Part 18 Flashcards
Which of the following includes setting governance gates as well as predecessors and dependencies? A Project communication B Project scheduling C Project change control D Project constraints
D
Project constraints
A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?
A
Determine the impact of the requested change.
B
Submit a change request to the CCB.
C
Implement the change to the project.
D
Update the schedule to accommodate the change.
A
Determine the impact of the requested change.
Which of the following are major characteristics of sprint planning? (Choose two.) A Defining the sprint parameters B Defining the number of sprints C Defining the sprint classifications D Defining the sprint durations E Defining the sprint owners
A
Defining the sprint parameters
D
Defining the sprint durations
A project manager detects low performance from a team member who previously demonstrated to be a highly skilled asset. The team member explains that being part of two teams is too time consuming. This is a disadvantage of having: A interproject dependencies. B resource overallocation. C shared resources. D dedicated resources.
C
shared resources.
A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company’s technological improvement goals, are identified. Which of the following BEST describes these projects? A Deliverable B Program C Portfolio D Outcome
B
Program
Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project? A WBS codes B Bill of materials C Cost baseline D PO numbers
A
WBS codes
A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core idea and now extra work may need to be performed. Which of the following approaches would BEST support on-time delivery considering these changes? A Strict change management controls B Regular milestone reviews C Regular Scrum meetings D Continuous requirements gathering
A
Strict change management controls
A member of a CCB notices a change request was not approved by the steering committee. Which of the following is the BEST method to handle this situation? A Disapprove the change request. B Develop a regression plan. C Evaluate the impact of the change. D Hold the change request for review
C
Evaluate the impact of the change.
Which of the following organizational structures uses project team members who are selected from within their department? A Strong matrix B Balanced matrix C Projectized D Functional
D
Functional
An audit, project change, task initiation/completion, gate review, and incident response are examples of: A risk events. B status reporting. C communication triggers. D change control.
C
communication triggers.
A project manager was reprimanded for failing to complete timely status reports and providing mixed messaging about a project’s performance.
Which of the following would be responsible for discussing and resolving this issue? A Project sponsor B Project stakeholder C Project coordinator D Project management office
D
Project management office
The Chief Executive Officer (CEO) of a company announced that a demerger operation will be completed in the next nine months. Which of the following BEST describes the organizational change? A Business reorganization B Business split C Business acquisition D Business relocation
B
Business split
Which of the following events would MOST likely merit immediate communication to all project stakeholders? (Choose two.) A Milestone achievement B Stakeholder changes C Incident response D Change request E Business continuity response F Schedule change
A
Milestone achievement
E
Business continuity response
When developing a project schedule, which of the following resources is the BEST to estimate task duration? A Project scheduler B Project sponsor C Project manager D Project team
A
Project scheduler
The government wants to start a project that will launch a satellite but lacks the appropriate SMEs. Which of the following would be BEST to solicit vendors? A RFQ B SOW C RFI D LOI
C
RFI