—Price and Payment Procedures
    * Section 01 21 00—Allowances: Allowances may be used when certain design decisions have not been made and whenprior to the start of work.
  • Section 01 22 00—Unit Prices: Define who is responsible for actual, including procedures for administration and coordination. The preferred practice is to include a listing of unit price items showing the item number, a designation of the item, and the unit and method of measurement in the unit price schedule incorporated into the agreement.
  • Section 01 23 00—Alternates: Clearly define theof each alternate and the procedure that will be used for evaluation and acceptance. Refer to each specification section that contains technical requirements for alternate products or systems or their installation.
  • Section 01 24 00—Value Analysis: Specify general requirements and procedures for, including description of participants, schedule, costs, evaluation, and reports. Indicate the method of acceptance and the implementation of results.
  • Section 01 25 00—Substitution Procedures: Specify basic requirements for consideration of the contractor’s, including general rules and procedures for determining whether products are equivalent.
  • Section 01 26 00—Contract Modification Procedures: Provide a method to allow the contractor or the ownerabout an item of work insufficiently described or detailed in the contract documents. Specifyto process contract modifications and to substantiate claims for extra time and costs. Stipulate the types of forms to be used by the contractor and the A/E to request prices for changes and to document the type of modifications to the contract.
  • Section 01 29 00—Payment Procedures: Specify related requirements for the contractor’s submittal of a schedule of values and requirements for the contractor’s submittal of.
A
  1. 5.2 Section 01 20 00—Price and Payment Procedures
    * Section 01 21 00—Allowances: Allowances may be used when certain design decisions have not been made and when quantities or unknowns cannot be determined prior to the start of work.
  • Section 01 22 00—Unit Prices: Define who is responsible for actual measurement of unit price quantities, including procedures for administration and coordination. The preferred practice is to include a listing of unit price items showing the item number, a designation of the item, and the unit and method of measurement in the unit price schedule incorporated into the agreement.
  • Section 01 23 00—Alternates: Clearly define the limits of the work of each alternate and the procedure that will be used for evaluation and acceptance. Refer to each specification section that contains technical requirements for alternate products or systems or their installation.
  • Section 01 24 00—Value Analysis: Specify general requirements and procedures for conducting value analysis, including description of participants, schedule, costs, evaluation, and reports. Indicate the method of acceptance and the implementation of results.
  • Section 01 25 00—Substitution Procedures: Specify basic requirements for consideration of the contractor’s proposals for substitution of products, including general rules and procedures for determining whether products are equivalent.
  • Section 01 26 00—Contract Modification Procedures: Provide a method to allow the contractor or the owner to request clarification about an item of work insufficiently described or detailed in the contract documents. Specify the modification procedures to be followed and the data required to process contract modifications and to substantiate claims for extra time and costs. Stipulate the types of forms to be used by the contractor and the A/E to request prices for changes and to document the type of modifications to the contract.
  • Section 01 29 00—Payment Procedures: Specify related requirements for the contractor’s submittal of a schedule of values and requirements for the contractor’s submittal of applications for payment.
17
Q

7.5.3 Section 01 30 00—Administrative Requirements

  • Section 01 31 00—Project Management and Coordination: Specify requirements and procedures for.
  • Section 01 32 00—Construction Progress Documentation: Specify requirements for the contractor’s submittal of construction, including type of schedule and time allowed for submittal, requirements for daily reports and.
  • Section 01 33 00—Submittal Procedures: Specify requirements for a schedule of submittals,, including reports and data to be processed as a basis prior to accepting the product or activity and the required format of each.
  • Section 01 35 00—Special Procedures: Specify procedures for projects requiringof work including restorations, preservations, historic restorations, alterations, and hazardous material abatement. Specify procedures for, including airports, detention facilities, hospitals, shopping centers, and nuclear facilities.
A

7.5.3 Section 01 30 00—Administrative Requirements

  • Section 01 31 00—Project Management and Coordination: Specify requirements and procedures for project coordination, project meetings, and project/site administration, and coordination drawings.
  • Section 01 32 00—Construction Progress Documentation: Specify requirements for the contractor’s submittal of construction progress schedule, including type of schedule and time allowed for submittal, requirements for daily reports and photographic documentation.
  • Section 01 33 00—Submittal Procedures: Specify requirements for a schedule of submittals, requirements for shop drawings, product data, and samples, including reports and data to be processed as a basis prior to accepting the product or activity and the required format of each.
  • Section 01 35 00—Special Procedures: Specify procedures for projects requiring exceptional or unusual workmanship of work including restorations, preservations, historic restorations, alterations, and hazardous material abatement. Specify procedures for specific facility types, including airports, detention facilities, hospitals, shopping centers, and nuclear facilities.
18
Q

7.5.4 Section 01 40 00—Quality Requirements

Specify the proceduresthe quality of the construction and performance of the contractor; construction, review, and use of mock-ups and field samples applied or assembled at the site as quality standards.

A

7.5.4 Section 01 40 00—Quality Requirements

Specify the procedures to control, measure, and report the quality of the construction and performance of the contractor; construction, review, and use of mock-ups and field samples applied or assembled at the site as quality standards.

19
Q
  1. 5.5 Section 01 50 00—Temporary Facilities and Controls
    * Section 01 51 00—Temporary Utilities: Include temporary water, fire protection, electric service, lighting, telephone, and heating, cooling, and ventilating. Specify responsibility for. Provide for equipment having special requirements.
  • Section 01 52 00—Construction Facilities: For, identify the contractor responsible for installation and costs. Specify requirements and limitations for location.
  • Section 01 53 00—Temporary Construction: Specify requirements for temporary structures required to.
  • Section 01 54 00—Construction Aids: Specify requirement . Include requirements for using tools and equipment during construction. Indicate requirements for sharing construction aids when multiple contracts are used.
  • Section 01 55 00—Vehicular Access and Parking: Specify requirements for temporary facilities requiredfor the construction or to accommodate the owner’s operations. Specify the procedures related to maintaining and controlling traffic and access to the construction.
  • Section 01 56 00—Temporary Barriers and Enclosures: Include requirements for facilities and procedures forduring construction.
  • Section 01 57 00—Temporary Controls: Include administrative and procedural provisions forand their installation and subsequent removal.
  • Section 01 58 00—Project Identification: Specify requirements and limitations for.
A
  1. 5.5 Section 01 50 00—Temporary Facilities and Controls
    * Section 01 51 00—Temporary Utilities: Include temporary water, fire protection, electric service, lighting, telephone, and heating, cooling, and ventilating. Specify responsibility for installation and usage costs. Provide for equipment having special requirements.
  • Section 01 52 00—Construction Facilities: For field offices and sanitation facilities, identify the contractor responsible for installation and costs. Specify requirements and limitations for location.
  • Section 01 53 00—Temporary Construction: Specify requirements for temporary structures required to accommodate access to the construction or to accommodate the owner’s operations.
  • Section 01 54 00—Construction Aids: Specify requirement for temporary elevators, hoists, cranes, scaffolding and platforms, and swing staging. Include requirements for using tools and equipment during construction. Indicate requirements for sharing construction aids when multiple contracts are used.
  • Section 01 55 00—Vehicular Access and Parking: Specify requirements for temporary facilities required to accommodate access and parking for the construction or to accommodate the owner’s operations. Specify the procedures related to maintaining and controlling traffic and access to the construction.
  • Section 01 56 00—Temporary Barriers and Enclosures: Include requirements for facilities and procedures for protecting facility users and existing spaces during construction.
  • Section 01 57 00—Temporary Controls: Include administrative and procedural provisions for surface water control and containment devices and their installation and subsequent removal.
  • Section 01 58 00—Project Identification: Specify requirements and limitations for project identification and temporary signs.
20
Q

7.5.6 Section 01 60 00—Product Requirements

  • Section 01 62 00—Product Options: Specify the basic requirements for contractors’ options in, including general rules and procedures for determining whether products are equivalent.
  • Section 01 64 00—Owner-Furnished Products: This section may be used to define the. Specify basic requirements and procedures for coordinating, scheduling, and receiving products to ensure that the condition of the products at the time of delivery is acceptable.
  • Section 01 65 00—Product Delivery Requirements: Specify the basic requirements for packing, shipping,.
  • Section 01 66 00—Product Storage and Handling Requirements: Specify the basic requirements forat the site.
A

7.5.6 Section 01 60 00—Product Requirements

  • Section 01 62 00—Product Options: Specify the basic requirements for contractors’ options in selecting products, including general rules and procedures for determining whether products are equivalent.
  • Section 01 64 00—Owner-Furnished Products: This section may be used to define the administrative requirements for owner-furnished products. Specify basic requirements and procedures for coordinating, scheduling, and receiving products to ensure that the condition of the products at the time of delivery is acceptable.
  • Section 01 65 00—Product Delivery Requirements: Specify the basic requirements for packing, shipping, delivery, and acceptance of products at the site.
  • Section 01 66 00—Product Storage and Handling Requirements: Specify the basic requirements for handling and storage of products at the site.
21
Q

7.5.7 Section 01 70 00—Execution and Closeout Requirements

  • Section 01 71 00—Examination and Preparation: Specify extraordinary requirements for, protection of adjacent construction, and surveying and the basic requirements for preparing to install, erect, or apply products.
  • Section 01 73 00—Execution: Specify the basic requirements for installing, applying, or erecting; the basic requirements for installing owner-furnished products and procedures for dealing with existing material and equipment.
  • Section 01 74 00—Cleaning and Waste Management: Specify requirements for. Include requirements for recycling materials.
  • Section 01 75 00—Starting and Adjusting: Specify schedule and requirements for starting and adjusting.
  • Section 01 76 00—Protecting Installed Construction: Include basic requirements and procedures for protecting finished work and existing finishes, if applicable, while continuing construction.
  • Section 01 77 00—Closeout Procedures: Specify administrative procedures forof the work. Describe the procedures required to identify, correct, and complete punch-list items.
  • Section 01 78 00—Closeout Submittals: Specify requirements for closeout submittals such as,,, and maintenance and operation data. Specify number and form of data to be submitted, such as manuals.
  • Section 01 79 00—Demonstration and Training: Specify requirements and procedures for the demonstration of the products and systems used in the facility, including training of the owner’s operations and maintenance staff.
A

7.5.7 Section 01 70 00—Execution and Closeout Requirements

  • Section 01 71 00—Examination and Preparation: Specify extraordinary requirements for preparing for construction, including initial construction layout, protection of adjacent construction, and surveying and the basic requirements for preparing to install, erect, or apply products.
  • Section 01 73 00—Execution: Specify the basic requirements for installing, applying, or erecting new and prepurchased products; the basic requirements for installing owner-furnished products and procedures for dealing with existing material and equipment.
  • Section 01 74 00—Cleaning and Waste Management: Specify requirements for cleaning during construction and final cleaning. Include requirements for recycling materials.
  • Section 01 75 00—Starting and Adjusting: Specify schedule and requirements for starting and adjusting equipment and systems.
  • Section 01 76 00—Protecting Installed Construction: Include basic requirements and procedures for protecting finished work and existing finishes, if applicable, while continuing construction.
  • Section 01 77 00—Closeout Procedures: Specify administrative procedures for substantial completion and final completion of the work. Describe the procedures required to identify, correct, and complete punch-list items.
  • Section 01 78 00—Closeout Submittals: Specify requirements for closeout submittals such as record documents, warranties, spare parts, and maintenance and operation data. Specify number and form of data to be submitted, such as manuals.
  • Section 01 79 00—Demonstration and Training: Specify requirements and procedures for the demonstration of the products and systems used in the facility, including training of the owner’s operations and maintenance staff.
22
Q

7.5.8 Section 01 80 00—Performance Requirements

A
  • Section 01 81 00—Facility Performance Requirements Specify general performance applicable to the entire facility.
23
Q

7.5.9 Cautions

A

Division 01 administrative and procedural requirements and temporary facilities and controls involve both direct and indirect costs. Over specifying in Division 01 may increase construction costs unnecessarily and may create excessive obligations for the entity administering the construction contract.

24
Q

7.6.1 Conditions of the Contract

The Allowances article in AIA Document A201, General Conditions of the Contract for Construction, provides for cash allowances that are included in the contract sum. However, the provisions limit the cash allowance to, including taxes. The contractor’s costs for labor, unloading and handling at the site, installation, overhead, profit, and other expenses are included in the contract sum unless otherwise provided in the contract documents.

The Cost of the Work; Allowances; Unit Price of Work article in EJCDC C-700, Standard General Conditions of the Construction Contract, provides for cash allowances that are included in the contract sum. The cash allowances are limited by the article’s provisions to , including taxes. If requirements stated in the general conditions must be modified to include other items, such as installation, quantities, or time, then the appropriate portions of the general conditions should be deleted in the supplementary conditions and the modified or expanded allowance requirements stated in Division 01.

A

7.6.1 Conditions of the Contract

The Allowances article in AIA Document A201, General Conditions of the Contract for Construction, provides for cash allowances that are included in the contract sum. However, the provisions limit the cash allowance to materials and equipment delivered to the site, including taxes. The contractor’s costs for labor, unloading and handling at the site, installation, overhead, profit, and other expenses are included in the contract sum unless otherwise provided in the contract documents.

The Cost of the Work; Allowances; Unit Price of Work article in EJCDC C-700, Standard General Conditions of the Construction Contract, provides for cash allowances that are included in the contract sum. The cash allowances are limited by the article’s provisions to materials and equipment delivered to the site, including taxes. If requirements stated in the general conditions must be modified to include other items, such as installation, quantities, or time, then the appropriate portions of the general conditions should be deleted in the supplementary conditions and the modified or expanded allowance requirements stated in Division 01.

25
Q

7.6.2 Specifications

Section 01 21 00—Allowances or the subordinate sections should specify theas well asrelating to handling allowances. Specific items covered by each allowance should be identified and may include cost of the product, delivery to site, installation (if applicable), and taxes. Cost items not covered by the allowance should also be identified in the order that they will be included in the contract sum. These sections should contain appropriate cross-references to sections in Divisions 02 through 49 in which the allowance items are specified.

Sections in Divisions 02 through 49 that are affected by allowances should contain an article incalling attention to the provisions for allowances. The items covered by an allowance should be cross-referenced to an allowance amount stated in the applicable Division 01 section. In addition, the A/E must provide enough information inof each section so that bidders will know exactly what is covered by the allowance. Both the products and their installation should be specified as completely as possible.

A

7.6.2 Specifications

Section 01 21 00—Allowances or the subordinate sections should specify the dollar amount or quantities as well as dollar amount or quantities relating to handling allowances. Specific items covered by each allowance should be identified and may include cost of the product, delivery to site, installation (if applicable), and taxes. Cost items not covered by the allowance should also be identified in the order that they will be included in the contract sum. These sections should contain appropriate cross-references to sections in Divisions 02 through 49 in which the allowance items are specified.

Sections in Divisions 02 through 49 that are affected by allowances should contain an article in PART 1—GENERAL calling attention to the provisions for allowances. The items covered by an allowance should be cross-referenced to an allowance amount stated in the applicable Division 01 section. In addition, the A/E must provide enough information in PART 2 and PART 3 of each section so that bidders will know exactly what is covered by the allowance. Both the products and their installation should be specified as completely as possible.

26
Q

7.7 Specifying Alternates

Most master guide specifications and standard documents do not contain extensive provisions for alternates, as they are generally unique to each project. If alternates are to be used, special provisions must be incorporated in the documents to make them effective.

  • Procurement Requirements: The solicitation, such as the, should inform bidders or proposers of the request for alternate prices.

may contain guidance for preparing alternate bids or proposals and state considerations for evaluation and award of contract. Bid or proposal forms should clearly identify alternates with.

  • Agreement and Conditions of the Contract: Themust indicate, as part of the description of the work, whichby the owner. The contract sum must accurately reflect those decisions.
  • Specifications: Section 01 23 00—Alternates should identify each alternate and describe the changes of work included in each. The sectionsthat are affected by the alternates should contain a coordinating or clarifying statement calling attention to the provisions for alternates. Statements should be included in PART 1—GENERAL under the article “Summary.”
A

7.7 Specifying Alternates

Most master guide specifications and standard documents do not contain extensive provisions for alternates, as they are generally unique to each project. If alternates are to be used, special provisions must be incorporated in the documents to make them effective.

  • Procurement Requirements: The solicitation, such as the invitation for bids, should inform bidders or proposers of the request for alternate prices.

Solicitation instructions may contain guidance for preparing alternate bids or proposals and state considerations for evaluation and award of contract. Bid or proposal forms should clearly identify alternates with spaces for the respective prices.

  • Agreement and Conditions of the Contract: The executed agreement must indicate, as part of the description of the work, which alternates have been selected by the owner. The contract sum must accurately reflect those decisions.
  • Specifications: Section 01 23 00—Alternates should identify each alternate and describe the changes of work included in each. The sections in Divisions 02 through 49 that are affected by the alternates should contain a coordinating or clarifying statement calling attention to the provisions for alternates. Statements should be included in PART 1—GENERAL under the article “Summary.”
27
Q

7.8 Specifying Unit Prices

A

Whether a project is based on a stipulated sum contract with a few unit prices listed for minor variables or is based entirely on unit prices, the requirements and procedures for handling unit prices must be defined in the procurement documents. These requirements will involve the bid or proposal form along with carefully written Division 01 sections, both of which must be coordinated with the applicable sections in Divisions 02 through 49.

28
Q

7.8.1 Conditions of the Contract

Specified unit price requirements must be coordinated with statements in the conditions of the contract in order to avoid conflicts, duplication of information, or omission of essential requirements. Most standard general conditions address unit prices. Typically, these requirements.

A

7.8.1 Conditions of the Contract

Specified unit price requirements must be coordinated with statements in the conditions of the contract in order to avoid conflicts, duplication of information, or omission of essential requirements. Most standard general conditions address unit prices. Typically, these requirements need to be expanded in Division 01.

29
Q

7.8.2 Specifications

A

Section 01 27 00—Unit Prices is generally the place for establishing procedural requirements for unit prices. The section covers methods of determining actual quantities for both progress and final payments. The section must be coordinated with the general conditions, as it may either establish or expand upon the following requirements.

30
Q

13.5.2 Division 01—General Requirements

A

Division 01 specifications are as important for purchase projects as they are for construction projects. These sections should be used to expand the provisions of the general conditions and to provide general procedural requirements that will govern the other specification sections