Part 13 Flashcards
A customer-requested change has been denied by the CCB.
Which of the following should the project manager do NEXT?
A
Report the denied request to the customer and proceed with project work.
B
Reestablish the project baselines.
C
Update the project issues log.
D
Halt project work until a meeting with the customer and the project sponsor takes place.
A
Report the denied request to the customer and proceed with project work.
Objectives and tasks are equally assigned by two different managers.
Which of the following BEST describes this organization type? A Functional B RACI C Projectized D Matrix
B
RACI
On larger projects, a vendor may occasionally proceed upon receipt of the: A NDA. B LOI. C RFI. D ROE.
B
LOI.
Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned.
Which of the following risk strategies was used? A Transfer B Avoid C Mitigate D Accept
D
Accept
A project manager has requested the procurement department collect detailed solutions with cost estimates from qualified third-party vendors.
This is an example of an: A RFP B MOA C RFQ D MOU E RFI
C
RFQ
Because of space limitations, there has been a long history of contention among the team.
Which of the following actions can the project manager take that would MOST contribute to a successful project? A Hold an open dialogue to build consensus. B Ignore the issue. C Require staff to focus on deliverables. D Replace team members.
A
Hold an open dialogue to build consensus.
A project team has just implemented an approved change to a project.
Which of the following should occur NEXT? A Update the issue log. B Implement a regression plan. C Evaluate the impact of the change. D Validate the change.
C
Evaluate the impact of the change.
Near the end of a sprint, the IT systems were taken down for a critical patch, and the team was inactive for four hours. The team members are concerned they will not be able to complete their tasks before the end of the sprint.
Which of the following BEST describes how the Scrum master should assist the team to finish on time?
A
Add the uncompleted work to the product backlog.
B
Bring the additional resources to help complete the work.
C
Inform the team members they will need to work longer hours.
D
Move the work to the next sprint.
B
Bring the additional resources to help complete the work.
A vendor developed a new payroll system for a local transit authority. Due to the system’s complexity, the vendor will need to work with the transit authority for three months after system implementation.
This will be documented in the: A SLA. B warranty. C WBS. D training plan.
A
SLA.
Which of the following normally would be completed prior to a vendor responding to an RFP? A Contract B SLA C PO D NDA
D
NDA
A project manager has gathered time estimates for a new project’s activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT? A Determine the critical path. B Prioritize tasks. C Create a WBS. D Determine predecessors and dependencies.
C
Create a WBS.
A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires.
Which of the following is the BEST change control process to follow?
A
Identify, evaluate, approve, implement, validate, update, communicate
B
Identify, approve, evaluate, implement, validate, update, communicate
C
Identify, validate, evaluate, approve, implement, update, communicate
D
Identify, implement, approve, evaluate, validate, update, communicate
A
Identify, evaluate, approve, implement, validate, update, communicate
A project manager needs to determine resource availability to assign the resources to project tasks.
Which of the following will the project manager MOST likely use? A Staffing management plan B Project calendar C Conflict resolution D Resource calendars
C
Conflict resolution
Which of the following would MOST likely be considered a project? A Remodeling a house B Picking and shipping a warehouse order C Troubleshooting a company-wide network issue D Performing scheduled maintenance
A
Remodeling a house
A project manager receives an initial project assignment.
Which of the following documents is MOST likely to indicate the organizational structure for the project? A Business case B Organizational breakdown structure C Communication management plan D Baseline
A
Business case