Task Item No. 5-5: Incorporate project-specific requirements into Division 01 sections. Flashcards
You Should Understand
Task Item No. 5-5: Incorporate project-specific requirements into Division 01 sections.
- Edit Division 01 to incorporate and not duplicate information
- Understand dependencies and relations relative to commissioning
- Understand Owner’s training requirements, and protocols and procedures of training
- Understand project design requirements and parameters
- Understand and coordinate the many divisions of the Project Manual to eliminate conflict and redundancy:
- Division 01 and Division 00
- Division 01 and Divisions 02-49 (technical sections)
- Division 01 and the General Conditions/Owner Requirements
- Identify appropriate locations within Division 01 to expand on responsibilities defined in General Conditions
- Establish procedures assigned to parties to the Contract
1.8.3 Division 01—General Requirements
Division 01 contains sections that specify procedures affecting project quality. The following are several Division 01 sections that often include provisions for quality assurance or establish quality controls over the work:
- Regulatory Requirements. Identifies AHJs along with related codes and requirements.
- Project Management and Coordination. Describes various types of meetings to.
- Submittal Procedures. Includes such things as shop drawings, product data, and samples and
- . Includes subjects such as manufacturer qualifications, supplier qualifications, installer qualifications, and testing agency qualifications as well as field samples, mock-up requirements, and contractor’s quality control.
- . Includes subjects such as testing laboratory services, source and field testing, and inspection services.
- . Establishes procedures for proposing and evaluating substitutions during the bidding/negotiating/purchasing and construction periods without compromising quality.
- Commissioning. Identifies process and requirements for facility, system, and component operation testing and checkout.
1.8.3 Division 01—General Requirements
Division 01 contains sections that specify procedures affecting project quality. The following are several Division 01 sections that often include provisions for quality assurance or establish quality controls over the work:
- Regulatory Requirements. Identifies AHJs along with related codes and requirements.
- Project Management and Coordination. Describes various types of meetings to ensure and monitor quality through interaction of the participants.
- Submittal Procedures. Includes such things as shop drawings, product data, and samples and provide proactive quality assurance through mutual understanding of the design intent and the contract requirements
- Quality Assurance. Includes subjects such as manufacturer qualifications, supplier qualifications, installer qualifications, and testing agency qualifications as well as field samples, mock-up requirements, and contractor’s quality control.
- Quality Control. Includes subjects such as testing laboratory services, source and field testing, and inspection services.
- Substitution Procedures. Establishes procedures for proposing and evaluating substitutions during the bidding/negotiating/purchasing and construction periods without compromising quality.
- Commissioning. Identifies process and requirements for facility, system, and component operation testing and checkout.
7.1 Division 01—General Requirements
The sections in Division 01, which are collectively referred to as the General Requirements, specify,, , , and .
Division 01 sections expand on certain of the administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications. Administrative and procedural requirements unique to a specific section should be covered in the affected section. Division 01 sections cover general requirements for execution of the work and should be written in language broad enough to apply to sections in Divisions 02 through 49. Without Division 01, these requirements would otherwise be repeated throughout the specifications, and the possibility of conflicts and omissions would be increased.
7.1 Division 01—General Requirements
The sections in Division 01, which are collectively referred to as the General Requirements, specify administrative requirements, procedural requirements, temporary facilities and controls, performance requirements, and life cycle activities.
Division 01 sections expand on certain of the administrative and procedural provisions in the conditions of the contract and apply broadly to the execution of the work of all the other sections of the specifications. Administrative and procedural requirements unique to a specific section should be covered in the affected section. Division 01 sections cover general requirements for execution of the work and should be written in language broad enough to apply to sections in Divisions 02 through 49. Without Division 01, these requirements would otherwise be repeated throughout the specifications, and the possibility of conflicts and omissions would be increased.
7.2 Organizational Basis for Division 01
The administrative sections of Division 01 parallel the succession of titles in MasterFortmat® and the procedural sequence of PART 1, PART 2, and PART 3 in SectionFormat™ to lay out a consistent and logical organization of titles.
7.2.2 Division 01 and SectionFormat™
Division 01 specifiescommon to many specification sections and to the project as a whole. Most of these requirements are related to the of the project, and others govern products and execution requirements.
Sections aligning with:
Are:
1
PART 1—GENERAL
A
Summary
2
PART 2—PRODUCTS
B
Price and Payment Procedures
3
PART 3—EXECUTION
C
Execution and Closeout Requirements
D
Product Requirements
E
Life Cycle Activities
F
Quality Requirements
G
Performance Requirements
H
Temporary Facilities and Controls
I
Administrative Requirements
7.2.2 Division 01 and SectionFormat™
Division 01 specifies procedural requirements common to many specification sections and to the project as a whole. Most of these requirements are related to the administrative activities of the project, and others govern products and execution requirements.
1. PART 1—GENERAL
A Summary, B Price and Payment Procedures, I Administrative Requirements, F Quality Requirements, H Temporary Facilities and Controls
2. PART 2—PRODUCTS
D Product Requirements, G Performance Requirements
3. PART 3—EXECUTION
C Execution and Closeout Requirements, E Life Cycle Activities
7.3.1 Procurement Requirements
By definition in American Institute of Architects (AIA) and Engineers Joint Contract Documents Committee (EJCDC) general conditions, procurement requirements are not a part of the:
- Construction Documents
- Bidding Requirements
- Contract Documents
- All of the above
The procurement requirements should not repeat Division 01 provisions but should instead refer to the appropriatesections, by number and title, to direct the bidder to relevant information.
7.3.1 Procurement Requirements
By definition in American Institute of Architects (AIA) and Engineers Joint Contract Documents Committee (EJCDC) general conditions, procurement requirements are not a part of the:
- Construction Documents
- Bidding Requirements
- Contract Documents
- All of the above
The procurement requirements should not repeat Division 01 provisions but should instead refer to the appropriate 3 / Division 01 sections, by number and title, to direct the bidder to relevant information.
7.3.2 Owner-Contractor Agreement
The owner-contractor agreement includes by reference all other contract documents. Certain provisions of the owner-contractor agreement are supplemented by the provisions of Division 01 sections that define in greater detail the responsibilities of the parties to the contract.
7.3.3 General Conditions
Thegovern the execution of the work and apply broadly to sections of the specifications, including those in Division 01. As these topics are covered only in very broad terms, they must be specified in further detail in Division 01 to. Although the topics are addressed in two locations, the Construction Specifications Institute (CSI) principle of “say it once” is not violated because the requirements are stated in two different levels of detail, without duplication or conflict
7.3.3 General Conditions
The general conditions of the contract govern the execution of the work and apply broadly to sections of the specifications, including those in Division 01. As these topics are covered only in very broad terms, they must be specified in further detail in Division 01 to tailor requirements to a specific project. Although the topics are addressed in two locations, the Construction Specifications Institute (CSI) principle of “say it once” is not violated because the requirements are stated in two different levels of detail, without duplication or conflict
7.3.4 Supplementary Conditions
Supplementary conditions should not repeat information contained in the General Conditions or encroach on topics that belong more appropriately in Division 01. Proper coordination between Division 01 and supplementary conditions will avoid conflicts, omissions, and duplications.
Other than a statement establishing the authority of Division 01, the supplementary conditions should not contain general references to Division 01.
7.3.5 Other Specification Sections
Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01. Project requirements become more specific for each successive level of a three-tier hierarchy:
- Thestate provisions in broad terms.
- elaborate on the broad provisions of the conditions of the contract, but it is still written broadly enough to apply to the work of all specification sections.
- in a specification section becomes very specific in project requirements for that section only.
7.3.5 Other Specification Sections
Specification sections are subject to the administrative and procedural requirements of the conditions of the contract and of Division 01. Project requirements become more specific for each successive level of a three-tier hierarchy:
- The general conditions state provisions in broad terms.
- Division 01—General Requirements elaborate on the broad provisions of the conditions of the contract, but it is still written broadly enough to apply to the work of all specification sections.
- PART 1—GENERAL in a specification section becomes very specific in project requirements for that section only.
7.3.6 Drawings
Drawings graphically define certain Division 01 subject matter, such as the extent of work, and may define related work that may or may not be part of the contract.
Sections, such as those covering,, and, usually require extensive delineation on the drawings and close coordination between the drawings and Division 01.
7.3.6 Drawings
Drawings graphically define certain Division 01 subject matter, such as the extent of work, and may define related work that may or may not be part of the contract.
Sections, such as those covering use of the site, phased construction, and multiple prime contracts, usually require extensive delineation on the drawings and close coordination between the drawings and Division 01.
7.4.1 Coordination with Division 01—General Requirements
A number of articles in the general conditions are usually expanded in Division 01—General Requirements to accommodate specific administrative and procedural requirements of a project. General and supplementary conditions are written in a paragraph style, while Division 01 is written in the three-part SectionFormat™.
Proper use of Division 01 avoids mixing conditions of the contract with the administrative and procedural details of the specifications. Coordination is necessary between each section of Division 01 and the sections of Divisions 02 through 49, and among the sections of Division 01 that cover interrelated administrative and procedural requirements.
As many of the contractual relationships and responsibilities described in Division 01 sections for any project are required by the owner, the A/E should obtain instructions for preparing the affected sections. The A/E should establish the basic responsibilities of the team members for preparation of the Division 01 requirements and for overall coordination of the specifications. This involves close coordination of Division 01 provisions at an early stage in the production of the contract documents to avoid conflicts, duplication, and omissions in the project manual. The coordination effort should include:
Multiple sections within an individual division have administrative and procedural requirements unique to that division. However, the common requirements should be specified in.
7.4.1 Coordination with Division 01—General Requirements
A number of articles in the general conditions are usually expanded in Division 01—General Requirements to accommodate specific administrative and procedural requirements of a project. General and supplementary conditions are written in a paragraph style, while Division 01 is written in the three-part SectionFormat™.
Proper use of Division 01 avoids mixing conditions of the contract with the administrative and procedural details of the specifications. Coordination is necessary between each section of Division 01 and the sections of Divisions 02 through 49, and among the sections of Division 01 that cover interrelated administrative and procedural requirements.
As many of the contractual relationships and responsibilities described in Division 01 sections for any project are required by the owner, the A/E should obtain instructions for preparing the affected sections. The A/E should establish the basic responsibilities of the team members for preparation of the Division 01 requirements and for overall coordination of the specifications. This involves close coordination of Division 01 provisions at an early stage in the production of the contract documents to avoid conflicts, duplication, and omissions in the project manual. The coordination effort should include:
Multiple sections within an individual division have administrative and procedural requirements unique to that division. However, the common requirements should be specified in Division 01.
7.5 Commonly Used Division 01 Sections
See next cards
7.5.1 Section 01 10 00—Summary
- Section 01 11 00—: Use this section to describe the work if all of the work required by the project manual and drawings is to be accomplished under one contract.
- Section 01 12 00—: Use this section if the work described in the project manual and drawings is to be accomplished by more than one contract.
- Section 01 14 00—Work Restrictions: Specify owner requirements for or occupancy of existing buildings. Carefully define restrictions on, especially if the project area will be occupied during construction. Limit this section to restrictions on the contractor’s use of the premises
7.5.1 Section 01 10 00—Summary
- Section 01 11 00—Summary of Work: Use this section to describe the work if all of the work required by the project manual and drawings is to be accomplished under one contract.
- Section 01 12 00—Multiple Contract Summary: Use this section if the work described in the project manual and drawings is to be accomplished by more than one contract.
- Section 01 14 00—Work Restrictions: Specify owner requirements for early partial occupancy of new construction or occupancy of existing buildings. Carefully define restrictions on the contractor’s use of premises, especially if the project area will be occupied during construction. Limit this section to restrictions on the contractor’s use of the premises