Task Item No. 1-14: Coordinate project manual deliverables. Flashcards

1
Q

You Should Understand

Task Item No. 1-14: Coordinate project manual deliverables.

  • Understand the elements that make up a project manual and the documents that should be included and those that should not.
  • Understand the process of organizing, editing, reviewing, and revising the project manual including the establishment of the table of contents, and the reproduction and distribution of the manual.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

CSPG

5.5 Inclusion of Agreement in Project Manual

Even though, published by professional societies, other organizations, and agencies, will be utilized, the A/E should avoid including the by reference only.

A

5.5 Inclusion of Agreement in Project Manual

Even though standard agreement forms, published by professional societies, other organizations, and agencies, will be utilized, the A/E should avoid including the agreement by reference only.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

6.2 General Conditions

Theshould always be bound into the project manual, not simply included by reference, so that they are easily available during progress of the work.

A

6.2 General Conditions

The general conditions should always be bound into the project manual, not simply included by reference, so that they are easily available during progress of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

1.10 Producing a Project Manual

…preparation should begin early in the construction documents phase. The following tasks should be performed, generally in this order:

  1. ____________________________________
  2. ____________________________________
  3. ____________________________________
  4. ____________________________________
  5. ____________________________________
  6. ____________________________________
  7. ____________________________________
  8. ____________________________________
  9. ____________________________________
  10. ____________________________________
  11. ____________________________________
  12. ____________________________________
  13. ____________________________________
A

1.10 Producing a Project Manual

…preparation should begin early in the construction documents phase. The following tasks should be performed, generally in this order:

  1. Obtain and review the owner-A/E agreement
  2. Request information from the owner for the type of construction contract, insurance, and bonds.
  3. Review the proposed agreement between the owner and the contractor
  4. Review the proposed general conditions of the contract
  5. Prepare the supplementary conditions to modify the general conditions
  6. Prepare Division 01—General Requirements coordinated with the project requirements of the agreement and the conditions of the contract.
  7. Send the proposed conditions of the contract and Division 01 to the owner and consultants for review.
  8. Prepare the project specifications.
  9. Make decisions about materials, equipment, and methods
  10. Develop specifications or edit master guide sections.
  11. Prepare or assemble other written procurement documents
  12. Coordinate graphic and written construction documents
  13. After final review, reproduce the project manual for distribution
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

1.5.7 Section Title List

Once basic requirements for the project are known, a list of section titles is developed, along with the scope of work associated with each….. Such a list in its final form can become the for the project manual.

A

1.5.7 Section Title List

Once basic requirements for the project are known, a list of section titles is developed, along with the scope of work associated with each….. Such a list in its final form can become the table of contents for the project manual.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

1.9.1 Preparing the Specifications

Prepare afor the project manual by identifying the specification sections from Master-Format® that will be needed to cover the extent of the project

A

1.9.1 Preparing the Specifications

Prepare a preliminary table of contents for the project manual by identifying the specification sections from Master-Format® that will be needed to cover the extent of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

11.3.4 Practices

The documents commonly referred to as the specifications normally contain much more than that name implies. The procurement requirements, contracting forms, and conditions of the contract are usually included, but they are not specifications.

A

11.3.4 Practices

The documents commonly referred to as the specifications normally contain much more than that name implies. The procurement requirements, contracting forms, and conditions of the contract are usually included, but they are not specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly