Task Item No. 1-11 Coordinate the documents of the interdisciplinary team members. Flashcards
You Should Understand
Task Item No. 1-11 Coordinate the documents of the interdisciplinary team members.
- Develop a method for ensuring coordination between disciplines to insure avoidance of duplication, overlap, and inconsistencies.
- Understand how specifications and drawing interrelate, what should be located in each, and how the information should be displayed.
CSPG
1.5.8 Coordinating with Consultants
Theshould assume responsibility for overall coordination of the specifications. Information regarding the type of project, contract, , general conditions, and especiallyrequirements should be made available to consultants prior to their preparing any sections. Input from them forsections should be requested at the same time. In this manner the consultants can avoid writing separatefor their disciplines, reducing the likelihood of conflicting requirements.
1.5.8 Coordinating with Consultants
The prime A/E should assume responsibility for overall coordination of the specifications. Information regarding the type of project, contract, specifications formats, general conditions, and especially Division 01 requirements should be made available to consultants prior to their preparing any sections. Input from them for Division 01 sections should be requested at the same time. In this manner the consultants can avoid writing separate general requirements for their disciplines, reducing the likelihood of conflicting requirements.
7.4.1 Coordination with Division 01—General Requirements
The coordination effort should include:
- Distributing a draft ofto the contributors to the specifications early in project development
- Preparing of a list by the consultants and other contributors of,
, andandrequirements for specific sections or divisions
- Determining which of these requirements should be covered in and which are specific only to
- Noting requirements and and resolving
- Revising thedraft for review by specification contributors
7.4.1 Coordination with Division 01—General Requirements
The coordination effort should include:
- Distributing a draft of Division 01 to the contributors to the specifications early in project development
- Preparing of a list by the consultants and other contributors of administrative, procedural, and temporary facility and control requirements for specific sections or divisions
- Determining which of these requirements should be covered in Division 01 and which are specific only to Division 01
- Noting individual specification sections requirements and overlapping and omissions and resolving conflicts
- Revising the Division 01 draft for review by specification contributors
8.1 Drawings
Coordination must occur at all levels of the project team.must ensure that the drawings and specifications _are fully coordinated. Various consultants must also coordinate their graphic and written materials . The responsible A/E must not only coordinate the drawings and specifications , but also be responsible for coordinating the entire and for maintaining thethat will facilitate this coordination.
8.1 Drawings
Coordination must occur at all levels of the project team. Consultants must ensure that the drawings and specifications within their offices are fully coordinated. Various consultants must also coordinate their graphic and written materials among their respective offices. The responsible A/E must not only coordinate the drawings and specifications within the A/E’s own office, but also be responsible for coordinating the entire construction document package and for maintaining the communication process that will facilitate this coordination.
8.1.4 Coordination
To facilitate coordination, especially on complex projects with many different materials, components, subcontractors, and trades, adhere to the established for properly within the contract documents
8.1.4 Coordination
To facilitate coordination, especially on complex projects with many different materials, components, subcontractors, and trades, adhere to the CSI principles established for locating information properly within the contract documents
8.1.4.1 Preliminary Coordination
Construction documents are generally reviewed at such as and.
8.1.4.1 Preliminary Coordination
Construction documents are generally reviewed at set milestones such as 50 percent completion and 90 percent completion.
14.10.1 Review Comments
often require changes to the drawings or specifications to make the documents conform to specific government criteria…. Each of theinvolves a different reviewer
14.10.1 Review Comments
Agency reviewers often require changes to the drawings or specifications to make the documents conform to specific government criteria…. Each of the disciplines involves a different reviewer