Condensate Transfer and Storage & Aux Feedwater Flashcards
What is design basis for Condensate Transfer & Storage system ?
-Initial fill for Condensate & FW system
-Help maintains level in Condenser hot wells
-Provide water for CD Demins for resin regeneration
-Backup water to Spent Fuel Pool
-Emergency makeup for EW,EW, & DG Jacket Water Surge Tanks
Why is the CST Tank reinforced with concrete ?
-Needs to meet seismic category 1 requirements to be functional during safe shutdown
-Protects against tornado borne missiles
What is 300,000 gallons of water dedicated to inside the CST Tank ?
-To use Aux. FW system and provide FW to maintain plant in hot standby for 8 hours
-Allows controlled plant cooldown at max rate of 75F/hr to shutdown cooling is initiated
What is the other 220,000 gallons dedicated for inside the CST Tank ?
-Dedicated to 3 days of normal makeup to Condensate & FW systems
-Used by Secondary Chemistry Control system without replenishment from DW
How are the penetrations into the CST Tank arranged ?
-Essential operations is everything below the 300,000 gallons
-Non-Essential has penetration above the 300,000gallons
What is the normal makeup to the CST ? How is it done ?
-DW is normal makeup and is normally done automatically based on CST lvl
-Makeup line has a bypass line that can be used when level control balance is isolated
What is the backup makeup water to the CST ? Why is this makeup water supply not normally used ?
-Recycled Monitor Tanks is backup makeup source to CST
-Not normally used because it can potentially be contaminated
What cover gas is used for the CST Tank ? How is regulated ?
-Nitrogen gas is used
-Regulated to 3.5 psig by a PCV
-Bypass line can be used when PCV is isolated
What’re the two breather valve used for?
-One breather valve is used pass nitrogen from atmosphere from failed open nitrogen supply line
-Other breather valve allows air into CST to prevent vacuum during Main Condenser Hotwell Makeup
What is the purpose for Tank Overflow & Loop Seal line ?
-Loop seal prevents nitrogen from leaking out
-Overflow is directed to north condenser sump
Why should the CST inventory not be <40F & >120F ?
-<40F precludes thermal shock to SGs
->120F is upper limit of design calculations
What is the primary supply line for the FLEX SG Makeup Pump ?
Pump draws from CST Drain Line
Where is the valve located that is used to align the FLEX SG Makeup Pumps used for ?
The valve to align is located in CST Drain Pit
What conditions must the CST Drain out be maintained in ?
CST Drain pit must be maintained locked by Operations & Security departments
What’re pre-requisites to placing CST in Normal Operation ?
-DW available
-LP Nitrogen is available
Where do the Condensate Transfer Pumps supply makeup water to ?
-DG Jacket Water Storage Tanks
-EC Surge Tanks
-EW Surge Tanks
-Spent Fuel Pool
Is there expected to be leakage from the Condensate Transfer Pumps ?
-Some leakage is expected both during operation & while secured
-Leakage will fall to pump skid and directed to floor drain
Where do the Condensate Transfer Pump recirc. lines discharge to ?
Recirc. lines will discharge back into CST from associated Train Aux FW Pump Recirc. Lines
Where are the Condensate Transfer Pumps powered from ?
Powered from class 480MCC (PH)
What ESFAS signals auto start the Condensate Transfer Pumps ?
-LOP (Train Specific)
-SIAS
-CREFAS
-CRVIAS
What do the CST Suction Isolation Valves to the ‘N’ Aux FW Pump do ?
Provides isolation for CST & Seismic break between Seismic Category 1 & Seismic Category 2 rated supply line
What conditions are the CST Suction Isolation Valves usually in ?
They’re normally closed
How are both of the CST Suction Isolation Valves interlocked with ‘N’ Aux Fw Pump ?
Provides low suction pressure protection
What position must the CST Suction Isolation Valves be in to start and run the pump ?
-Both valves must be >80% open
-If one valve drops below 80% open it will trip the ‘N ‘ Aux FW Pump
Where are the ‘N’ Aux FW Pump suction isolation valves powered from ?
They’re BOTH powered from ‘A’ train
Which condenser hotwell does CST provide makeup water for ?
‘A’ Main Condenser Hotwell Halves
What controls the makeup to the ‘A’ Main Condenser hotwell ?
Makeup is controlled by ‘C’ Main Condenser Hotwell half level
When is condensate rejected from the Main Condenser ?
High lvl in ‘C’ condenser will open Condenser Hotwell Draw Off Level Control Valve and return it to CST
What is the most common use of the CST system ?
-CST is used for Condensate Demins
What do the Regenerate Water Transfer Pumps in Secondary Chemistry control system used for ?
Transfers water from CST to Condensate Demins during regen process to:
-Trasnfer resin between vessels
-Rinse vessels after resin is transferred
-Dilute acid and concentration during chemical cleaning of cation resin
-Backwash resin
-Fill service vessel after transferring resin back into them
What’s status are the CST pumps during normal operation ?
-Condensate pump are normally in standby
-If makeup water is needed then Control Room can manually start it
How does Essential Lighting interface with CST ?
QB provides lighting for CST Pump House
How many CST gallons is designated for a controlled shutdown & cooldown ?
300,000 gallons designated to supply Essential Aux FW Pumps
What should CST level be ?
> 29.5 ft
What should CST have sufficient cooling for?
-Must have sufficient cooling to remove decay heat for 4hrs following reactor trip from 102%
-Then cooldown RCS for Shutdown Cooling entry conditions
Why must there be a volume of 300,000 gallons ?
This 300,000 gallons will hold unit in mode 3 for 8 hours followed by cooldown to SDC entry conditions at 75F per hour
What is the design basis for Aux. Feedwater system?
-Provide flow for RCS temp. during Normal startup, hot standby, & shutdown conditions
-Supports orderly ,controlled shutdown & cooldown of reactor
-Used to remove decay heat from RCS during Station Blackout
What are the UFSAR Design Bases ?
-RCS cooldown at max rate of 75F per hour to 350F during LOOP
-Hot standby for 8hours during LOOP
-RCS cooldown using SG following main steam line break,or Main FW Break inside containment during LOOP
When does ‘N’ Aux FW Pump deliver Feedwater to Steam Generator ?
-During normal startup, Hot Standby, & Shutdown conditions
-Also provides chemically treated water to SG for initial fill
How are the ‘N’ Aux FW motor & pump bearings lubricated ?
Bearings are self lubricated using slinger rings to throw oil on bearings
How are the ‘N’ Aux FW Pump motor bearings cooled ?
Motor bearings cooled by shaft mounted fan
How is the ‘N’ Aux FW Pump bearings cooled?
-Pump bearings cooled with discharge of pumps 1st stage through integral oil cooler
-After 1st stage cools bearings it’s then sent back to suction of pump