Part 10 Flashcards

1
Q
A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?
 A
Decrease staff
 B
Update the WBS
 C
Increase the budget
 D
Reduce the scope
A

B

Update the WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:
A
notify the legal department representative in the event of an upcoming audit.
B
follow the change process flow and notify the legal department after the change is implemented.
C
extend a formal invitation to the legal department representative to join the CCB.
D
hold a separate meeting with the legal department representative and ask for approval.

A

C

extend a formal invitation to the legal department representative to join the CCB.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
 A
Additional resources
 B
A performance audit
 C
A risk register update
 D
A gate review
A

C

A risk register update

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?
 A
MOU
 B
SLA
 C
PO
 D
SOW
A

D

SOW

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A customer has requested additional features for an active project.

Which of the following steps should take place NEXT?
 A
Submit the requested changes to the CCB.
 B
Evaluate the impact of the changes.
 C
Update all project documents.
 D
Implement the requested changes.
A

B

Evaluate the impact of the changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.

Which of the following is the MOST likely reason?
 A
Established communication plan
 B
Iterative approach
 C
Resource constraints
 D
Scope creep
A

D

Scope creep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
Which of the following project documents should be used to record the occurrence of an unplanned event?
 A
Issue log
 B
Action log
 C
Risk log
 D
Change log
A

A

Issue log

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which of the following describes how a project is related to a program?
A
A program is a part of a project.
B
A program is a combination of multiple projects.
C
A program contains an element of the project.
D
A program uses half of the project’s budget.

A

B

A program is a combination of multiple projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.

Which of the following is a necessary step to record the actual durations?
 A
Establish the tollgates.
 B
Establish and set the quality gates.
 C
Establish and set the baseline.
 D
Establish each WBS work package resource.
A

C

Establish and set the baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which of the following describes risk mitigation?
A
The weighting or prioritization of the risk against all other identified risks within this project or others associated with it.
B
The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
C
The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
D
The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.

A

B
The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor’s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?
A
During the project team’s regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
B
The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
C
During the planning phase, the project manager should have recognized the relationship between the vendor’s and project team’s tasks and adjusted the schedule for the project team to begin activities two months later.
D
During the project team’s regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.

A

B
The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
A company is hired to perform some of another organization’s work. Which of the following types of organizational change is described?
 A
Shared resources
 B
Business process change
 C
Outsourcing
 D
Split
A

C

Outsourcing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
Which of the following are examples of organizational change? (Choose two.)
 A
Scope
 B
Business process
 C
Risk event
 D
Relocation
 E
Schedule
A

B
Business process

D
Relocation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.

Which of the following should the project manager do to resolve this issue?
 A
Implement change control management.
 B
Inform the stakeholders of the issue.
 C
Modify the project baselines.
 D
Update the scope management plan.
A

B

Inform the stakeholders of the issue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?
 A
Sales clerk
 B
Product item
 C
Team lead
 D
Marketing representative
A

D

Marketing representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
 A
Business continuity response
 B
Quality audit
 C
Completion of a task
 D
Replacement of a subcontractor
A

A

Business continuity response

17
Q

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?
A
Give approval for the change requested by the project sponsor.
B
Document the change request from the project sponsor.
C
Deny the request from the project sponsor.
D
Ask the project sponsor to change the request.

A

B

Document the change request from the project sponsor.

18
Q

During the execution phase of a project, a project task has run longer than anticipated.

image 4

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
 A
16 days
 B
14 days
 C
19 days
 D
12 days
A

D

12 days

19
Q
In which of the following organizational structures would a project manager have the MOST authority?
 A
Functional
 B
Projectized
 C
Strong matrix
 D
Balanced matrix
A

B

Projectized

20
Q
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called:
 A
an MOU.
 B
an SLA.
 C
an NDA.
 D
an RFP.
A

C

an NDA.

21
Q

A senior manager asks a project manager for an estimated budget on a new project.

Which of the following is the BEST step for the project manager to take?
A
Tell the senior manager the estimation is not available yet.
B
Gather the team to immediately generate estimates.
C
Ask a SME for an opinion and propose an estimate.
D
Use the budget from a similar project to generate estimates.

A

D

Use the budget from a similar project to generate estimates.

22
Q

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?
 A
Project statement of work
 B
Project schedule
 C
Project charter
 D
Project management plan
A

A

Project statement of work

23
Q

A vendor is unable to deliver an order by the specified date.

Which of the following should be the project manager’s NEXT steps? (Choose two.)
A
The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B
The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
C
The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
D
The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
E
The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.

A

A
The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B
The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.

24
Q

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.

Which of the following factors will MOST likely influence the communication methods used in the project?
 A
Cultural differences
 B
Personal preferences
 C
Technological factors
 D
Language barriers
A

C

Technological factors

25
Q

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.

Which of the following techniques is the project manager using?
 A
Compromising
 B
Smoothing
 C
Accepting
 D
Withdrawing
A

D

Withdrawing