Module 5 - Production Quiz Flashcards
A section is divided into three PARTs as defined in:
A. UniFormat™
B. OmniClass™
C. SectionFormat™
D. MasterFortmat®
C. SectionFormat™ [CSPG 4.2]
The major criteria for quality are described in the:
A. Specifications
B. Drawings
C. Resource drawings
D. Procurement Requirements
A. Specifications [CSPG 1.8.1]
Three articles that deal specifically with quality are:
A. Demonstration, related sections, manufactures
B. Administrative requirements, submittals, and quality assurance
C. Submittals, field quality control, warranty
D. Examination, references, finishes
B. Administrative requirements, submittals, and quality assurance [CSPG 1.8.4]

True or False: Division 01 sections are organized and written in the same outline style and three-part SectionFormat™ as sections in Division 02 through 49.
True [CSPG 7.4]
The final copy of the specifications should be distributed to each team member for:
A. Regulatory agency approvals
B. Funding approvals
C. Procurement purposes
D. Record document
E. All of the above
E. All of the above [CSPG 1.13.3]
The drawings illustrate:
A. Size
B. Form
C. Quantity
D. Relationship
E. All of the above
E. All of the above [CSPG 8.1]
True or False: The specifications describe administrative procedures regarding both drawings and specifications.
True [CSPG 8.1]
True or False: To save time in preparation, copies of previous project specifications should be edited for a new project.
False [CSPG 1.5.5]
When producing a project manual, tasks should generally be completed in a certain order. Please list these tasks in numerical order.

- Obtain and review the owner-A/E agreement
- Prepare Division 01 – General Requirements
- Prepare the project specifications
- Make decisions about materials, equipment, and methods
- Coordinate graphic and written construction documents [CSPG 1.10]

Addenda should be arranged in the same sequence as the project manual and drawings. Please list the basic components in the order they should appear.

- Addenda number and date of addendum
- Project identification
- Name and address of A/E
- To whom an addenda is issued
- Opening remarks and notice to bidders or proposers
- Changes prior to addenda
- Changes to procurement requirements
- Changes to contracting requirements
- Changes to specifications, in sequence, including approved substitutions [CSPG 9.3.4]
- Changes to drawings in sequence