Q
A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:
 A
RFP
 B
RFI
 C
RTM
 D
RFQ
A

B

RFI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
Company A and Company B have come together to form a new Company C. Staff members from both companies have been moved to Company C, and there are rumors that some staff might be asked to leave. These are examples of: (Choose two.)
 A
business relocation
 B
business outsourcing
 C
business reorganization
 D
business merger
 E
business process change
A

C
business reorganization
D
business merger

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
 A
risk impact
 B
risk trigger
 C
risk owner
 D
risk review
A

B

risk trigger

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes. Which of the following BEST describes how the project manager should respond?
A
Ask a project team member to make the changes
B
Quickly make the changes
C
Take the request to the CCB
D
Inform the sponsor of the stakeholder’s request

A

A

Ask a project team member to make the changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
An organization is divided into three separate entities based on geographical region. Which of the following types of organizational change is this?
 A
Relocation
 B
Split
 C
Outsourcing
 D
Demerger
A

B

Split

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
A small company has a successful proof of concept for an innovative new service but lacks the necessary expertise to deploy it. Which of the following is the BEST course of action to address this deficiency?
 A
Internal reorganization
 B
Business process change
 C
Business merger/acquisition
 D
Outsourcing
A

D

Outsourcing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A busy project manager has a diverse set of stakeholders and team members with respect to age and cultural background. Which of the following is the BEST method for communicating to the project manager’s audiences?
A
Determine a single best communication method to provide efficient and consistent communications to all the audiences
B
Utilize a variety of communication methods, such as email, IM, conference calls, and face-to-face meetings, to reach all the audiences
C
Speak with each individual, and communicate with that individual according to stated and demonstrated preferences
D
Develop a communications plan that considers the individual’s impact on the project and preferred communication method

A

D

Develop a communications plan that considers the individual’s impact on the project and preferred communication method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

pic 12

Which of the following is the NEXT appropriate step for the project manager to take?
A
Update the issue log
B
Consult the risk management plan
C
Change the risk status to closed for 2 and 6
D
Identify risk strategies for the realized events

A

D

Identify risk strategies for the realized events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
A project manager is implementing a new edition of a magazine with an end-of-the-week deadline. The design analyst notices two main articles were not included, as requested by the client. Which of the following constraints should be considered FIRST?
 A
Budget
 B
Scope
 C
Quality
 D
Time
A

D

Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
A project manager has set aside a contingency reserve for unforeseen communications. Which of the following types of communication is MOST likely to utilize this contingency reserve?
 A
Closure conference
 B
Distributed printed media
 C
Kickoff meeting
 D
Impromptu meeting
A

D

Impromptu meeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

A project manager creates a Pareto chart based on the table below:

pic 13

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?
A
To take corrective action and identify the effects resulting in the highest number of issues
B
To take corrective action and identify the causes resulting in the highest number of issues
C
To take preventive action and identify and frequencies resulting in the highest number of issues
D
To take preventive action and identify the causes resulting in the highest number of issues

A

D

To take preventive action and identify the causes resulting in the highest number of issues

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
 A
December 18
 B
December 22
 C
December 21
 D
December 20
 E
December 19
A

A

December 18

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
A financial audit is being performed on a closed project. Which of the following should be communicated with FIRST?
 A
Stakeholders
 B
Project management office
 C
Quality control
 D
Functional managers
A

B

Project management office

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?
 A
Business continuity response
 B
Schedule response
 C
Resource change response
 D
Incident response
A

A

Business continuity response

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
When a project team member completes a task in the WBS, which of the following are the primary recipients of the notification? (Choose two.)
 A
Human resources
 B
Key stakeholder
 C
Project scheduler
 D
Project manager
 E
Project sponsor
 F
Project management office
A

C
Project scheduler
D
Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?
 A
Status
 B
Impromptu
 C
Kickoff
 D
Closure
A

A

Status

17
Q
An engineer is troubleshooting a malfunctioning physical deliverable and requires assistance from remote team members. Which of the following would be the BEST communication method for the engineer to use?
 A
Face-to-face meeting
 B
Video conference
 C
Phone conversation
 D
Instant messaging
A

B

Video conference

18
Q

Language barriers will MOST likely influence a PM to:
A
hire a bilingual project team that is fluent in the language to reduce conflict.
B
hire an interpreter to ensure verbal and written communications are accurate.
C
use more print media to communicate with the stakeholders.
D
learn the unknown language to be able to communicate effectively with stakeholders.

A

A

hire a bilingual project team that is fluent in the language to reduce conflict.

19
Q
A project manager is not going to finish a project on time but cannot change the deadline or add more budget. Which of the following types of change would allow the project manager to finish the project successfully?
 A
Communication
 B
Organization
 C
Resources
 D
Quality
A

D

Quality

20
Q
A stakeholder wants to add four more data entry points on the accounts receivable screen of the current application being developed. Which of the following constraints would this impact directly?
 A
Environment
 B
Quality
 C
Risks
 D
Scope
A

D

Scope

21
Q
Two parties are beginning conversations regarding the purchase of professional services. Which of the following should be in place FIRST?
 A
NDA
 B
LOI
 C
RFP
 D
SOW
A

C

RFP

22
Q
A project manager is collecting the number of hours, the resources, and the amount of money spent on hardware and software. Which of the following is MOST likely the purpose of collecting this information?
 A
Competitive advantage
 B
Budget constraints
 C
Expenditure tracking
 D
Financial stability
A

C

Expenditure tracking

23
Q
A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder’s expectations?
 A
Review previous meeting minutes.
 B
Analyze the RASI chart
 C
Initiate a change control request.
 D
Updates the communications plan.
A

B

Analyze the RASI chart

24
Q
Many questions have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this information?
 A
CCB meeting
 B
Kickoff meeting
 C
Status report
 D
Company-wide email
A

B

Kickoff meeting

25
Q
Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?
 A
Funding
 B
Requirements
 C
Resources
 D
Scope
A

A

Funding