A project manager needs status on the project timeline.
Which of the following team members should provide an update? A Sponsor B Product owner C Scheduler D Business analyst
C
Scheduler
Which of the following conflict resolution techniques relies on establishing areas of agreement rather than disagreement? A Compromising B Smoothing C Avoiding D Collaborating
B
Smoothing
Tasks B and D start after Task A is completed. Task C starts after Tasks B and D are completed. task E starts after Task D is completed. Task H starts after task B is completed. Task G starts after Tasks C and H are completed. Task F starts after Task E is completed.
Following are the durations of all tasks: Task Duration A Four weeks B Two weeks C Six Weeks D Three Weeks E Seven Weeks F One Weeks G Two Weeks H Nine Weeks
Which of the following tasks are on the critical path? A A, B, C, G B A, D, E, F C A, D, C, G D A, B, H, G
D
A, B, H, G
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
Project title description Preassigned resources Budget WBS Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter? A Budget B Measurable project objectives C Preassigned resources D WBS E Project title and description
D
WBS
A team member has completed a project task. Which of the following is the FASTEST method to communicate the task completion? A Team meeting B Social media C Email D Instant messaging
C
A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT? A Implement the risk response plan B Conduct an immediate emergency team meeting C Refer to the contingency plan D Perform a SWOT analysis
C
Refer to the contingency plan
Which of the following features describe a projectized organization? (Choose two.)
A
The project manager has less authority over the project team than in a strong matrix.
B
Team members are solely dedicated to project activities.
C
Team members from various departments are assigned to the project.
D
The project manager has full authority over the project team members.
E
The functional manager has full authority over the project team members.
B
Team members are solely dedicated to project activities.
D
The project manager has full authority over the project team members.
A Chief Executive Officer (CEO) has approached a project team member to request a project change.
Which of the following would be the BEST step for the project manager to take to prevent scope creep? A Ask the CEO to follow the communications plan. B Submit the request to the CCB. C Implement the project change. D Deny the CEO’s request.
B
Submit the request to the CCB.
Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.) A Earned value B Planned value C Schedule variance D Cost variance E Acceptable variance
A
Earned value
D
Cost variance
A project sponsor, project manager, and project facilitator are drafting a project charter. The final contents of this documentation will be presented to the project steering committee for review and approval. The following sections are currently documented:
Project description Draft project timeline and schedule Rough milestones Draft project budget Draft resources required High-level risk review
Which of the following sections should be included in this document? A Full resource requirements B Full risk assessment results C Draft work breakdown structure D Business information
C
Draft work breakdown structure
A new contractor joining the project team is an example of: A outsourcing B offshoring C rightsizing D offboarding
A
outsourcing
A resource is assigned to two projects with two scheduled tasks that complete at the same time.
This is known as: A dedicated resource contention B interproject resource contention C intraproject resource contention D shared resource contention
B
interproject resource contention
Communication on a project is flowing well. Team members are motivated, and they are allowed to make decisions about their work.
Which of the following management styles is the project manager MOST likely using? A Authoritative B Retrospective C Exploitive D Participative
D
Participative
Under an Agile methodology, standup meetings occur: A twice daily B daily C ad hoc D weekly
B
daily
Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data? A Project schedule B Pie chart C Run chart D Dashboard information
D
Dashboard information