Module 3 - Research Quiz Flashcards

1
Q

True or False: Under a single-prime contract, the owner has a contractual relationship with suppliers and subcontractors.

A

False [PDPG 5.6.1]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

True or False: There being no contractual relationship between the A/E and the contractor, there is also no contractual relationship between the A/E and the subcontractors and suppliers.

A

True [PDPG 5.6.1]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The contractual relationship governed by the conditions of the contract is between:

A. Owner and contractor

B. A/E and contractor

C. Owner and subcontractors

D. Owner, contractor, and A/E

A

A Owner and contractor [PDPG 11.5.4]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Lump sum, unit price, or cost-plus-fee constitutes the basis of:

A. Selection

B. Payment

C. Award

D. Contract

A

B Payment [PDPG 7.1.6]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The nationally recognized California AIA “Integrated Project Delivery Guide” redefines the stages of a project to include which of the following:

A. Conceptualization

B. Criteria design

C. Detailed design

D. Implementation documents

E. All of the above

A

E All of the above [PDPG 7.7.2]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

List six limitations of the design-bid-build project delivery method:

A

[PDPG 7.2.5]

  1. bid-day surprise
  2. adversarial …constantly seeking change orders
  3. cannot rely on the owner’s carrying a contingency
  4. a gamble when unknowns are not considered. – shortness of bid period
  5. makes everyone an individual competitor
  6. selected bidder also brings all of their subs (whether they are good or not)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the four principal types (business arrangements) of the design-build project delivery method?

A

[PDPG 7.5.2]

  1. Owner contracts with A/E who then contracts with Contractor
  2. A/E and Contractor Joint venture
  3. Owner contracts with Contractor who then contracts with A/E
  4. The DB company may be a single entity company
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

True or False: A limitation of the design-build project delivery method is that the owner is less involved in the project design, including for example material selection.

A

True [PDPG 7.5.5]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly