Part 8 Flashcards

1
Q
During a project, a key stakeholder asks a project team member to add a requirement. The team member adds the requirement without informing the project manager. Which of the following is described in this scenario?
 A
Change request
 B
Scope creep
 C
Change control
 D
Risk mitigation
A

B

Scope creep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

imagine 3

Which of the following calculations accurately shows the critical path?
 A
20 days
 B
39 days
 C
52 days
 D
49 days
A

C

52 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?
 A
Issue log
 B
Procurement report
 C
Post-mortem analysis
 D
Risk register
A

C

Post-mortem analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
A project team has purchased computers with warranties extending throughout the entire project. Which of the following represents the risk strategy utilized?
 A
Avoid
 B
Share
 C
Transfer
 D
Mitigate
A

D

Mitigate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?
 A
Scatter chart and scope analysis
 B
Issue log and process diagram
 C
Stakeholder analysis and communication plan
 D
Resource analysis and Gantt chart
A

D

Resource analysis and Gantt chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Choose two.)
A
The WBS is the best way to determine risks of the project.
B
Using the WBS will help prevent work from slipping or being forgotten.
C
TheWBS will aid in determining which resources are required for the project.
D
TheWBS will be required on very large projects.
E
TheWBS will be required if the project manager has the time available to complete it.

A

B
Using the WBS will help prevent work from slipping or being forgotten.
C
TheWBS will aid in determining which resources are required for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:
 A
Outsourcing
 B
Work relocation
 C
Staff Augmentation
 D
Resource leveling
A

A

Outsourcing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:
 A
process diagram.
 B
quality plan.
 C
project management plan.
 D
risk register.
A

B

quality plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A project is in the initiation phase. Which of the following tasks will take place during this phase?
 A
Acquire the project resources.
 B
Define the project requirements.
 C
Develop a WBS.
 D
Create a project charter.
A

D

Create a project charter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
Which of the following charts is a graphical representation of the causes of a specific event?
 A
Gantt
 B
Histogram
 C
Fishbone
 D
Scatter
A

C

Fishbone

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
A team member has completed an assigned task. Which of the following roles should be notified FIRST?
 A
Project sponsor
 B
Project team
 C
Key stakeholders
 D
Project manager
A

D

Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Which of the following shows projected project expenditures?
 A
Budget milestone
 B
Cash flow schedule
 C
Work breakdown structure
 D
Cash burn rate
A

C

Work breakdown structure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
A
Review the PERT chart and evaluate if the task is a critical dependency.
B
Review the PERT chart and evaluate if the task is an external dependency.
C
Review the PERT chart and evaluate if the task is a discretionary dependency.
D
Review the PERT chart and evaluate if the task is a real dependency.

A

C

Review the PERT chart and evaluate if the task is a discretionary dependency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which of the following elements should be included on a responsibility assignment matrix?
A
Responsible, accountable, consulted, informed
B
Resource, accountable, signoff, input
C
Responsible, accurate, confidential, informed
D
Resource, accountable, consulted, informed

A

A

Responsible, accountable, consulted, informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Using Scrum, which of the following are discussed in a daily standup meeting?
A
What was done yesterday, what is planned for today, and what deliverables were completed
B
What was done yesterday, what is planned for this week, and what items from the backlog are priority
C
What was done yesterday, what is planned for the week, and what issues were resolved
D
What was done yesterday, what is planned for today, and what roadblocks need to be removed

A

D

What was done yesterday, what is planned for today, and what roadblocks need to be removed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
 A
MOU
 B
SLA
 C
SOW
 D
MOA
A

D

MOA

17
Q
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?
 A
Zero
 B
One
 C
Three
 D
Two
A

C

Three

18
Q
Which of the following documents need to be updated as events occur during a project? (Choose two.)
 A
Risk register
 B
Change request
 C
Meeting minutes
 D
Issue log
 E
Status report
A

C
Meeting minutes

E
Status report

19
Q
Which of the following job roles is primarily tasked with communicating the project timeline changes?
 A
Project manager
 B
Project coordinator
 C
Project sponsor
 D
Project scheduler
A

A

Project manager

20
Q
Which of the following vendor documents specifically address quality? (Choose two.)
 A
PO
 B
SLA
 C
NDA
 D
LOI
 E
Warranty
A

B
SLA

D
LOI

21
Q
A software upgrade project has been postponed because it may impact a critical business system. Which of the following strategies has been applied?
 A
Accept risk
 B
Avoid risk
 C
Exploit risk
 D
Mitigate risk
A

B

Avoid risk

22
Q

A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:

Coordinate project schedule
Manage to the triple constraint
Provide performance feedback to team members’ managers

Which of the following types of organizational structures did the new project manager MOST likely join?
 A
Strong matrix
 B
Balanced matrix
 C
Projectized
 D
Functional
A

C

Projectized

23
Q
A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?
 A
Time zones
 B
Cultural differences
 C
Personal preferences
 D
Language barriers
A

B

Cultural differences

24
Q
A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?
 A
Project schedule
 B
Project charter
 C
Action items
 D
Communication plan
A

A

Project schedule

25
Q

Which of the following are characteristics of a project? (Choose two.)
A
A project provides a unique product, service, or result.
B
A project is an ongoing endeavor.
C
A project involves scheduled maintenance.
D
A project includes life-cycle cost management.
E
A project is a temporary endeavor.

A

A
A project provides a unique product, service, or result.

E
A project is a temporary endeavor.